Guyang Jinshan Cogen power station
| Part of the Global Coal Plant Tracker, a Global Energy Monitor project. |
| Related coal trackers: |
Guyang Jinshan Cogen power station (蒙能包头固阳金山热电厂) is an operating power station of at least 700-megawatts (MW) in Jinshan, Guyang, Baotou, Inner Mongolia, China. It is also known as 新恒丰热电 (Unit 1), 包头市新恒丰能源公司 (Unit 2).
Location
Table 1: Project-level location details
| Plant name | Location | Coordinates (WGS 84) |
|---|---|---|
| Guyang Jinshan Cogen power station | Jinshan, Guyang, Baotou, Inner Mongolia, China | 40.963132, 110.086384 (exact) |
Unit-level coordinates (WGS 84):
- Unit 1, Unit 2: 40.963132, 110.086384
Project Details
Table 2: Unit-level details
| Unit name | Status | Fuel(s) | Capacity (MW) | Technology | CHP | Start year | Emergency/Backup |
|---|---|---|---|---|---|---|---|
| Unit 1 | Operating | coal: unknown[1] | 350 | supercritical | yes | 2019 | False |
| Unit 2 | Operating | coal: unknown[1] | 350 | supercritical | yes | 2019 | False |
Table 3: Unit-level ownership and operator details
| Unit name | Owner | Parent |
|---|---|---|
| Unit 1 | Baotou Power Generation Branch of Inner Mongolia Energy Power Generation Investment Group Co Ltd [100%] | Inner Mongolia Energy Power Generation Investment Group Co Ltd [90.0%]; Inner Mongolia State Owned Capital Operation Co Ltd [10.0%] |
| Unit 2 | Baotou Power Generation Branch of Inner Mongolia Energy Power Generation Investment Group Co Ltd [100%] | Inner Mongolia Energy Power Generation Investment Group Co Ltd [90.0%]; Inner Mongolia State Owned Capital Operation Co Ltd [10.0%] |
Project-level captive use details
- Captive industry use (heat or power): both
- Captive industry: Aluminum
- Non-industry use: both
Project-level coal details
- Coal source(s): domestic
Ownership Tree
This ownership tree is part of the Global Energy Ownership Tracker, a project of Global Energy Monitor.
Background on Project
Inner Mongolia Energy Generation & Investment Group is seeking approval for a 2 x 350 MW supercritical power station at Jinshan, Guyang County.[2] It is described as a captive power plant for the East Hope Group.[3]
The plant was permitted in November 2015.[4] It is planned for operation in 2017. The plant is for residential heating and is a considered a poverty reduction project.[5]
Planet satellite imagery suggests construction began in June 2017 and then proceeded rapidly. The plant is planned for operation in 2019.[3]
Units 1 and 2 were commissioned in September 2019.[6][7]
Articles and Resources
References
- ↑ 1.0 1.1 https://www.gem.wiki/Coal_source_methodology_for_the_Global_Coal_Plant_Tracker.
{{cite web}}: Missing or empty|title=(help) - ↑ "包头固阳金山工业园区热电厂2×350MW工程环境影响评价信息第二次公示," btjsgyyq.gov.cn, 2015-6-23
- ↑ 3.0 3.1 "建设公司】内蒙古固阳项目图片快讯," PowerChina, 2018-06-08
- ↑ "内蒙古自治区发展和改革委员会关于内蒙古能源发电投资集团有限公司固阳热电联产项目核准的批复," Inner Mongolia DRC, 2015-12-08
- ↑ "内蒙古能源发电包头固阳金山工业园区热电厂2×350MW发电机组工程进行设计图纸交底," 15-08-17
- ↑ [内蒙古包头固阳县新恒丰2×350兆瓦热电联产工程2号机组168小时试运一次成功,"] 中国火力发电网, 2019-09-30
- ↑ "内蒙古能建所属电建一公司承建包头新恒丰热电厂2×350MW机组工程1号机组168小时试运行圆满成功 - 区属企业 - 内蒙古国资委". gzw.nmg.gov.cn. 2019-09-20. Retrieved 2021-01-06.
{{cite web}}: CS1 maint: url-status (link)