Jiangsu Guoxin Shazhou power station (江苏国信沙洲发电项目) is an operating power station of at least 2000-megawatts (MW) in Zhangjiagang, Suzhou, Jiangsu, China.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Jiangsu Guoxin Shazhou power station Zhangjiagang, Suzhou, Jiangsu, China 31.985654, 120.684419 (exact)[1]
Loading map...

Unit-level coordinates (WGS 84):

  • Unit 1, Unit 2: 31.985654, 120.684419

Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology Start year Emergency/Backup
Unit 1 Operating[2] coal: unknown[3][4] 1000[4] ultra-supercritical[4] 2025[2] False
Unit 2 Operating[5] coal: unknown[3][4] 1000[4] ultra-supercritical[4] 2025[5] False

Table 3: Unit-level ownership and operator details

Unit name Owner Parent
Unit 1 Jiangsu Guoxin Shazhou Power Generation Co Ltd [100%][6] Jiangsu Guoxin Corp Ltd [51.0%]; Wintime ENERGY Group Co Ltd [15.0%]; Zhangjiagang State Owned Capital Investment Group Co Ltd [15.0%]; Suzhou Urban Construction Investment Development Co Ltd [13.8%]; unknown [5.2%]
Unit 2 Jiangsu Guoxin Shazhou Power Generation Co Ltd [100%][6] Jiangsu Guoxin Corp Ltd [51.0%]; Wintime ENERGY Group Co Ltd [15.0%]; Zhangjiagang State Owned Capital Investment Group Co Ltd [15.0%]; Suzhou Urban Construction Investment Development Co Ltd [13.8%]; unknown [5.2%]

Project-level coal details

  • Coal source(s): domestic/imported

Ownership Tree

This ownership tree is part of the Global Energy Ownership Tracker, a project of Global Energy Monitor.

Background

This 2 x 1,000 MW ultra-supercritical coal-fired power plant is one of the three "establish first and then reform" projects to provide a clean, efficient and supportive power supply to Jiangsu province.[7]

The power station would be on the southwest side of Zhangjiagang Shazhou power station.

Permission to build was granted on 28 October 2022 by Jiangsu Provincial Development and Reform Commission (苏发改能源发〔2022〕1250号, portal update timestamp: 2023/01/16).[8] It was reported the construction for this plant may have begun on November 25, 2022 but concrete was poured into the foundation of the main structure at the end of June 2023, which indicates construction officially began.[9][10]

As of May 2023, EPC information for Jiangsu Guoxin Shazhou power station was available. The project was slated for operation in 2025.[11]

In October 2023, a ceremony of concrete pouring for Unit 1 was held[12]. In December 2023, the first boiler steel frame was erected[13].

In May 2024, the main plant structure was completed[14]. In June 2024, the boiler header was lifted[15].

In February 2025, the generator rotor for Unit 1 was inserted[16]. In March 2025, the generator stator was positioned[17]. In July 2025, Unit 1 achieved grid connection[18].

In August 2025, Unit 1 completed its 168‑hour trial run[19].

In September 2023, the first boiler steel frame for Unit 2 was erected[20].

In March 2024, the boiler heating surface was lifted[21]. In May 2024, the high‑pressure heater was positioned[22].

In June 2025, Unit 2 achieved grid connection[23].

In July 2025, Unit 2 completed its 168‑hour trial run[24].

Articles and Resources

References

  1. https://mp.weixin.qq.com/s/r2n5ZeaKSRq7qeZM0hmuWQ. {{cite web}}: Missing or empty |title= (help)
  2. 2.0 2.1 https://news.bjx.com.cn/html/20250827/1457874.shtml. {{cite web}}: Missing or empty |title= (help)
  3. 3.0 3.1 https://www.gem.wiki/Coal_source_methodology_for_the_Global_Coal_Plant_Tracker. {{cite web}}: Missing or empty |title= (help)
  4. 4.0 4.1 4.2 4.3 4.4 4.5 https://www.stcn.com/article/detail/715990.html. {{cite web}}: Missing or empty |title= (help)
  5. 5.0 5.1 https://mp.weixin.qq.com/s/FhsYVpNEcEe7-JPev2jAdg. {{cite web}}: Missing or empty |title= (help)
  6. 6.0 6.1 https://news.bjx.com.cn/html/20221009/1259151.shtml. {{cite web}}: Missing or empty |title= (help)
  7. "国信沙洲2×100万千瓦煤电项目最新进展!江苏国信拟设立合资公司!". 北极星火力发电网. 2022-10-09. Retrieved 2023-02-06.{{cite web}}: CS1 maint: url-status (link)
  8. "苏发改能源发〔2022〕1250号". 江苏省发展和改革委员会行政许可和行政处罚信息公示专栏. 2023/01/16. Retrieved 2023-08-15. {{cite web}}: Check date values in: |date= (help)CS1 maint: url-status (link)
  9. "中国能建江苏院设计的国信沙洲支撑性电源项目开工". 中国能建网站. 2022-12-01. Retrieved 2023-02-06.{{cite web}}: CS1 maint: url-status (link)
  10. "国信沙洲2×1000MW机组扩建项目主体工程首砼浇筑!". 北极星电力网. 2023-06-29. Retrieved 2023-8-15. {{cite web}}: Check date values in: |access-date= (help)CS1 maint: url-status (link)
  11. 拟在建电厂项目推荐(05月10日), mp.weixin.qq.com, 2023-05-09
  12. "国信沙洲2×100万千瓦机组扩建项目#1机主厂房首砼浇筑仪式举行". WeChat. 2023-10-30. Retrieved 2026-07-21.{{cite web}}: CS1 maint: url-status (link)
  13. "国信沙洲2×100万千瓦机组扩建项目#1锅炉首根钢架顺利吊装就位". WeChat. 2024-04-12. Retrieved 2026-07-21.{{cite web}}: CS1 maint: url-status (link)
  14. "国信沙洲2×1000MW机组扩建工程项目主厂房A排结构施工到顶". WeChat. 2024-06-13. Retrieved 2026-07-21.{{cite web}}: CS1 maint: url-status (link)
  15. "国信沙洲2×100万千瓦机组扩建项目1号锅炉大板梁顺利吊装". WeChat. 2024-07-09. Retrieved 2026-07-21.{{cite web}}: CS1 maint: url-status (link)
  16. "国信沙洲电厂2×1000MW机组扩建工程项目发电机穿转子完成". BJX. 2025-02-19. Retrieved 2026-07-21.{{cite web}}: CS1 maint: url-status (link)
  17. "国信沙洲2×100万千瓦机组扩建工程1号机组发电机定子吊装就位". BJX. 2025-04-09. Retrieved 2026-07-21.{{cite web}}: CS1 maint: url-status (link)
  18. "江苏国信沙洲电厂2×100万千瓦机组扩建项目1号机组首次并网一次成功". WeChat. 2025-08-04. Retrieved 2026-07-21.{{cite web}}: CS1 maint: url-status (link)
  19. "江苏国信沙洲发电有限公司第二台100万千瓦机组完成168小时满负荷试运行". BJX. 2025-08-27. Retrieved 2026-07-21.{{cite web}}: CS1 maint: url-status (link)
  20. "国信沙洲电厂2×1000MW扩建工程2号锅炉钢结构首根钢架顺利完成吊装". WeChat. 2023-12-07. Retrieved 2026-07-21.{{cite web}}: CS1 maint: url-status (link)
  21. "国信沙洲电厂2×1000MW机组扩建工程项目2号锅炉首片受热面吊装就位". WeChat. 2024-04-12. Retrieved 2026-07-21.{{cite web}}: CS1 maint: url-status (link)
  22. "江苏国信沙洲2×1000MW高效清洁燃煤发电项目2号机组首台高压加热器顺利吊装就位". WeChat. 2024-06-13. Retrieved 2026-07-21.{{cite web}}: CS1 maint: url-status (link)
  23. "国信沙洲2台1000兆瓦机组扩建工程2号机组首次并网一次成功". WeChat. 2025-07-07. Retrieved 2026-07-21.{{cite web}}: CS1 maint: url-status (link)
  24. "国信沙洲百万千瓦煤电项目2号机组顺利通过168小时试运行". WeChat. 2025-07-30. Retrieved 2026-07-21.{{cite web}}: CS1 maint: url-status (link)

Additional data

To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.