Huaneng Dalian-2 power station
Part of the Global Coal Plant Tracker, a Global Energy Monitor project. |
Related coal trackers: |
Huaneng Dalian-2 power station (华能大连第二热电厂) is an operating power station of at least 800-megawatts (MW) in Haimao Street, Ganjingzi, Dalian, Liaoning, China. It is also known as 大连开发区第二热电 (Unit 3, Unit 4), 华能大连热电 (Unit 3, Unit 4), 华能大连第二热电厂“上大压小”新建工程.
Location
Table 1: Project-level location details
Plant name | Location | Coordinates (WGS 84) |
---|---|---|
Huaneng Dalian-2 power station | Haimao Street, Ganjingzi, Dalian, Liaoning, China | 38.993019, 121.656412 (exact) |
Unit-level coordinates (WGS 84):
- Unit 1, Unit 2, Unit 3, Unit 4: 38.993019, 121.656412
Project Details
Table 2: Unit-level details
Unit name | Status | Fuel(s) | Capacity (MW) | Technology | Start year |
---|---|---|---|---|---|
Unit 1 | Operating | coal: unknown | 50 | subcritical | 2020 |
Unit 2 | Operating | coal: unknown | 50 | subcritical | 2020 |
Unit 3 | Operating | coal: unknown | 350 | supercritical | 2022 |
Unit 4 | Operating | coal: unknown | 350 | supercritical | 2022 |
Table 3: Unit-level ownership and operator details
Unit name | Owner | Parent |
---|---|---|
Unit 1 | Huaneng (Dalian) Thermal Power Co Ltd [100%] | Huaneng Power International Inc [100.0%] |
Unit 2 | Huaneng (Dalian) Thermal Power Co Ltd [100%] | Huaneng Power International Inc [100.0%] |
Unit 3 | Huaneng (Dalian) Thermal Power Co Ltd [100%] | Huaneng Power International Inc [100.0%] |
Unit 4 | Huaneng (Dalian) Thermal Power Co Ltd [100%] | Huaneng Power International Inc [100.0%] |
Project-level captive use details
- Captive industry use (heat or power): both
- Captive industry: Chemicals
- Non-industry use: heat
Ownership Tree
This ownership tree is part of the Global Energy Ownership Tracker, a project of Global Energy Monitor.
Background
China Huaneng sought permitting for 2 x 350 MW supercritical units in Ganjingzi District (Units 3-4) with two 50 MW back-pressure units (Units 1-2). The two 50 MW units were permitted for construction in 2015.[1]
As of July 2015, the two 50 MW back-pressured units were under construction. They were planned for commissioning in 2019.[2] They began operating in June 2020.[3]
2017: Nationwide Restrictions Imposed on Development of Coal-Fired Power Capacity
In January 2017 China's National Energy Administration suspended over 100 planned and under-construction coal power projects in 13 provinces, including unit 4 of Huaneng Dalian-2. It was unclear when or if the projects would be revived.[4][5] (For details, see China's 2016 Restrictions on Development of Coal-Fired Power Capacity.)
2021: Units 3-4 underway
Construction began on units 3 and 4 in 2021.[6]
Unit 3 was commissioned on June 1, 2022 and Unit 4 went into commercial operation on December 7, 2022.[7][8]
Articles and Resources
References
- ↑ 华能大连第二热电厂背压机组新建工程项目获核准 BJX News, 北极星电力网新闻中心,来源:华能集团. 11-17-2014
- ↑ "华能大连热电厂项目开工," China CEM, July 22, 2015
- ↑ "华能大连第二热电厂背压机组新建工程两台机组投产," 中国火力发电网, 2020-07-06
- ↑ "能源局下发13省市新建火电机组停建清单(附文件)," Polaris, Jan 16, 2017
- ↑ "国家能源局发文推迟辽宁、四川两省2个煤电项目," 中国电力化工网, 2017-01-17
- ↑ "华能大连第二热电厂新建工程4号机组发电机定子顺利吊装完成," 北极星电力网新闻中心, 2021/10/2
- ↑ 华能大连热电厂3号机组投入商运, BJX, 2022-06-01
- ↑ "我们的历史 - 2022年大事记". 中国华能集团有限公司网站. January 2023.
{{cite web}}
: CS1 maint: url-status (link)
Additional data
To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.