Heze power station

From Global Energy Monitor
Part of the
Global Coal Plant Tracker,
a Global Energy Monitor project.
Download full dataset
Report an error
Related coal trackers:

Heze power station (国电菏泽电发电厂) is an operating power station of at least 1530-megawatts (MW) in Yuecheng Town, Mudan District, Heze, Shandong, China.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Heze power station Yuecheng Town, Mudan District, Heze, Shandong, China 35.2406919, 115.5334526 (exact)

The map below shows the exact location of the power station.

Loading map...


Unit-level coordinates (WGS 84):

  • Phase I Unit 1, Phase I Unit 2, Phase II Unit 3, Phase II Unit 4, Phase III Unit 5, Phase III Unit 6: 35.2406919, 115.5334526

Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology Start year Retired year
Phase I Unit 1 operating coal - anthracite 135 subcritical 1990
Phase I Unit 2 operating coal - anthracite 135 subcritical 1992
Phase II Unit 3 operating coal - anthracite 300 subcritical 2003
Phase II Unit 4 operating coal - anthracite 300 subcritical 2003
Phase III Unit 5 operating coal - anthracite 330 subcritical 2006
Phase III Unit 6 operating coal - anthracite 330 subcritical 2006

Table 3: Unit-level ownership and operator details

Unit name Owner
Phase I Unit 1 National Energy Heze Power Generation Co Ltd [100.0%]
Phase I Unit 2 National Energy Heze Power Generation Co Ltd [100.0%]
Phase II Unit 3 National Energy Heze Power Generation Co Ltd [100.0%]
Phase II Unit 4 National Energy Heze Power Generation Co Ltd [100.0%]
Phase III Unit 5 National Energy Heze Power Generation Co Ltd [100.0%]
Phase III Unit 6 National Energy Heze Power Generation Co Ltd [100.0%]

Background

The Heze power station is a power plant providing electricity to the Heze, Shandong area.[1] In 2017, the plant produced around 1.068 billion kilowatt-hours (kWh) of power.[2]

Construction began in 1990 for the first two units (which appeared to total 2 x 135 MW by 2021[3]); the second phase of the plant (Units 3 and 4) had a total investment of 3.511 billion RMB, with construction beginning in 1998. The third phase (Units 5 and 6) was built jointly by the China Guodian Corporation and Luneng Development Group Co., Ltd., Heze City Investment Company and Heze Tianze Industrial Group Co., Ltd. In 2012, it was reported that the fourth phase of the plant, which would add up to 1490 MW to the power plant, undergoing preliminary work; however, there has been no further reports on this fourth phase of expansion.[4]

In 2018, Units 1 and 2 had their operation permits extended until August 2031 and March 2031, respectively.[5]

Articles and Resources

References

  1. http://enipedia.tudelft.nl/wiki/Heze_Powerplant
  2. "国电菏泽公司年发电量突破10亿千瓦时-国务院国有资产监督管理委员会". www.sasac.gov.cn (in 中文(中国大陆)). 2017-03-07. Retrieved 2021-07-30.{{cite web}}: CS1 maint: url-status (link)
  3. "在那牡丹盛开的地方," CEIC, 2021-11-18
  4. "国电菏泽发电厂". www.hlfdw.com. 2012-04-05. Retrieved 2021-07-30.{{cite web}}: CS1 maint: url-status (link)
  5. Zhang, Jianfeng (2021-06-29). "山东菏泽公司:逐日求新 筑梦前行". www.ceic.com. Retrieved 2021-07-30.{{cite web}}: CS1 maint: url-status (link)

Additional data

To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.