Huaneng Dongguan Gas Thermal power station (华能东莞燃机热电, 东莞华能谢岗天然气发电项目, 华能东莞燃机二期(2-1 and 2-2)) is an operating power station of at least 945-megawatts (MW) in Yinshan Technology Park, Caole Village, Xie Gang Town, Dongguan, Guangdong, China with multiple units, some of which are not currently operating.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Huaneng Dongguan Gas Thermal power station Yinshan Technology Park, Caole Village, Xie Gang Town, Dongguan, Guangdong, China 22.983207, 114.102517 (exact)[1]

The map below shows the exact location of the power station.

Loading map...


Unit-level coordinates (WGS 84):

  • 1-1, 1-2, 2-1, 2-2: 22.983207, 114.102517

Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology CHP Start year
1-1 Operating[2] fossil gas: natural gas[3] 473[3] combined cycle[2] yes[3] 2020[4]
1-2 Operating[2] fossil gas: natural gas[3] 472.5[3] combined cycle[2] yes[3] 2020[5]
2-1 Construction[6] fossil gas: natural gas[7] 498[8] combined cycle[7] not found 2025 (planned)[9][10]
2-2 Construction[10] fossil gas: natural gas[7] 498[8] combined cycle[7] not found 2025 (planned)[9][10]

CHP is an abbreviation for Combined Heat and Power. It is a technology that produces electricity and thermal energy at high efficiencies. Coal units track this information in the Captive Use section when known.

Table 3: Unit-level ownership and operator details

Unit name Owner Parent
1-1 Huaneng Dongguan Gas Turbine Thermal Power Co Ltd [100%][9][11][3][12] Huaneng Power International Inc [80.0%]; Kunlun Energy Co Ltd [20.0%]
1-2 Huaneng Dongguan Gas Turbine Thermal Power Co Ltd [100%][9][11][3][12] Huaneng Power International Inc [80.0%]; Kunlun Energy Co Ltd [20.0%]
2-1 Huaneng Dongguan Gas Turbine Thermal Power Co Ltd [100%][9][11][3][12] Huaneng Power International Inc [80.0%]; Kunlun Energy Co Ltd [20.0%]
2-2 Huaneng Dongguan Gas Turbine Thermal Power Co Ltd [100%][9][11][3][12] Huaneng Power International Inc [80.0%]; Kunlun Energy Co Ltd [20.0%]

Background

The Phase I of this project received approval from the Guangdong Provincial Development and Reform Commission in August 2015. It officially entered construction on December 26, 2017[13], and went into operation on August 27, 2020.[14]

The Phase II of this project received approval from the Guangdong Provincial Development and Reform Commission in February 2022. [15]It officially entered construction in May 2023[16], and it is expected to start operation in the second half of 2024.[17]

Articles and Resources

References

  1. https://web.archive.org/web/20210605004839/https://www.sohu.com/a/204248149_379273. Archived from the original on 2021-06-05. {{cite web}}: Missing or empty |title= (help)
  2. 2.0 2.1 2.2 2.3 http://www.nengyuanjie.net/article/40264.html. {{cite web}}: Missing or empty |title= (help)
  3. 3.0 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 https://web.archive.org/web/20210604044901/https://www.china5e.com/news/news-1015993-1.html. Archived from the original on 2021-06-04. {{cite web}}: Missing or empty |title= (help)
  4. https://web.archive.org/web/20210604210632/https://news.bjx.com.cn/html/20200611/1080412.shtml. Archived from the original on 2021-06-04. {{cite web}}: Missing or empty |title= (help)
  5. https://news.dayoo.com/gzrbyc/202004/21/158752_53299437.htm. {{cite web}}: Missing or empty |title= (help)
  6. ,https://news.bjx.com.cn/html/20221130/1272984.shtml https://www.powerchina.cn/art/2023/5/17/art_7445_1667654.html ,https://news.bjx.com.cn/html/20221130/1272984.shtml. {{cite web}}: Check |url= value (help); Missing or empty |title= (help)
  7. 7.0 7.1 7.2 7.3 ,http://dgdp.dg.gov.cn/zmhd/zjdc/content/post_3597902.html https://www.powerchina.cn/art/2023/5/17/art_7445_1667654.html ,http://dgdp.dg.gov.cn/zmhd/zjdc/content/post_3597902.html. {{cite web}}: Check |url= value (help); Missing or empty |title= (help)
  8. 8.0 8.1 https://www.powerchina.cn/art/2023/5/17/art_7445_1667654.html. {{cite web}}: Missing or empty |title= (help)
  9. 9.0 9.1 9.2 9.3 9.4 9.5 "华能东莞燃机二期项目开工 建成后年发电量约40亿千瓦时__南方+_南方plus". static.nfapp.southcn.com. 2023-11-01. Archived from the original on 2024-04-16. Retrieved 2024-04-15.
  10. 10.0 10.1 10.2 https://www.dg.gov.cn/zwgk/zfxxgkml/xgz/ywgz/zdjsxm/content/post_4210609.html. {{cite web}}: Missing or empty |title= (help)
  11. 11.0 11.1 11.2 11.3 https://www.qcc.com/firm_66TQ5ZX.shtml. {{cite web}}: Missing or empty |title= (help)
  12. 12.0 12.1 12.2 12.3 https://web.archive.org/web/20220415233527/http://dgdp.dg.gov.cn/zmhd/zjdc/content/post_3597902.html. Archived from the original on 2022-04-15. {{cite web}}: Missing or empty |title= (help)
  13. "华能东莞燃机热电一期工程正式开工". 2017-12-29. Retrieved 2023-10-30.{{cite web}}: CS1 maint: url-status (link)
  14. "广东火电参建的东莞燃机热电一期工程全面投产". 2020-09-09. Retrieved 2023-10-30.{{cite web}}: CS1 maint: url-status (link)
  15. "广东省发展改革委关于华能东莞燃机二期工程项目核准的批复". 2022-02-16. Retrieved 2023-10-30.{{cite web}}: CS1 maint: url-status (link)
  16. "华能东莞燃机二期项目正式开工". 2023-05-17. Retrieved 2023-10-30.{{cite web}}: CS1 maint: url-status (link)
  17. "高质量发展看东莞|华能东莞热电二期将于明年下半年投产发电". 2023-02-27. Retrieved 2023-10-30.{{cite web}}: CS1 maint: url-status (link)

Additional data

To access additional data, including an interactive map of gas-fired power stations, a downloadable dataset, and summary data, please visit the Global Oil and Gas Plant Tracker on the Global Energy Monitor website.