Jawa-6 power station

From Global Energy Monitor

Jawa-6 power station is a power station in Muara Gembong, Bekasi, Jawa, Indonesia with multiple units of varying statuses, none of which are currently operating. It is also known as 爪哇6号电站.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Jawa-6 power station Muara Gembong, Bekasi, Jawa, Indonesia -5.935064, 107.030182 (approximate)
Loading map...

Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology Start year Emergency/Backup
New 1 Announced[1] fossil gas: LNG[1] 1000[1] combined cycle[1] 2034 (planned)[1] no
Unit 1 Cancelled coal: unknown 1000 supercritical 2027 no
Unit 2 Cancelled coal: unknown 1000 supercritical 2027 no

CHP is an abbreviation for Combined Heat and Power. It is a technology that produces electricity and thermal energy at high efficiencies. Coal units track this information in the Captive Use section when known.

Table 3: Unit-level ownership and operator details

Unit name Owner Parent
New 1 PT PLN (Persero) [100%] PT PLN (Persero) [100.0%]
Unit 1 PT PLN (Persero) [100%] PT PLN (Persero) [100.0%]
Unit 2 PT PLN (Persero) [100%] PT PLN (Persero) [100.0%]

Ownership Tree

This ownership tree is part of the Global Energy Ownership Tracker, a project of Global Energy Monitor.

Background

PLN's 2014 long-range plan shows the development of Jawa-5 and Jawa-6 coal-fired power plants, totaling four 1,000-MW coal-fired units, being built in West Java Province. The project is shown on a map contained in PLN's long-range plan, which shows it located near the Babalam. In the plan, the four units are scheduled for completion in 2018, 2019, 2020, and 2021.[2]

PLN's 2015-2024 plan lists Jawa-6 as completed in 2023.[3]

PLN's 2016-2025 plan lists Jawa-6 as completed in 2025.[4]

PLN's 2017-2026 plan lists Jawa-6 as completed in 2023 and 2024.[5]

PLN's 2018-2027 plan defers the completion of Jawa-6 until after 2027, effectively shelving it.[6] PLN's 2021-2030 plan did not list the project. With no progress in more than four years, it appears to be cancelled.

Financing

In May 2017, DBS was appointed the financial adviser for the project.[7]

Articles and Resources

References

  1. ↑ 1.0 1.1 1.2 1.3 1.4 (PDF) https://web.archive.org/web/20260311161557/https://gatrik.esdm.go.id/assets/uploads/download_index/files/b967d-ruptl-pln-2025-2034-pub-.pdf. Archived from the original (PDF) on 2026-03-11. {{cite web}}: Missing or empty |title= (help)
  2. ↑ “PLN Long Term Electricity Plan (2013-2023),” presentation by Moch. Sofyan, Head of New & Renewable Division of PT PLN (Persero), 06 March 2014
  3. ↑ "Executive Summary: Electricity Supply Business Plan, PT PLN (Persero) 2015-2014,"
  4. ↑ “Rencana Usaha Penyediaan Tenaga Listrik, PT PLN (Persero), 2016-2025,” Kementerian Energi Dan Sumber Daya Mineral, June 2016
  5. ↑ Rencana Usaha Penyediaan Tenaga Listrik (RUPTL) 2017-2026, PT PLN Persero, p. VI-54
  6. ↑ Rencana Usaha Penyediaan Tenaga Listrik (RUPTL) 2018-2027, PT PLN Persero, Table 5.3, V-5
  7. ↑ "PLN selects financial adviser for Java 6 coal-fired | News | IJGlobal". ijglobal.com. Retrieved 2020-11-05.

Additional data

To access additional data, including interactive maps of the power stations, downloadable datasets, and summary data, please visit the Global Coal Plant Tracker and the Global Oil and Gas Plant Tracker on the Global Energy Monitor website.