Juhua Quzhou Complex power station (衢州巨化热电厂) is an operating power station of at least 375-megawatts (MW) in Huayuan Town Huayuan Village, Kecheng, Quzhou, Zhejiang, China. It is also known as 巨宏热电 (Unit 9).

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Juhua Quzhou Complex power station Huayuan Town Huayuan Village, Kecheng, Quzhou, Zhejiang, China 28.9022094, 118.8811483 (exact)

The map below shows the exact location of the power station.

Loading map...


Unit-level coordinates (WGS 84):

  • Unit 10, Unit 11, Unit 6, Unit 7, Unit 8, Unit 9: 28.9022094, 118.8811483

Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology Start year Retired year
Unit 10 operating coal - bituminous 30 subcritical 2015
Unit 11 operating coal - bituminous 30 subcritical 2021
Unit 6 operating coal - bituminous 60 subcritical 1991
Unit 7 operating coal - bituminous 60 subcritical 1996
Unit 8 operating coal - bituminous 60 subcritical 2001
Unit 9 operating coal - bituminous 135 unknown 2006

Table 3: Unit-level ownership and operator details

Unit name Owner
Unit 10 Juhua Group Co. Thermoelectricity Factory [100.0%]
Unit 11 Juhua Group Co. Thermoelectricity Factory [100.0%]
Unit 6 Juhua Group Co. Thermoelectricity Factory [100.0%]
Unit 7 Juhua Group Co. Thermoelectricity Factory [100.0%]
Unit 8 Juhua Group Co. Thermoelectricity Factory [100.0%]
Unit 9 Juhua Group Co. Thermoelectricity Factory [100.0%]

Project-level captive use details

  • Captive industry use (heat or power): chemicals
  • Captive industry: Both

Background

The Juhua Quzhou Complex power station was originally built in 1958 by the Juhua Group. The steam and electricity from the plant powers the chemical manufacturing/processing park it is located in. The total investment of the plant exceeds 300 million RMB (46.4 million USD). The plant supplies 351 million kilowatt-hours of electricity per year as well.

In 2014, the Juhua Group spent over 300 million RMB investing in environmental protection technologies, including desulfurization, denitrification, and dust removal units.[1]

In 2020, it was announced that a new unit, Unit 11, was under construction, along with several other projects funded by the Juhua Group. While there was no specific number for the investment into Unit 11, the total capital investment for these projects combined was three billion RMB.[2] As of 2023, Unit 11 was described as operating.[3]

Articles and Resources

References

  1. "专家:煤改气无助于控制氮氧化物排放 - 分析测试百科网". m.antpedia.com (in 中文(中国大陆)). 2014-06-26. Retrieved 2021-08-03.{{cite web}}: CS1 maint: url-status (link)
  2. "巨化集团斥资15亿元 上马重大公用配套项目". wap.qz96811.com. 2020-09-02. Retrieved 2021-08-03.{{cite web}}: CS1 maint: url-status (link)
  3. 【聘】浙江巨化热电2022校园3招聘, http://ccutchi.hjiuye.com/, 2023-05-09

Additional data

To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.