Kathautia Coal Mine is an operating coal mine in Kathautia, Palamau, Jharkhand, India.

Location

Table 1: Project-level location details

Mine Name Location Coordinates (WGS 84)
Kathautia Coal Mine Kathautia, Palamau, Jharkhand, India 24.132523, 84.08231 (exact)

The map below shows the exact location of the coal mine:

Loading map...

Project Details

Table 2: Project status

Status Status Detail Opening Year Closing Year
Operating 2012

Table 3: Operation details

Note: The asterisk (*) signifies that the value is a GEM estimated figure.
Capacity (Mtpa) Production (Mtpa) Year of Production Mine Type Mining Method Mine Size (km2) Mine Depth (m) Workforce Size
0.8[1] 0.03[2] 2022[2] Surface Open Pit 4.5 60* 468*

Table 4: Coal resources and destination

Total Reserves (Mt) Year of Total Reserves Recorded Total Resources (Mt) Coalfield Coal Type Coal Grade Primary Consumer/ Destination
26.011 29.293 Daltonganj Bituminous Met

Table 5: Ownership and parent company

Owner Parent Company Headquarters
Hindalco Industries Ltd Aditya Birla Group India

Note: The above section was automatically generated and is based on data from the GEM April 2024 Global Coal Mine Tracker dataset.

Background on Mine

The Kathautia Coal Mine has a designed capacity of 0.8 MTPA on mining lease area of 938.27 ha is located in villages Kathautia, Kajri, Garikhas, Palhekhurd, Sakhui, Sika and Batsara, Tehsil Patan, District Palamau, State Jharkand, India.

The mine was first allotted to Usha Martin Limited for which the environment clearance was obtained on 19 June 2006. Usha Martin operated the mine and extracted 2.084 MT coal till 31 March 2014.[3] However, the mine was cancelled by Supreme Court in wake of the coalgate scam and further allotted by Ministry of Coal on 23 March 2015 to Hindalco Industries Limited and the Environment Clearance was trasferred on 10 June 2015[4] In FY 2017-2018 Hindalco achieved 0.80 Million Tonnes production. In FY 2018-19 it achieved 0.798. Presently the project is running with full capacity.[5]

Expansion Details

  • Status:
  • Size of Expansion:
  • Permits and Applications:

Articles and Resources

Additional data

To access additional data, including an interactive map of world coal mines, a downloadable dataset, and summary data, please visit the Global Coal Mine Tracker on the Global Energy Monitor website.

References

  1. (PDF) https://web.archive.org/web/20240124191015/https://coal.nic.in/sites/default/files/2023-06/16-06-2023-3a-sec.pdf. Archived from the original (PDF) on 24 January 2024. {{cite web}}: Missing or empty |title= (help)
  2. 2.0 2.1 (PDF) https://web.archive.org/web/20240125230149/https://coal.gov.in/sites/default/files/2023-06/opt/Minutes-of-Meeting-held-on4112022.pdf. Archived from the original (PDF) on 25 January 2024. {{cite web}}: Missing or empty |title= (help)
  3. Cite error: Invalid <ref> tag; no text was provided for refs named MC
  4. EC Transfer for Kathautia Opencast Coal Mine Project to Hindalco Industries Limited, MoEF&CC India, 16 April 2015
  5. Esuvidha portal of Ministry of Coal, accessed on March 21, 2020