Huaneng Fuzhou power station
| Part of the Global Coal Plant Tracker, a Global Energy Monitor project. |
| Related coal trackers: |
Huaneng Fuzhou power station (华能国际福州电厂) is an operating power station of at least 2020-megawatts (MW) in Choudong, Changle, Fuzhou, Fujian, China with multiple units, some of which are not currently operating. It is also known as 华能福州电厂一期机组等容量煤电替代项目 (Phase IR Unit 3).
Location
Table 1: Project-level location details
| Plant name | Location | Coordinates (WGS 84) |
|---|---|---|
| Huaneng Fuzhou power station | Choudong, Changle, Fuzhou, Fujian, China | 25.99083, 119.4816 (exact) |
Unit-level coordinates (WGS 84):
- Phase I Unit 1, Phase I Unit 2, Phase II Unit 3, Phase II Unit 4, Phase III Unit 5, Phase III Unit 6, Phase IR Unit 3: 25.99083, 119.4816
Project Details
Table 2: Unit-level details
| Unit name | Status | Fuel(s) | Capacity (MW) | Technology | Start year |
|---|---|---|---|---|---|
| Phase I Unit 1 | Mothballed[1] | coal: bituminous | 350 | subcritical | 1988 |
| Phase I Unit 2 | Mothballed[1] | coal: bituminous | 350 | subcritical | 1988 |
| Phase II Unit 3 | Operating | coal: bituminous | 350 | subcritical | 1999 |
| Phase II Unit 4 | Operating | coal: bituminous | 350 | subcritical | 1999 |
| Phase III Unit 5 | Operating | coal: bituminous | 660 | ultra-supercritical | 2010 |
| Phase III Unit 6 | Operating | coal: bituminous | 660 | ultra-supercritical | 2010 |
| Phase IR Unit 3 | Announced[2] | coal: bituminous[3] | 700[3] | ultra-supercritical[3] | 2024 (planned)[3] |
Table 3: Unit-level ownership and operator details
| Unit name | Owner | Parent |
|---|---|---|
| Phase I Unit 1 | Huaneng (Fujian) Energy Development Co Ltd [100%] | Huaneng Power International Inc [100.0%] |
| Phase I Unit 2 | Huaneng (Fujian) Energy Development Co Ltd [100%] | Huaneng Power International Inc [100.0%] |
| Phase II Unit 3 | Huaneng (Fujian) Energy Development Co Ltd [100%] | Huaneng Power International Inc [100.0%] |
| Phase II Unit 4 | Huaneng (Fujian) Energy Development Co Ltd [100%] | Huaneng Power International Inc [100.0%] |
| Phase III Unit 5 | Huaneng (Fujian) Energy Development Co Ltd [100%] | Huaneng Power International Inc [100.0%] |
| Phase III Unit 6 | Huaneng (Fujian) Energy Development Co Ltd [100%] | Huaneng Power International Inc [100.0%] |
| Phase IR Unit 3 | Huaneng (Fujian) Energy Development Co Ltd [100%] | Huaneng Power International Inc [100.0%] |
Ownership Tree
This ownership tree is part of the Global Energy Ownership Tracker, a project of Global Energy Monitor.
Background
The first four coal-fired units of Huaneng Fuzhou power station – the two-unit Huaneng Fuzhou-1 and two-unit Huaneng Fuzhou-2 totaling 1,400 MW, were brought online between 1988 and 1999. The plant is owned by China Huaneng.[4]
In 2010, China Huaneng built two additional coal-fired units at this plant, Huaneng Fuzhou-3, with a total capacity of 1,320 MW.[5][6][7]
Units 1 and 2 appeared mothballed in 2022.[8]
Description of Expansion
In January 2021, an additional 700 MW unit was planned for commissioning in 2024, Huaneng Fuzhou-1R Unit 3.[9][10]
In 2023, with two years since the last known development, Huaneng Fuzhou-1R Unit 3 was presumed to be shelved.
Articles and Resources
References
- ↑ 1.0 1.1 "中国能源新闻网". www.cpnn.com.cn. 2022-04-1. Archived from the original on 2024-01-25. Retrieved 2023-10-11.
{{cite web}}: Check date values in:|date=(help) - ↑ https://mp.weixin.qq.com/s/J2rk9X0YtHXRlv8Y6A3h7Q.
{{cite web}}: Missing or empty|title=(help) - ↑ 3.0 3.1 3.2 3.3 http://news.bjx.com.cn/html/20210114/1129655.shtml.
{{cite web}}: Missing or empty|title=(help) - ↑ "Huaneng Fuzhou Coal Power Plant China," Global Energy Observatory, accessed July 2013.
- ↑ Ailun Yang and Yiyun Cui, "Global Coal Risk Assessment: Data Analysis and Market Research," World Resources Institute working paper, November 2012
- ↑ "福建华能福州电厂6号机组“上大压小”工程通过核准," accessed June 2013
- ↑ “华能福州电厂,” 华能国际电力股份有限工司, accessed 2014-08-26
- ↑ 华能福州电厂1、2号机组见证电厂36年发展, cpnn.com.cn, 2022-04-13
- ↑ "华能2台35万千瓦机组拟关停 等容量替代项目环评服务已开始招标 - 北极星火力发电网". news.bjx.com.cn. 2021-01-14. Retrieved 2021-01-15.
{{cite web}}: CS1 maint: url-status (link) - ↑ "华能福州电厂一期机组等容量煤电替代项目接入系统设计报告编制【重新招标】招标," dlztb.com, 2021-01-10
Additional data
To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.