Hotan power station
| Part of the Global Coal Plant Tracker, a Global Energy Monitor project. |
| Related coal trackers: |
Hotan power station (新疆和田热电联产项目) is an operating power station of at least 700-megawatts (MW) in Kunlun Lake Community, Gujiang Bage Town, Hotan, Xinjiang, China.
Location
Table 1: Project-level location details
| Plant name | Location | Coordinates (WGS 84) |
|---|---|---|
| Hotan power station | Kunlun Lake Community, Gujiang Bage Town, Hotan, Xinjiang, China | 37.2661537, 79.9923769 (exact) |
Unit-level coordinates (WGS 84):
- Unit 1, Unit 2: 37.2661537, 79.9923769
Project Details
Table 2: Unit-level details
| Unit name | Status | Fuel(s) | Capacity (MW) | Technology | CHP | Start year | Emergency/Backup |
|---|---|---|---|---|---|---|---|
| Unit 1 | Operating[1] | coal: unknown[2] | 350 | unknown | yes | 2024 | False |
| Unit 2 | Operating | coal: unknown[2] | 350 | unknown | yes | 2025 | False |
Table 3: Unit-level ownership and operator details
| Unit name | Owner | Parent |
|---|---|---|
| Unit 1 | Xinjiang Energy (Group) Hetian Energy Co Ltd [100%] | Xinjiang Energy (Group) Co Ltd [100.0%] |
| Unit 2 | Xinjiang Energy (Group) Hetian Energy Co Ltd [100%] | Xinjiang Energy (Group) Co Ltd [100.0%] |
Project-level coal details
- Coal source(s): domestic
Ownership Tree
This ownership tree is part of the Global Energy Ownership Tracker, a project of Global Energy Monitor.
Background on Project
Hotan power station is a proposed 2 x 350 MW coal-fired power station in Gujiang Bage Town. It was listed as one of the "Key Projects" for Xinjiang in 2021.[3]
The project was approved in June 2021, and construction began in November 2021.[4]
The project progressed through 2024 with the Unit 1 boiler water pressure test in April[5] and grid connection in September 2024[6]. Unit 1 successfully completed the 168-hour trial run in October 2024[7].
Unit 2 construction progressed, and the unit was expected to be commissioned by late 2024 or early 2025[8].
Articles and Resources
References
- ↑ "和田2×35万千瓦热电联产项目1号机组正式投产-北极星火力发电网". news.bjx.com.cn. 2024-10-31. Archived from the original on 2025-06-30. Retrieved 2024-11-01.
- ↑ 2.0 2.1 https://www.gem.wiki/Coal_source_methodology_for_the_Global_Coal_Plant_Tracker.
{{cite web}}: Missing or empty|title=(help) - ↑ "2021年新疆自治区重点项目清单发布:涉及多个电力项目," 北极星电力网新闻中心, 2021/3/24
- ↑ "新疆能源集团和田2x35万千瓦热电联产项目开工," XJHT, 2021-11-29
- ↑ "新疆和田2×350MW热电联产项目1号锅炉水压试验一次成功". WeChat. 2024-04-05. Retrieved 2026-07-28.
{{cite web}}: CS1 maint: url-status (link) - ↑ "和田能源2×35万千瓦热电联产项目1号机组首次并网一次成功". 北极星电力网. 2024-09-25. Retrieved 2026-07-28.
{{cite web}}: CS1 maint: url-status (link) - ↑ "和田2×35万千瓦热电联产项目1号机组168小时满负荷试运行圆满成功". WeChat. 2024-10-28. Retrieved 2026-07-28.
{{cite web}}: CS1 maint: url-status (link) - ↑ "和田新疆能源2×35万千瓦热电联产项目1号机组并网发电,预计2号机组将于2024年11月底前建成投产". 新疆维吾尔自治区发展和改革委员会. 2024-10-24. Retrieved 2026-07-28.
{{cite web}}: CS1 maint: url-status (link)