Henglian Wucaiwan power station
| Part of the Global Coal Plant Tracker, a Global Energy Monitor project. |
| Related coal trackers: |
Henglian Wucaiwan power station (新疆恒联五彩湾电厂) is an operating power station of at least 1320-megawatts (MW) in Wucaiwan Town, Jimsar, Changji, Xinjiang, China with multiple units, some of which are not currently operating.
Location
Table 1: Project-level location details
| Plant name | Location | Coordinates (WGS 84) |
|---|---|---|
| Henglian Wucaiwan power station | Wucaiwan Town, Jimsar, Changji, Xinjiang, China | 44.7898011, 89.1894077 (exact) |
Unit-level coordinates (WGS 84):
- Phase I Unit 1, Phase I Unit 2, Phase II Unit 3, Phase II Unit 4: 44.7898011, 89.1894077
Project Details
Table 2: Unit-level details
| Unit name | Status | Fuel(s) | Capacity (MW) | Technology | Start year | Emergency/Backup |
|---|---|---|---|---|---|---|
| Phase I Unit 1 | Operating | coal: unknown[1] | 660 | ultra-supercritical | 2017 | False |
| Phase I Unit 2 | Operating | coal: unknown[1] | 660 | ultra-supercritical | 2017 | False |
| Phase II Unit 3 | Cancelled | coal: unknown[1] | 660 | ultra-supercritical | – | False |
| Phase II Unit 4 | Cancelled | coal: unknown[1] | 660 | ultra-supercritical | – | False |
Table 3: Unit-level ownership and operator details
| Unit name | Owner | Parent |
|---|---|---|
| Phase I Unit 1 | Xinjiang Henglian Energy Co Ltd [100%] | Fujian Henglian Group Co Ltd [100.0%] |
| Phase I Unit 2 | Xinjiang Henglian Energy Co Ltd [100%] | Fujian Henglian Group Co Ltd [100.0%] |
| Phase II Unit 3 | Xinjiang Henglian Energy Co Ltd [100%] | Fujian Henglian Group Co Ltd [100.0%] |
| Phase II Unit 4 | Xinjiang Henglian Energy Co Ltd [100%] | Fujian Henglian Group Co Ltd [100.0%] |
Project-level coal details
- Coal source(s): domestic
Ownership Tree
This ownership tree is part of the Global Energy Ownership Tracker, a project of Global Energy Monitor.
Description of Expansion
Henglian Group is currently developing two coal-fired units, with a total planned capacity of 1,320 MW. The environmental impact report for the project was approved in 2014, and construction was initiated later in 2014.[2][3]
The two units were commissioned in January and March 2017, respectively.[4][5]
Articles and Resources
References
- ↑ 1.0 1.1 1.2 1.3 https://www.gem.wiki/Coal_source_methodology_for_the_Global_Coal_Plant_Tracker.
{{cite web}}: Missing or empty|title=(help) - ↑ "关于新疆恒联五彩湾(2×660兆瓦)电厂一期工程环境影响报告书的批复", 中华人民共和国环境保护部, 2014-06-26
- ↑ "西北电建新疆恒联五彩湾工程一号机组开始安装", 华商网, 2014-09-10
- ↑ "西北院设计的新疆恒联五彩湾电厂一期1号机组通过168运行",西北电力设计院有限公司, 2017-1-10
- ↑ "新疆恒联五彩湾电厂2号机通过试运行", 中国能源报, 2017-3-22
Additional data
To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.