Jinchang Tengger power station

From Global Energy Monitor
Part of the
Global Coal Plant Tracker,
a Global Energy Monitor project.
Download full dataset
Report an error
Related coal trackers:

Jinchang Tengger power station (甘肃腾格里沙漠河西新能源基地配套金昌2×1000兆瓦调峰煤电项目, 华电金昌腾格里发电厂) is a power station under construction in Hexipu, Yongchang, Jinchang, Gansu, China.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Jinchang Tengger power station Hexipu, Yongchang, Jinchang, Gansu, China 38.364337, 102.097343 (exact)[1]
Loading map...

Unit-level coordinates (WGS 84):

  • Unit 1, Unit 2: 38.364337, 102.097343

Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology Emergency/Backup
Unit 1 Construction[2][3] coal: unknown[4][3] 1000[3] ultra-supercritical[3] False
Unit 2 Construction[2][3] coal: unknown[4][3] 1000[3] ultra-supercritical[3] False

Table 3: Unit-level ownership and operator details

Unit name Owner Parent
Unit 1 Huadian Gansu Energy Co Ltd [100%][1] China Huadian Corp Ltd [52.4%]; Huadian Power International Co Ltd [31.0%]; unknown [16.6%]
Unit 2 Huadian Gansu Energy Co Ltd [100%][1] China Huadian Corp Ltd [52.4%]; Huadian Power International Co Ltd [31.0%]; unknown [16.6%]

Project-level coal details

  • Coal source(s): domestic

Ownership Tree

This ownership tree is part of the Global Energy Ownership Tracker, a project of Global Energy Monitor.

Background

As one of the peak-shaving supporting power sources for the Hexi clean energy base in the Tengger Desert, the Gansu Huadian Jinchang Tengger 2×1000MW coal power project started the project preparation stage in 2023. The call for the project environmental impact assessment was released on 1 February 2023[5] and the call for feasibility study design was announced at the end of March[6].

Major equipment contracts were awarded in early 2024[7]. By September 2024, construction officially commenced with excavation[8]. Equipment procurement and construction tenders continued through 2025[9].

In 2025, significant progress included boiler beam hoisting, cooling tower column work, and boiler heating surface placement[10][11]. In October 2025, Unit 2 boiler steel hoisting and other activities advanced.

In 2026, generator rotor placement for Unit 1 occurred in March[12], Unit 2 generator stator placement in March[13], and power transmission was achieved in June 2026[14].

Articles and Resources

References

  1. 1.0 1.1 1.2 https://slt.gansu.gov.cn/slt/c209640/202403/173878249.shtml. {{cite web}}: Missing or empty |title= (help)
  2. 2.0 2.1 https://mp.weixin.qq.com/s/F1V9NwFf4Z4Gj8bEGFiNQA. {{cite web}}: Missing or empty |title= (help)
  3. 3.0 3.1 3.2 3.3 3.4 3.5 3.6 3.7 "2×1000MW!甘肃华电金昌腾格里煤电项目可行性研究阶段勘察设计招标-北极星火力发电网". news.bjx.com.cn. 2023-03-30. Archived from the original on 2024-01-25. Retrieved 2023-10-12.
  4. 4.0 4.1 https://www.gem.wiki/Coal_source_methodology_for_the_Global_Coal_Plant_Tracker. {{cite web}}: Missing or empty |title= (help)
  5. 永昌县发展和改革局 (2023-02-27). "甘肃华电金昌腾格里2×1000MW煤电项目环评第一次信息公示". 北极星火力发电网.{{cite web}}: CS1 maint: url-status (link)
  6. "甘肃华电金昌腾格里2×1000MW煤电项目可行性研究阶段勘察设计招标公告". 中国电力招标采购网. 2023-03-29.{{cite web}}: CS1 maint: url-status (link)
  7. "华电金昌2×1000兆瓦调峰煤电项目三大主机中标结果公示". 微信公众平台. 2024-01-05. Retrieved 2024-01-05.{{cite web}}: CS1 maint: url-status (link)
  8. "甘肃腾格里沙漠河西新能源基地配套金昌2×1000兆瓦调峰煤电项目烟囱基础开挖". 北极星电力网. 2024-09-17. Retrieved 2024-09-19.{{cite web}}: CS1 maint: url-status (link)
  9. "甘肃金昌2×1000兆瓦调峰煤电项目第二批辅机设备采购招标". 北极星电力网. 2024-10-12. Retrieved 2024-10-17.{{cite web}}: CS1 maint: url-status (link)
  10. "金昌2×1000兆瓦调峰煤电项目建设工程1号锅炉大板梁正式开吊". 微信公众平台. 2025-05-19. Retrieved 2025-05-27.{{cite web}}: CS1 maint: url-status (link)
  11. "甘肃华电金昌2×1000兆瓦调峰煤电项目1号锅炉受热面首片吊装就位". 微信公众平台. 2025-06-08. Retrieved 2025-06-19.{{cite web}}: CS1 maint: url-status (link)
  12. "甘肃华电金昌2x1000MW调峰煤电项目1号机组发电机转子穿装顺利完成". 微信公众平台. 2026-03-20. Retrieved 2026-04-09.{{cite web}}: CS1 maint: url-status (link)
  13. "金昌2×1000兆瓦调峰煤电项目#2机组发电机定子顺利吊装就位". 微信公众平台. 2026-03-25. Retrieved 2026-04-09.{{cite web}}: CS1 maint: url-status (link)
  14. "甘肃腾格里沙漠河西新能源基地配套金昌调峰煤电项目2号机组倒送电一次成功". 微信公众平台. 2026-06-26. Retrieved 2026-07-13.{{cite web}}: CS1 maint: url-status (link)

Additional data

To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.