Jilin Dongfang power station
| Part of the Global Coal Plant Tracker, a Global Energy Monitor project. |
| Related coal trackers: |
Jilin Dongfang power station (吉林市亿斯特能源有限公司, 吉林市怡东热电有限公司整体搬迁工程, 吉林市东方电力公司整体搬迁新建发电厂) is an operating power station of at least 150-megawatts (MW) in Changyi, Jilin, China. It is also known as Jilin Dongguan power station relocation project 东关热电厂.
Location
Table 1: Project-level location details
| Plant name | Location | Coordinates (WGS 84) |
|---|---|---|
| Jilin Dongfang power station | Changyi, Jilin, Jilin, China | 43.85622, 126.585371 (exact)[1] |
Unit-level coordinates (WGS 84):
- New Unit 1: 43.85622, 126.585371
- New Unit 2, New Unit 3: 43.8423213, 126.613131
Project Details
Table 2: Unit-level details
| Unit name | Status | Fuel(s) | Capacity (MW) | Technology | CHP | Emergency/Backup |
|---|---|---|---|---|---|---|
| New Unit 1 | Operating[2] | coal: bituminous[3][1] | 50[1] | subcritical[1] | yes[1] | False |
| New Unit 2 | Operating[2] | coal: bituminous[3][1] | 50[1] | subcritical[1] | yes[1] | False |
| New Unit 3 | Operating[2] | coal: bituminous[3][1] | 50[1] | subcritical[1] | yes | False |
Table 3: Unit-level ownership and operator details
| Unit name | Owner | Parent |
|---|---|---|
| New Unit 1 | Jilin Dongfang Electric Power Co Ltd [100%][1] | Jilin Hongze Investment Co Ltd [100.0%] |
| New Unit 2 | Jilin Dongfang Electric Power Co Ltd [100%][1] | Jilin Hongze Investment Co Ltd [100.0%] |
| New Unit 3 | Jilin Dongfang Electric Power Co Ltd [100%][1] | Jilin Hongze Investment Co Ltd [100.0%] |
Project-level coal details
- Coal source(s): unknown
Ownership Tree
This ownership tree is part of the Global Energy Ownership Tracker, a project of Global Energy Monitor.
Background
Jilin Dongguan cogen power station located in 99 Liaobei Road, Changyi District Jilin City. It was built between 1997 and 2011 with four units totalling 74 megawatt of power capacity and supplying electricity to the Changyi district in the city of Jilin. [4] The operating company is Jilin Dongguan Thermal Power Company.[5]
A relocation project of Jilin Dongguan power station with three units of 50 MW each was announced in January 2020 as part of Jilin Province Energy Administration's plan for the upcoming year, along with eleven other thermal power projects.[6] It was approved in December 2020, for a total investment of 1.4 billion RMB (217 thousand USD).[7][8] The new location is in Fengman District of Jilin City, Jiangnan Town, Yong'an village. [9]
Construction was said to begin in June 2021; however, no confirmation of construction has been released.[8]
In March 2023, the project approval was extended to 29 December 2023[10]. Construction likely started in the second half of 2023.
By late 2024, satellite imagery showed the plant was in operation. The plant was renamed to 吉林市亿斯特能源有限公司[11]. Status changed to operating from second half of 2024.
Articles and Resources
References
- ↑ 1.00 1.01 1.02 1.03 1.04 1.05 1.06 1.07 1.08 1.09 1.10 1.11 1.12 1.13 1.14 https://jldrc.jl.gov.cn/zfgk/zdjsxm/jggs/202302/t20230227_8672854.html.
{{cite web}}: Missing or empty|title=(help) - ↑ 2.0 2.1 2.2 http://www.jlcity.gov.cn/yw/jcyw/202510/t20251014_1290567.html.
{{cite web}}: Missing or empty|title=(help) - ↑ 3.0 3.1 3.2 https://www.gem.wiki/Coal_source_methodology_for_the_Global_Coal_Plant_Tracker.
{{cite web}}: Missing or empty|title=(help) - ↑ "吉林市东关热电厂三期扩建工程建设项目环保设施竣工验收监测报告" (PDF). 吉林省生态环境厅. 2017-07-18.
{{cite web}}: CS1 maint: url-status (link) - ↑ "吉林市东关热电有限责任公司". www.qcc.com.
{{cite web}}: CS1 maint: url-status (link) - ↑ "名单 | 吉林省规划建设12个热电项目! - 北极星火力发电网". BJX News. 2020-01-13. Retrieved 2021-07-30.
{{cite web}}: CS1 maint: url-status (link) - ↑ "吉林市东方电力有限责任公司整体搬迁工程核准的批复 - 北极星火力发电网". BJX News. 2020-12-29. Retrieved 2021-07-30.
{{cite web}}: CS1 maint: url-status (link) - ↑ 8.0 8.1 "总投资超14亿元!"东关热电厂"要搬迁了 - 北极星火力发电网". BJX News. 2021-01-29. Retrieved 2021-07-30.
{{cite web}}: CS1 maint: url-status (link) - ↑ "建设项目用地预审与选址意见书 -吉林市东方电力公司整体搬迁工程". ghzr.jlcity.gov.cn. 2021-08-11.
{{cite web}}: CS1 maint: url-status (link) - ↑ "吉林市怡东热电有限公司整体搬迁工程核准文件有效期延期至2023年12月29日". BJX. 2023-03-06. Retrieved 2026-07-21.
{{cite web}}: CS1 maint: url-status (link) - ↑ "胡斌检查我市冬季供热保障工作". 吉林市人民政府. 2025-10-14. Retrieved 2026-07-21.
{{cite web}}: CS1 maint: url-status (link)
Additional data
To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.