Huaneng Chongqing Liangjiang Gas power station
| Part of the Global Oil and Gas Plant Tracker, a Global Energy Monitor project. |
| Related categories: |
Huaneng Chongqing Liangjiang Gas power station (华能重庆两江燃机发电厂一期 (Units 1-1, 1-2), 华能重庆两江燃机发电厂二期 (Units 2-1, 2-2, 2-3), 华能重庆两江燃机发电厂) is an operating power station of at least 2424-megawatts (MW) in Beibei District, Chongqing, China with multiple units, some of which are not currently operating.
Location
Table 1: Project-level location details
| Plant name | Location | Coordinates (WGS 84) |
|---|---|---|
| Huaneng Chongqing Liangjiang Gas power station | Beibei District, Chongqing, China | 29.7862319, 106.5095197 (exact)[1][2][3][4] |
Unit-level coordinates (WGS 84):
- 1-1, 1-2, 2-1, 2-2, 2-3: 29.7862319, 106.5095197
Project Details
Table 2: Unit-level details
| Unit name | Status | Fuel(s) | Capacity (MW) | Technology | CHP | Start year | Equipment | Emergency/Backup |
|---|---|---|---|---|---|---|---|---|
| 1-1 | Operating[5] | fossil gas: natural gas[5] | 470[6] | combined cycle[5] | yes[5] | 2014[5] | not found: 9F[7] | no |
| 1-2 | Operating[5] | fossil gas: natural gas[5] | 470[6] | combined cycle[5] | yes[5] | 2014[5] | not found: 9F[7] | no |
| 2-1 | Operating[8] | fossil gas: natural gas[9] | 742[10][7] | combined cycle[1][9] | yes[1][5] | 2025[8] | Mitsubishi Power: M701J[11] | no |
| 2-2 | Operating[12] | fossil gas: natural gas[9] | 742[10][7] | combined cycle[1][9] | yes[1][5] | 2025[12] | Mitsubishi Power: M701J[11] | no |
| 2-3 | Cancelled[10] | fossil gas: natural gas[9] | 700[1][9] | combined cycle[9] | yes[5] | – | not found: 9H[1] | no |
CHP is an abbreviation for Combined Heat and Power. It is a technology that produces electricity and thermal energy at high efficiencies. Coal units track this information in the Captive Use section when known.
Table 3: Unit-level ownership and operator details
| Unit name | Owner | Parent |
|---|---|---|
| 1-1 | Huaneng Chongqing Liangjiang Gas Turbine Power Generation Co Ltd [100%][10] | Huaneng Power International Inc [75.0%]; Kunlun Energy Company Limited Co Ltd [15.0%]; Chongqing Gas Group Corp Ltd [10.0%] |
| 1-2 | Huaneng Chongqing Liangjiang Gas Turbine Power Generation Co Ltd [100%][10] | Huaneng Power International Inc [75.0%]; Kunlun Energy Company Limited Co Ltd [15.0%]; Chongqing Gas Group Corp Ltd [10.0%] |
| 2-1 | Huaneng Chongqing Liangjiang Gas Turbine Power Generation Co Ltd [100%][10] | Huaneng Power International Inc [75.0%]; Kunlun Energy Company Limited Co Ltd [15.0%]; Chongqing Gas Group Corp Ltd [10.0%] |
| 2-2 | Huaneng Chongqing Liangjiang Gas Turbine Power Generation Co Ltd [100%][10] | Huaneng Power International Inc [75.0%]; Kunlun Energy Company Limited Co Ltd [15.0%]; Chongqing Gas Group Corp Ltd [10.0%] |
| 2-3 | Huaneng Chongqing Liangjiang Gas Turbine Power Generation Co Ltd [100%][10] | Huaneng Power International Inc [75.0%]; Kunlun Energy Company Limited Co Ltd [15.0%]; Chongqing Gas Group Corp Ltd [10.0%] |
Ownership Tree
This ownership tree is part of the Global Energy Ownership Tracker, a project of Global Energy Monitor.
Background
Huaneng Chongqing Liangjiang Gas power station project is approved to construct 5 sets of F-class natural gas combined heat and power units. [13]
The first phase of the project started in December 2012 and was put into operation in 2014.
The second phase of the project commenced in July 2023 and is expected to be operational by March 2026.[14]
Articles and Resources
References
- ↑ 1.0 1.1 1.2 1.3 1.4 1.5 1.6 "中国华能集团有限公司重庆分公司华能重庆两江燃机二期项目环境影响报告表" (PDF). 2022-05. Archived from the original (PDF) on 2024-04-09. Retrieved 2024-04-04.
{{cite web}}: Check date values in:|date=(help) - ↑ "华能重庆两江燃机2×741.87兆瓦二期项目又有新进展". 2023-11-27. Archived from the original on 2024-04-09. Retrieved 2024-04-04.
- ↑ "重庆市生态环境局两江新区分局审查建设项目环评信息公示表(华能重庆两江燃机二期项目(500kV升压站扩建)建设项目环评信息公示表)-华能重庆两江燃机二期项目(500kV升压站扩建)". 2023-04-26. Archived from the original on 2026-01-22. Retrieved 2025-12-17.
- ↑ https://web.archive.org/web/20210604005001/https://www.industryabout.com/country-territories-3/1705-china/fossil-fuels-energy/25503-liangjiang-gas-power-plant. Archived from the original on 2021-06-04.
{{cite web}}: Missing or empty|title=(help) - ↑ 5.00 5.01 5.02 5.03 5.04 5.05 5.06 5.07 5.08 5.09 5.10 5.11 5.12 https://m.bjx.com.cn/mnews/20180423/893562.shtml.
{{cite web}}: Missing or empty|title=(help) - ↑ 6.0 6.1 http://paper.people.com.cn/zgnyb/html/2015-01/12/content_1520420.htm.
{{cite web}}: Missing or empty|title=(help) - ↑ 7.0 7.1 7.2 7.3 https://m.bjx.com.cn/mnews/20230714/1319352.shtml.
{{cite web}}: Missing or empty|title=(help) - ↑ 8.0 8.1 https://www.powerchina.cn/col/col7460/art/2025/art_848477974.html.
{{cite web}}: Missing or empty|title=(help) - ↑ 9.0 9.1 9.2 9.3 9.4 9.5 9.6 https://web.archive.org/web/20220708183757/https://m.21jingji.com/article/20211216/herald/0f9fa68020365b34aadefc737ed09ce9.html. Archived from the original on 2022-07-08.
{{cite web}}: Missing or empty|title=(help) - ↑ 10.0 10.1 10.2 10.3 10.4 10.5 10.6 10.7 "重庆市发展和改革委员会关于华能重庆两江燃机二期项目核准内容变更的批复_审批核准备案信息_重庆市发展和改革委员会". fzggw.cq.gov.cn. 2024-01-17. Archived from the original on 2024-04-09. Retrieved 2024-04-04.
- ↑ 11.0 11.1 https://gas.in-en.com/html/gas-3676368.shtml.
{{cite web}}: Missing or empty|title=(help) - ↑ 12.0 12.1 "华能重庆两江燃机二期项目投产". 2025-08-15. Archived from the original on 2026-01-22. Retrieved 2025-12-17.
- ↑ "三菱M701F级燃机26家电厂、66台机组汇总". 2018-04-23. Retrieved 2023-10-16.
{{cite web}}: CS1 maint: url-status (link) - ↑ "2×741.87MW!中国能建中标华能重庆两江燃机二期项目标段二". 2023-07-14. Retrieved 2023-10-16.
{{cite web}}: CS1 maint: url-status (link)