Huasheng Jiangquan cogen power station

From Global Energy Monitor
Part of the
Global Coal Plant Tracker,
a Global Energy Monitor project.
Download full dataset
Report an error
Related coal trackers:

Huasheng Jiangquan cogen power station (临沂恒新能源集团2×35万千瓦热电联产项目, 华盛江泉罗庄热电联产项目) is a power station under construction in Xishantou Village, Luozhuang District, Linyi, Shandong, China.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Huasheng Jiangquan cogen power station Xishantou Village, Luozhuang District, Linyi, Shandong, China 34.945412, 118.313026 (exact)
Loading map...

Unit-level coordinates (WGS 84):

  • Unit 1, Unit 2: 34.945412, 118.313026

Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology
Unit 1 Construction coal: waste coal 350 supercritical
Unit 2 Construction coal: waste coal 350 supercritical

Table 3: Unit-level ownership and operator details

Unit name Owner Parent
Unit 1 Shandong Huasheng Jiangquan Thermoelectricity Co Ltd [100%] Huasheng Jiangquan Group Co Ltd [95.0%]; natural person(s) [5.0%]
Unit 2 Shandong Huasheng Jiangquan Thermoelectricity Co Ltd [100%] Huasheng Jiangquan Group Co Ltd [95.0%]; natural person(s) [5.0%]

Project-level coal details

  • Coal source(s): 大同矿区山西中煤杨涧煤业有限公司和大同煤矿集团轩岗煤电有限责任公司提供
  • Permit(s): 鲁发改能源〔2017〕51号[1]

Ownership Tree

This ownership tree is part of the Global Energy Ownership Tracker, a project of Global Energy Monitor.

Background on Project

Huasheng Jiangquan cogen power station is a proposed 2 x 350 MW coal plant in Xishantou Village, Luozhuang District, sponsored by Huasheng Jiangquan Group.[2]

Construction was reported in January 2017,[3] however satellite photos through May 2018 show no construction, and a meeting to discuss preliminary work on the project was held in May 2018,[4] suggesting construction is still planned but has yet to begin.

Construction was reported in March 2019.[5]

Articles and Resources

References

  1. http://fgw.shandong.gov.cn/art/2017/3/16/art_102383_7446063.html. {{cite web}}: Missing or empty |title= (help)
  2. "华盛江泉集团2×350MW热电联产项目社会稳定风险评估会议召开," Huasheng Jiangquan Group, accessed Nov 2016
  3. "华盛江泉集团2×35万千瓦热电联产项目奠基," 凤凰网资讯, Jan 27, 2017
  4. "华盛江泉集团2×350MW热电联产项目初步设计审查会议召开," Huasheng Jiangquan Group, 2018-05-24
  5. "预算投资30亿!罗庄一热电联产项目开工建设," 致远天宸府, 2019年03月28日