Huaihe Energy Selian Second Mine pilot coal power project
| Part of the Global Coal Plant Tracker, a Global Energy Monitor project. |
| Related coal trackers: |
Huaihe Energy Selian Second Mine pilot coal power project (淮河能源色连二矿2×1000MW超超临界机组新一代煤电试点项目) is an announced power station in Hantai Town, Dongsheng District, Ordos, Inner Mongolia, China.
Location
Table 1: Project-level location details
| Plant name | Location | Coordinates (WGS 84) |
|---|---|---|
| Huaihe Energy Selian Second Mine pilot coal power project | Hantai Town, Dongsheng District, Ordos, Inner Mongolia, China | 39.87049, 109.85477 (approximate)[1] |
Project Details
Table 2: Unit-level details
| Unit name | Status | Fuel(s) | Capacity (MW) | Technology | Emergency/Backup |
|---|---|---|---|---|---|
| Unit 1 | Announced[1] | coal: unknown[1] | 1000[1] | ultra-supercritical[1] | False |
| Unit 2 | Announced[1] | coal: unknown[1] | 1000[1] | ultra-supercritical[1] | False |
Table 3: Unit-level ownership and operator details
| Unit name | Owner | Parent |
|---|---|---|
| Unit 1 | Huaihe Energy Western Coal Power Group Co Ltd [100%][1] | Huaihe Energy Holding Group Co Ltd [82.9%]; unknown [8.8%]; China Cinda Asset Management Co Ltd [8.3%] |
| Unit 2 | Huaihe Energy Western Coal Power Group Co Ltd [100%][1] | Huaihe Energy Holding Group Co Ltd [82.9%]; unknown [8.8%]; China Cinda Asset Management Co Ltd [8.3%] |
Project-level captive use details
- Captive industry: Coal Mining & Coal Products[1]
Ownership Tree
This ownership tree is part of the Global Energy Ownership Tracker, a project of Global Energy Monitor.
Background
In June 2025, Huadian Group issued a public tender for feasibility study and power grid connection scheme preparation services for the first phase of its planned 2×1000MW coal-fired power project in Dongtou, Wenzhou, Zhejiang Province[2]. In August 2025, China Energy Engineering Group Zhejiang Electric Power Design Institute Co., Ltd. won the bid for these services with a quoted price of 4.8 million yuan[3]. Subsequently, in September 2025, Zhejiang Environmental Science Technology Co., Ltd. was awarded the contract for environmental impact assessment and marine use demonstration services for the project, with a bid price of 6.1 million yuan[4]. The project is planned to consist of four 1000MW ultra-supercritical coal-fired units in total, with the first phase including two units.
Articles and Resources
References
- ↑ 1.00 1.01 1.02 1.03 1.04 1.05 1.06 1.07 1.08 1.09 1.10 1.11 https://mp.weixin.qq.com/s/d2i3YRojRKKs3svHUQ0akQ.
{{cite web}}: Missing or empty|title=(help) - ↑ "华电温州洞头一期2×1000MW煤电项目可研报告及电力系统接入方案编制服务项目招标公告". 火电之声. 2025-06-18. Retrieved 2026-05-29.
{{cite web}}: CS1 maint: url-status (link) - ↑ "浙江院中标华电温州洞头一期2×1000MW煤电项目可研报告及电力系统接入方案编制服务". 火电之声. 2025-08-11. Retrieved 2026-05-29.
{{cite web}}: CS1 maint: url-status (link) - ↑ "浙江华电温州洞头一期2×100万千瓦煤电项目环评及海域使用论证等环保相关专题技术服务中标结果". 火电之声. 2025-09-25. Retrieved 2026-05-29.