Guodian Shangqiu Minquan power station

From Global Energy Monitor

Guodian Shangqiu Minquan power station (国电商丘民权发电厂) is a 1,260-megawatt (MW) coal-fired power plant in Henan Province, China.

An additional 2,000 MW has been proposed.

Location

The photo below shows the plant east of Minquan, Shangqiu City, Shangqiu Prefecture, the approximate location of the plant in Henan Province.

Loading map...

Background on Plant

The two existing coal-fired units of Guodian Shangqiu Minquan power station, totaling 1,260 MW, were brought online in 2008. The plant was originally owned by China Guodian.[1]

Expansion

Guodian is currently planning to build two additional coal-fired units at this plant, with a total planned capacity of 2,000 MW.[2]

However, with no updates since 2012, plans for the units appear to be abandoned.

Ownership

On August 28, 2017, China's State-owned Assets Supervision and Administration Commission of the State Council (SASAC) announced that China Guodian Corporation and Shenhua Group will be jointly restructured. Shenhua Group will become China National Energy Investment Group and will absorb China Guodian Corporation. It will be the largest power company in the world by installed capacity, as well as the world's largest coal producer.[3][4] The merger was completed on November 28, 2017.[5]

Plant Details for Existing Units 1 & 2

  • Sponsor: China Guodian Corp
  • Parent company: National Energy Investment Group)
  • Location: Minquan, Shangqiu City, Shangqiu Prefecture, Henan Province, China
  • Coordinates: 34.6194266, 115.2920508 (exact)
  • Status: Operating
  • Gross capacity: 1,260 MW (Units 1 & 2: 630 MW)
  • Type: Supercritical
  • In service: 2008
  • Coal type:
  • Coal source:
  • Source of financing:

Project Details for Units 3 & 4 Expansion

  • Sponsor: Guodian Henan Power
  • Parent company: Guodian (now National Energy Investment Group)
  • Location: Minquan, Shangqiu City, Shangqiu Prefecture, Henan Province, China
  • Coordinates: 34.6194266, 115.2920508 (exact)
  • Status: Cancelled
  • Gross capacity: 2,000 MW (Units 3 & 4: 1,000 MW)
  • Type: Supercritical
  • Projected in service:
  • Coal type: Bituminous
  • Coal source:
  • Source of financing:

Articles and resources

References

  1. "国电民权发电有限公司", 中国国电集团公司, 2009-12-30
  2. "国电民权发电有限公司二期2×1000MW机组初可报告评估会在郑州举行", 中国中小企业民权网, 2012-12-30
  3. "Factbox: Shenhua and Guodian - China's latest state marriage". Reuters. 29 August 2017. Retrieved 30 August 2017.
  4. "China Is Creating the World's Largest Power Company". Bloomberg News. 28 August 2017. Retrieved 29 August 2017.
  5. "China’s Newly-Established National Energy Investment Group Sets World Records in Its Sector, With Assets of Over CNY1.8 Trillion," Yicai Global, 11-28-2017

Related SourceWatch articles