Jiantao Cogen power station (建滔(衡阳)实业有限公司热电联产) is a power station under construction in Songmu Town, Shigu District, Hengyang, Hunan, China.
Location
Table 1: Project-level location details
Plant name | Location | Coordinates (WGS 84) |
---|---|---|
Jiantao Cogen power station | Songmu Town, Shigu District, Hengyang, Hunan, China | 26.99216, 112.643208 (exact) |
The map below shows the exact location of the power station.
Unit-level coordinates (WGS 84):
- Unit 1: 26.99216, 112.643208
Project Details
Table 2: Unit-level details
Unit name | Status | Fuel(s) | Capacity (MW) | Technology | Start year | Retired year |
---|---|---|---|---|---|---|
Unit 1 | construction | coal - unknown | 60 | subcritical | – | – |
Table 3: Unit-level ownership and operator details
Unit name | Owner |
---|---|
Unit 1 | Hengyang King Board Chemical Co Ltd [100.0%] |
Background
The Jiantao Cogen power station was proposed by the Jiantao Chlor Alkali company in 2017. The site selected for the project is located within the industrial land range defined in the "Master Plan of the Songmu Township, Shigu District, Hengyang City (2015-2020)," which meets the requirements of the town's master plan.[1] It was proposed to replace the existing coal-fired boilers in the chemical-processing facility it will power.[2] It is estimated to have an annual power generation capacity of approximately 509.9×106 kilowatt-hours (kWh).[3]
In 2019, after a total investment of 900 million yuan, the Hengyang News Network stated that the preliminary procedures for the plant's construction have been completed, and land acquisition and relocation are underway.[4]
Articles and Resources
References
- ↑ "建滔(衡阳)热电联产项目选址松木经开区 规划用地约11公顷". 每日头条. January 5, 2017. Retrieved May 26, 2021.
{{cite web}}
: CS1 maint: url-status (link) - ↑ "建滔(衡阳)实业有限公司热电联产项目". Ixbang. May 23, 2017. Retrieved May 26, 2021.
{{cite web}}
: CS1 maint: url-status (link) - ↑ "建滔(衡阳)实业有限公司热电联产项目". Ixbang. March 2, 2017. Retrieved May 26, 2021.
{{cite web}}
: CS1 maint: url-status (link) - ↑ "壮丽70年 奋斗新时代--中部崛起时 建滔集团:七大项目推进势如虹". 衡阳新闻联播. June 2, 2019. Retrieved May 26, 2021.
{{cite web}}
: CS1 maint: url-status (link)
Additional data
To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.