Kamalanga power station

From Global Energy Monitor
Part of the
Global Coal Plant Tracker,
a Global Energy Monitor project.
Download full dataset
Report an error
Related coal trackers:

Kamalanga power station is an operating power station of at least 1050-megawatts (MW) in Kamalanga, Odapada, Dhenkanal, Odisha, India with multiple units, some of which are not currently operating.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Kamalanga power station Kamalanga, Odapada, Dhenkanal, Odisha, India 20.870576, 85.266979 (exact)

The map below shows the exact location of the power station.

Loading map...


Unit-level coordinates (WGS 84):

  • Phase I Unit 1, Phase I Unit 2, Phase I Unit 3, Phase II Unit 4: 20.870576, 85.266979

Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology Start year Retired year
Phase I Unit 1 operating coal - bituminous 350 subcritical 2013
Phase I Unit 2 operating coal - bituminous 350 subcritical 2013
Phase I Unit 3 operating coal - bituminous 350 subcritical 2014
Phase II Unit 4 pre-permit coal - unknown 350 subcritical

Table 3: Unit-level ownership and operator details

Unit name Owner
Phase I Unit 1 GMR Energy Ltd [100.0%]
Phase I Unit 2 GMR Energy Ltd [100.0%]
Phase I Unit 3 GMR Energy Ltd [100.0%]
Phase II Unit 4 GMR Energy Ltd [100.0%]

Project-level coal details

  • Coal source(s): Rampia coal blocks, Ib Valley
  • Permit(s): February 5, 2008 – Environmental Clearance, November 30, 2022 – Environmental Clearance Extension; Fresh Terms of Reference: 2024-01-06; Environmental Clearance Extension: 2019-04-11[1][2]

Background

Kamalanga power station is proposed by a GMR Energy subsidiary, GMR Kamalanga Energy Ltd. It would consist of four 350 MW units built in two phases: 3x350 MW and 1x350 MW, respectively, for a total of 1400MW. GKEL would supply power to Odisha, Bihar, Haryana and other parts of the country.[3][4]

Phase 1: 1050 MW

The first two units (350 MW each) were commissioned in 2013.[5]

The third unit (350 MW) went into operation on March 25, 2014.[6]

Phase II: 350 MW addition

On December 5, 2011, the Ministry of Environment and Forests (MoEF) approved the fourth 350 MW unit at the same location. GMR Energy said no additional land will be required for the expansion. The company will use imported coal until indigenous coal linkage is obtained. Coal will be imported from Indonesia. A public hearing was held on March 30, 2011.[7]

As of February 2015, phase II has not entered construction and did not have a planned commissioning date.[8]

On April 11, 2019, the environmental clearance for phase II was extended. The unit was planned for commissioning in 2023.[9]

With no known updates on the project, the unit was presumed shelved.

In 2022, GMR Kamalanga Energy Limited requested for extension of validity of the Environmental Clearance (EC) for 5 more years, so the project was presumed revived. On November 30, 2022, the government's Expert Appraisal Committee recommended the extension to start operation for one year, or until December 3, 2023.[10]

According to the company's application, "[t]he lone unit of 1 X 350 MW was already executed for more than 60% progress in overall Project Works and 90% of Civil work including chimney construction," but was delayed for various reasons.[11][12]

As of January 2023, the company's website did not provide any details about the expansion.[13]

The three existing units were clear in Planet satellite imagery from 2016 through 2022, but the development of the fourth unit was unclear. Although the unit was reportedly under construction, it was simply presumed as re-permitted. Based on project plans (pptx file), the fourth unit was planned for east of the existing facility:

Image from 1111161224121859267234EACPresentationCompressed.png

As of October 2023, it remained unclear whether construction of Unit 4 had yet begun; Planet imagery from October 2022 to October 2023 did not show clear signs of construction or site development, and India's Broad Status reports of thermal power projects under construction did not indicate that construction had started.[14]

In the meeting minutes of the Expert Appraisal Committee's October/November meeting, it was noted that GMR Kamalanga Energy had applied for fresh Terms of Reference for the expansion, due to its previous EC's expiration.[15] According to the meeting minutes, the committee had recommended the grant of Terms of Reference. In the November 2023 meeting minutes of the Expert Appraisal Committee, it was noted that the committee recommended the deletion of a sub-clause in the unit's ToR regarding the implementation of a socio-economic study for the new unit.[16] Considering the ongoing re-permitting process for Unit 4, construction had presumably not yet begun by the end of 2023.

Financing for Phase I and II

In May 2009, a financing agreement for phase I and II was closed. US$721.73 million in loans was provided by State Bank of India, Punjab & Sind Bank, Corporation Bank, Andhra Bank, United Bank of India, Uco Bank, Indian Bank, Infrastructure Development Finance Company, Central Bank of India, Bank of Baroda, Canara Bank, IDBI Bank, and State Bank of India. US$240.57 million in equity was provided by GMR Group and Infrastructure Development Finance Company.[17]

In June 2015, a refinancing agreement for phase I was closed. US$518.21 million in loans was provided by State Bank of India, Indian Bank, Bank of Baroda, Canara Bank, State Bank of Mysore, Central Bank of India, Corporation Bank, IDBI Bank, United Bank of India, Punjab & Sind Bank, and Uco Bank. SBI Capital Markets acted as financing adviser to the sponsors.[18]

Sell-off abandoned

In August 2020, the Indian power utility JSW Energy announced that it had called off its deal to acquire the 1,050 MW Kamalanga power station project in Odisha after entering into exclusive talks with GMR Energy to buy it in October 2019, and then signing a purchase agreement in February 2020. The company is aiming to be carbon neutral by 2050 and will instead focus on renewable energy. Speaking to India's Economic Times, JSW's CEO Prashant Jain explained why the company was abandoning its plan to expand its thermal power capacity through acquisitions: "“We have realised that many of these existing thermal assets have ongoing litigations and the government is increasing taxes on polluting industries, so it will be a continuous struggle for the next 15-20 years for the balance life of the plant. Given all this, renewables is a better option.”[19]

Opposition

According to Bank Information Center, members of MASS filed a complaint formally challenging IFC’s funding for the GMR Kamalanga Energy Limited. According to the BIC:[20]

After months of independent research and connecting the dots, complainants discovered a can of worms that IFC and its client are hiding.
One, IFC does not want the public to know that its FI investment is located in a Revenue Block that the Ministry of the Environment classifies as 7th of the 88 most polluted hot spots in the country. The project site is highly uninhabitable as industrial wastes that run into the water streams contain highly deadly fluorine. In 2010, the Environmental Ministry issued a moratorium for constructing new projects in the area.
Had this been a direct IFC investment, safeguards check and risk mitigation such as environmental impact assessment, pollution abatement and community health and safety should have applied. But by concealing the basic information from the public, IFC is seen to be perpetuating the disasters now engulfing the agricultural and water resources of tribal, dalit and poor farming communities.
Amulya Nayak, Convenor of the Odisha Chas Parivesh Surekhsa Parishad (Parishad) and complainant to CAO revealed: “The company never shows any regard for community health. It ignores villagers’ requests to not dump its garbage to adjacent agricultural lands. GKEL employs dynamite blasting at the project site, which causes cracks in nearby houses and primary school building. Project also extracts huge water volume and we witness in our bore wells the depleting water level, which is the main source of drinking, cooking and washing for thousands of families.”
Two, the IFC holds back facts about the economic displacement resulting from this FI loan. Although public hearing is legally mandated for any kind of land acquisition process in India, the company did not comply with it prior to constructing the plant. GKEL acquired 1200 acres of mostly prime agricultural land irrigated by the Rengali Canal System.
The 900 acres private land acquired used to feed and employ nearly 1,300 families in 4 villages. With no livelihood restoration plan in place and with many affected families getting no proper land compensation until today, hundreds have lost their land, crops, trees and other properties. Those economically displaced include the agricultural laborers and share croppers, the Khaira tribe and the dalit.
Three, the company, in collusion with the administration, uses force and other tactics to intimidate people. Women and men are randomly arrested and implicated in false cases. Some were beaten, tortured and intimidated by the police before their release. A climate of fear now engulfs the community as police continues with its random arrest, threats and high-handedness.
Asks Bhakta Bandhu Behera, a project affected person from Manibeda village and member of Parishad asks, “are these the types of information the IFC does not want to share with us and the greater public because it will jeopardize the interest of its client? Will the World Bank Group remain mum to safeguard its borrower? What about the real dangers we now face?”

Articles and Resources

References

  1. (PDF) https://web.archive.org/web/20240125142847/https://parivesh.nic.in/utildoc/24401228_1700034939902.pdf. Archived from the original (PDF) on 25 January 2024. {{cite web}}: Missing or empty |title= (help)
  2. (PDF) https://web.archive.org/web/20240218232936/https://parivesh.nic.in/certificates/_GMR_KAMALANGA_ENERGY_LIMITED/5/18088687/IA_OR_THE_449476_2023_18088695_-signed.pdf. Archived from the original (PDF) on 18 February 2024. {{cite web}}: Missing or empty |title= (help)
  3. "GKEL gets mega power status" Industry Monitor, December 16, 2011.
  4. "GMR Kamalanga Energy Ltd. (GKEL)", GMR Group website, accessed November 2011.
  5. Monthly Report on Broad Status of Thermal Power Projects in the Country, Central Electricity Authority, September 2013
  6. "Third unit of GMR’s Kamalanga thermal power plant operational," The Hindu, March 25, 2014.
  7. Environmental clearance letter from MoEF to Kalamanga Energy Ltd, December 5, 2011
  8. Broad Status Report, India Central Electrical Authority, February 2015
  9. Environmental Clearance extension, India MoEF, April 11, 2019
  10. "Minutes of the 33rd Meeting of the Re-Constituted Expert Appraisal Committee (EAC) on Environmental Impact Assessment (EIA) of Thermal Power Projects Held on 30th November, 2022," MoEF, November 30, 2022
  11. "Project Note and Reasons for delay in Completion of 1x350 MW Power Project," Proposal No. IA/OR/THE/75/2011
  12. "Application for Extension," Expansion by addition of 1x350 MW Imported Coal based Thermal Power Plant (Phase-II) at village Kamalanga, in Odapada Taluk, Dhenkanal District, Odisha, IA/OR/THE/293656/2022
  13. "Overview," GMR Kamalanga Energy Limited, accessed January 2023
  14. Broad Status Report of Under Construction Thermal Power Projects - August 2023, Central Electricity Authority, August 2023
  15. Minutes of 02ND Meeting of the Re-Constituted Expert Appraisal Committee (EAC) meeting - Thermal Projects held from 31/10/2023 to 01/11/2023, MoEFCC, November 15, 2023
  16. Minutes of 3RD MEETING OF THE RE-CONSTITUTED EXPERT APPRAISAL COMMITTEE (EAC) ON ENVIRONMENTAL IMPACT ASSESSMENT (EIA) meeting Thermal Projects held from 30/11/2023 to 30/11/2023, MoEFCC, December 22, 2023
  17. "Preview of GMR Kamalanga Coal-fired Power Plant (1400MW) | Transaction | IJGlobal". ijglobal.com. Retrieved 2020-10-19.
  18. "Preview of Kamalanga Power Plant Refinancing (1400MW) | Transaction | IJGlobal". ijglobal.com. Retrieved 2020-10-19.
  19. Rachita Prasad, "JSW Energy pulls the plug on thermal asset expansion, focus on green energy now", Economic Times, Aug. 3, 2020
  20. "IFC Ombudsman accepts complaint against GMR project in Odisha," Bank Information Center press release, May 13, 2011.

Additional data

To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.