Henan Yongcheng power station
Part of the Global Coal Plant Tracker, a Global Energy Monitor project. |
Related coal trackers: |
Henan Yongcheng power station (河南永城发电厂) is an operating power station of at least 630-megawatts (MW) in Houling Town, Yongcheng, Shangqiu, Henan, China with multiple units, some of which are not currently operating. It is also known as 中煤永城发电厂 (New Unit 1, New Unit 2), 中煤永城发电厂超超临界机组工程 (New Unit 1, New Unit 2), 永城发电厂 (Unit 1, Unit 2), 永煤集团裕东发电厂 (Unit 1, Unit 2).
Location
Table 1: Project-level location details
Plant name | Location | Coordinates (WGS 84) |
---|---|---|
Henan Yongcheng power station | Houling Town, Yongcheng, Shangqiu, Henan, China | 33.8865342, 116.3639922 (exact) |
The map below shows the exact location of the power station.
Unit-level coordinates (WGS 84):
- Unit 1, Unit 2: 33.8865342, 116.3639922
- New Unit 1, New Unit 2: 33.95412, 116.415988
Project Details
Table 2: Unit-level details
Unit name | Status | Fuel(s) | Capacity (MW) | Technology | Start year | Retired year |
---|---|---|---|---|---|---|
New Unit 1 | construction | coal - unknown | 1000 | ultra-supercritical | – | – |
New Unit 2 | construction | coal - unknown | 1000 | ultra-supercritical | – | – |
Unit 1 | operating | coal - anthracite | 315 | subcritical | 2005 | – |
Unit 2 | operating | coal - anthracite | 315 | subcritical | 2005 | – |
Table 3: Unit-level ownership and operator details
Unit name | Owner |
---|---|
New Unit 1 | China Coal Power Co Ltd [100.0%] |
New Unit 2 | China Coal Power Co Ltd [100.0%] |
Unit 1 | Shangqiu Yudong Power Generation Co Ltd [100.0%] |
Unit 2 | Shangqiu Yudong Power Generation Co Ltd [100.0%] |
Project-level coal details
- Permit(s): November 3, 2022
Background
Yongcheng power station is a two-unit coal-fired power plant with a total capacity of 630 MW.[1] The plant was completed in 2005, and is owned by Yongcheng Mine Group.[2][3] An additional 2,000 MW of coal capacity is under development.
New Project
A new project was listed in Yongcheng City's 14th Five-Year plan.[4][5]
The project was permitted November 3, 2022.[6] Construction reportedly began December 29, 2022.[7]
The project was so rushed that based on available information, it was hard to tell if it was being built at the same site or if the project was a relocation. There is a possibility the older 2 x 315 MW could be shut down to make room for the new one.[8]
Articles and Resources
References
- ↑ "裕东电厂--永城市人民政府网站". www.ycs.gov.cn. 2017-03-07.
{{cite web}}
: CS1 maint: url-status (link) - ↑ Yongcheng Powerplant, Enipedia, accessed Sept. 2015.
- ↑ "河南永城电厂2号30万千瓦机组投产," Sina, Jan 5, 2005
- ↑ "河南永城:建设中煤永城2×1000MW高效超超临界机组工程项目," BJX, 2022-10-09
- ↑ "YCS," Archive, accessed October 2023
- ↑ "中煤永城2×1000MW高效超超临界机组工程获得核准," BJX, 2022-12-04
- ↑ "中煤·商丘(永城)2×1000MW高效超超临界机组工程开工," BJX, 2023-01-13
- ↑ See, e.g., "总投资约70亿,中煤永城2×1000MW高效超超临界机组工程项目新进展," Tou Tiao, 2022-08-07
Additional data
To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.