Huadian Gaochang Cogen power station

From Global Energy Monitor
Part of the
Global Coal Plant Tracker,
a Global Energy Monitor project.
Download full dataset
Report an error
Related coal trackers:

Huadian Gaochang Cogen power station (华电新疆高昌热电厂) is an operating power station of at least 700-megawatts (MW) in Ya‘er Town, Gaochang, Turpan, Xinjiang, China. It is also known as 华电吐鲁番发电, Huadian Turpan Cogen power station.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Huadian Gaochang Cogen power station Ya‘er Town, Gaochang, Turpan, Xinjiang, China 42.879651, 89.167144 (exact)

The map below shows the exact location of the power station.

Loading map...


Unit-level coordinates (WGS 84):

  • Unit 1, Unit 2: 42.879651, 89.167144

Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology Start year Retired year
Unit 1 operating coal - unknown 350 supercritical 2020
Unit 2 operating[1] coal - unknown 350 supercritical 2023[1]

Table 3: Unit-level ownership and operator details

Unit name Owner
Unit 1 Xinjiang Huadian Gaochang Thermal Power Co Ltd [100.0%]
Unit 2 Xinjiang Huadian Gaochang Thermal Power Co Ltd [100.0%]

Project-level coal details

  • Permit(s): June 26, 2015

Background

In 2014 China Huadian proposed a cogeneration power station of 2 x 350 MW in Turpan prefecture. The feasibility study was released in 2015.[2]

Construction began in November 2015.[3]

Unit 1 was commissioned on December 30, 2020.[4]

As of April 2022, Unit 2 was slated to be operational by the end of the year.[5] Unit 2 began operating in April 2023.[6]

Articles and Resources

References

  1. 1.0 1.1 https://web.archive.org/web/20240125141856/https://news.bjx.com.cn/html/20230505/1304680.shtml. Archived from the original on 25 January 2024. {{cite web}}: Missing or empty |title= (help)
  2. "华电吐鲁番热电厂、八钢托克逊热电厂纳入国家2014年火电建设规划," 2015-01-27
  3. "新疆华电高昌热电有限公司2×350MW工程开工仪式," Turpan government, 2015-11-09
  4. "新疆吐鲁番热电项目1号机组投运 - 北极星火力发电网". news.bjx.com.cn. 2021-01-04. Retrieved 2021-01-05.{{cite web}}: CS1 maint: url-status (link)
  5. 华电2×350MW冷热电联产项目2号机组计划于2022年底投产, news.bjx.com, April 11, 2022
  6. 新疆华电高昌热电公司2号机组投产发电, news.bjx.com, May 5, 2023