Huangling waste coal power station (陕煤集团黄陵矿业煤矸石热电公司) is an operating power station of at least 700-megawatts (MW) in Shuanglong Town, Huangling, Yan'an, Shaanxi, China with multiple units, some of which are not currently operating.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Huangling waste coal power station Shuanglong Town, Huangling, Yan'an, Shaanxi, China 35.660349, 108.922901 (exact)

The map below shows the exact location of the power station.

Loading map...


Unit-level coordinates (WGS 84):

  • Phase III Unit 5, Phase III Unit 6, Phase IV Unit 7, Phase IV Unit 8: 35.660349, 108.922901
  • Phase II Unit 3, Phase II Unit 4: 35.655767, 109.061847

Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology Start year Retired year
Phase II Unit 3 operating coal - waste coal 50 unknown 2007
Phase II Unit 4 operating coal - waste coal 50 unknown 2007
Phase III Unit 5 operating coal - waste coal 300 subcritical 2015
Phase III Unit 6 operating coal - waste coal 300 subcritical 2015
Phase IV Unit 7 cancelled coal - waste coal 300 subcritical
Phase IV Unit 8 cancelled coal - waste coal 300 subcritical

Table 3: Unit-level ownership and operator details

Unit name Owner
Phase II Unit 3 Huangling Mining Industry Coal Gangue Power Generation Co Ltd [100.0%]
Phase II Unit 4 Huangling Mining Industry Coal Gangue Power Generation Co Ltd [100.0%]
Phase III Unit 5 Huangling Mining Industry Coal Gangue Power Generation Co Ltd [100.0%]
Phase III Unit 6 Huangling Mining Industry Coal Gangue Power Generation Co Ltd [100.0%]
Phase IV Unit 7 Huangling Mining Industry Coal Gangue Power Generation Co Ltd [100.0%]
Phase IV Unit 8 Huangling Mining Industry Coal Gangue Power Generation Co Ltd [100.0%]

Project-level coal details

  • Permit(s): December 29, 2014

Background

The existing coal-fired units are as follows: Phase I (2 x 15 MW), Phase II (2 x 50 MW), Phase III (2 x 300 MW). Construction is by Northwest Power Construction Group, and the sponsor is Huangling Mining Group Co.[1][2]

A groundbreaking ceremony celebrating construction of the plant was held in 2008. Construction was halted in 2010 when inspectors with the State Environmental Protection Department found the project had not yet acquired the land required for environmental approval when construction began. Fines for the permit violation were reportedly settled in 2013.[3]

The project was permitted in 2014.[4] The power station completed trial operation in 2015.[5]

Articles and Resources

References

  1. Ailun Yang and Yiyun Cui, "Global Coal Risk Assessment: Data Analysis and Market Research," World Resources Institute working paper, November 2012
  2. "黄陵矿业煤矸石发电公司十年发展历程," Shaanxi Coal & Chemical Industry Group, 2013-7-26
  3. "山西黄陵煤矸石电厂停工2年后获批," bjx.com, March 14, 2013.
  4. "黄陵矿业2×300MW煤矸石电厂项目顺利取得环评批复", 陕西煤业化工集团有限责任公司, 2014-07-07
  5. "黄陵矿业建成西北最大煤矸石电厂," 陕西农村报, 2015-08-14