Guoxin Jingjiang power station (江苏国信靖江发电厂) is an operating power station of at least 1320-megawatts (MW) in Xieqiao, Jingjiang, Taizhou, Jiangsu, China with multiple units, some of which are not currently operating. It is also known as 江苏国信靖江发电有限公司一期项目; Jiangsu Guoxin Jingjiang power station (Unit 1, Unit 2), 江苏国信靖江发电有限公司二期项目 (Unit 3, Unit 4), Yancheng Binhai Port power station.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Guoxin Jingjiang power station Xieqiao, Jingjiang, Taizhou, Jiangsu, China 32.030487, 120.383144 (exact)

The map below shows the exact location of the power station.

Loading map...


Unit-level coordinates (WGS 84):

  • Unit 1, Unit 2, Unit 3, Unit 4: 32.030487, 120.383144

Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology Start year Retired year
Unit 1 operating coal - bituminous 660 ultra-supercritical 2013
Unit 2 operating coal - bituminous 660 ultra-supercritical 2014
Unit 3 permitted coal - bituminous 1000 ultra-supercritical
Unit 4 permitted coal - bituminous 1000 ultra-supercritical

Table 3: Unit-level ownership and operator details

Unit name Owner
Unit 1 Jiangsu Guoxin Jingjiang Power Generation Co Ltd [100.0%]
Unit 2 Jiangsu Guoxin Jingjiang Power Generation Co Ltd [100.0%]
Unit 3 Jiangsu Guoxin Jingjiang Power Generation Co Ltd [100.0%]
Unit 4 Jiangsu Guoxin Jingjiang Power Generation Co Ltd [100.0%]

Project-level coal details

  • Permit(s): June 30, 2023, 2015

Background on Project

Guoxin Jingjiang power station is a two-unit coal-fired power plant with a total capacity of 1,320 MW in Jiangsu Province. Units 1 and 2 began operating in 2013 and 2014, respectively. The plant is owned by Jiangsu Guoxin Investment Group (55%), Shanxi Coal Import & Export Group (35%), and Jiangsu Huajing Asset Management (10%).[1][2]

As of January 2023, an additional two 1,000 MW coal units were proposed.[3] The project's environmental impact assessment was also prepared.[4]

In May 2023, China Energy Construction Jiangsu Institute won the bid for survey and design of Units 3 and 4.[5]

In June 2023, the power station was approved by the Jiangsu Provincial Development and Reform Commission.[6] The power station would soon enter construction preparation.[7]

The project launching ceremony was held on 8 August 2023.[8][9]

Articles and Resources

References

  1. "江苏国信靖江发电有限公司1号机组顺利通过168满负荷试运行", 江苏省国信资产管理集团有限公司, 2013-12-30
  2. "国信靖江发电有限公司2号机组顺利通过168小时满负荷试运行", 江苏省国信资产管理集团有限公司, 2014-03-31
  3. "关于“先立后改”煤电支撑性电源项目(第二批)规划建设实施方案的公示," Jiangsu, 2023-01-11
  4. "江苏国信靖江二期2×1000MW高效清洁燃煤发电扩建项目," news.bjx.com, 2023-04-13
  5. "2×1000MW!中国能建江苏院中标江苏国信靖江二期高效清洁燃煤发电扩建项目," news.bjx.com, 2023-05-12
  6. "国信靖江2×100万千瓦机组扩建项目获得核准!," news.bjx.com, 2023-07-04
  7. "国信靖江百万千瓦机组扩建项目喜获核准," jsgzw.jiangsu.gov, 2023-07-07
  8. 江苏省国信集团 (2023-08-10). "国信靖江2×100万千瓦机组扩建项目正式启动". 北极星火力发电网. Retrieved 2023-9-4. {{cite web}}: Check date values in: |access-date= (help)CS1 maint: url-status (link)
  9. "国信靖江2×1000MW煤电扩建项目正式启动". 电力项目圈. 2023-08-10. Retrieved 2023-9-4. {{cite web}}: Check date values in: |access-date= (help)CS1 maint: url-status (link)