Haldia FSRU
| Part of the Global Gas Infrastructure Tracker, a Global Energy Monitor project. |
Haldia FSRU is an LNG import terminal in India with units that are proposed.
Location
Table 1: Location details
| Name | Location | Coordinates (WGS 84) |
|---|---|---|
| Phase 1 | India[1][2] | 22.037345, 88.087662 (approximate) |
| Phase 2 | India[1][2] | 22.037345, 88.087662 (approximate) |
The map below shows the approximate location of the terminal:
Project Details
Table 2: Infrastructure details
| Name | Facility type | Status | Capacity | Total terminal capacity | Offshore | Associated infrastructure |
|---|---|---|---|---|---|---|
| Phase 1 | import[1] | proposed[1] | 1.5 mtpa[1] | 3.0 mtpa | True | – |
| Phase 2 | import[1] | proposed[1] | 1.5 mtpa[1] | 3.0 mtpa | True | – |
Table 3: Cost
| Name | Facility type | Cost | Total known terminal costs |
|---|---|---|---|
| Phase 1 | import[1] | US$300,000,000[3] | US$300,000,000 |
| Phase 2 | import[1] | – | US$300,000,000 |
Financing
No financing data available.
Table 4: Project timeline
| Name | Facility type | Status | Proposal year | FID year | Construction year | Operating year | Inactive year |
|---|---|---|---|---|---|---|---|
| Phase 1 | import[1] | proposed[1] | 2025[1] | – | – | –[1][1] | – |
| Phase 2 | import[1] | proposed[1] | 2025[1] | – | – | – | – |
Ownership
Table 5: Ownership
| Name | Facility type | Status | Owners | Parent companies | Operator |
|---|---|---|---|---|---|
| Phase 1 | import[1] | proposed[1] | Invenire Petrodyne Ltd[1] | Invenire Energy Pvt Ltd | – |
| Phase 2 | import[1] | proposed[1] | Invenire Petrodyne Ltd[1] | Invenire Energy Pvt Ltd | – |
Background
In September 2025, Syama Prasad Mookerjee Port awarded a 30-year concession to a consortium of Invenire Petrodyne Limited and Excelerate Global Operations LLC to develop a floating LNG import terminal. The facility, which will use a floating storage and regasification unit (FSRU), will be located at the Haldia Dock Complex, Kolkata and have an initial capacity of 1.5 mtpa that could later be expanded to 3 mtpa. The developers aim to launch the project in the second half of 2027.[4] The investment required for the first phase of development is estimated to be US$300 million.[5]
In February 2026, it was reported that Excelerate Energy and Invenire Petrodyne are moving forward with their plans to develop an LNG import terminal at the Syama Prasad Mookerjee Port in Haldia.[6]
Articles and Resources
Additional data
To access additional data, including an interactive map of LNG terminals, a downloadable dataset, and summary data, please visit the Global Gas Infrastructure Tracker on the Global Energy Monitor website.
References
- ↑ 1.00 1.01 1.02 1.03 1.04 1.05 1.06 1.07 1.08 1.09 1.10 1.11 1.12 1.13 1.14 1.15 1.16 1.17 1.18 1.19 1.20 1.21 1.22 1.23 https://therisk.global/energy/haldia-fsru-project/?srsltid=AfmBOoqr2D7uOYUsus1BNQwP88B5NscfUU-zB2BYUgUAh1utVH0HqFYz.
{{cite web}}: Missing or empty|title=(help) - ↑ 2.0 2.1 https://www.google.com/maps/place/22%C2%B002'14.4%22N+88%C2%B005'15.6%22E/@22.0445329,88.0813539,3362m/data=!3m1!1e3!4m4!3m3!8m2!3d22.0373448!4d88.0876616?entry=ttu&g_ep=EgoyMDI1MTAwOC4wIKXMDSoASAFQAw%3D%3D.
{{cite web}}: Missing or empty|title=(help) - ↑ https://www.spglobal.com/commodity-insights/en/news-research/latest-news/crude-oil/091025-appec-invenire-boosts-india-upstream-presence-ventures-into-lng-infrastructure.
{{cite web}}: Missing or empty|title=(help) - ↑ SMP Kolkata awards 30-year licence for floating LNG terminal at Haldia, India Seatrade News, September 8, 2025
- ↑ https://www.spglobal.com/commodity-insights/en/news-research/latest-news/crude-oil/091025-appec-invenire-boosts-india-upstream-presence-ventures-into-lng-infrastructure
- ↑ "Excelerate, Invenire move forward with Indian LNG terminal plans - LNG Prime". lngprime.com. Retrieved 2026-08-06.