Laguna Colorada geothermal power plant (Central geotérmica Laguna Colorada) is a geothermal power plant under construction in Sud Lípez, Potosí, Bolivia.

Project Details

Table 1: Unit-level project details for Laguna Colorada geothermal power plant

Unit name Status Commissioning year Nameplate capacity Technology Owner Operator
1 Construction[1] 2026 (planned)[1] 50 MW[2][3] Unknown type Empresa Nacional de Electricidad SA (ENDE) [100%][4] Empresa Nacional de Electricidad SA (ENDE)[4]
2 Construction[1] 2026 (planned)[1] 50 MW[2][3] Unknown type Empresa Nacional de Electricidad SA (ENDE) [100%][4] Empresa Nacional de Electricidad SA (ENDE)[4]

Location

Table 2: Unit-level location details for Laguna Colorada geothermal power plant

Unit name Location Coordinates (WGS 84)
1 Sud Lípez, Potosí, Bolivia[2][5] -22.4254978, -67.7499615 (exact)[2][5]
2 Sud Lípez, Potosí, Bolivia[2][5] -22.4254978, -67.7499615 (exact)[2][5]

The map below shows the exact locations of the geothermal power plant units:

Loading map...

Articles and Resources

Additional data

To access additional data, including an interactive map of global geothermal power plants, a downloadable dataset, and summary data, please visit the Global Geothermal Power Tracker on the Global Energy Monitor website.

References

  1. 1.0 1.1 1.2 1.3 https://web.archive.org/web/20240319061612/https://www.worldconstructionnetwork.com/data-insights/construction-laguna-colorada-geothermal-power-plant-100-mw/. Archived from the original on 2024-03-19. {{cite web}}: Missing or empty |title= (help)
  2. 2.0 2.1 2.2 2.3 2.4 2.5 https://web.archive.org/web/20230305002620/https://www.ende.bo/proyectos/resena/proyecto--const.-central-geotermica-de-laguna-colorada. Archived from the original on 2023-03-05. {{cite web}}: Missing or empty |title= (help)
  3. 3.0 3.1 https://web.archive.org/web/20221209030456/https://www.energias-renovables.com/geotermica/sacyr-y-ormat-se-adjudican-la-construccion-20190405. Archived from the original on 2022-12-09. {{cite web}}: Missing or empty |title= (help)
  4. 4.0 4.1 4.2 4.3 https://web.archive.org/web/20220720050257/https://www.thinkgeoenergy.com/construction-of-bolivias-first-geothermal-plant-progressing/. Archived from the original on 2022-07-20. {{cite web}}: Missing or empty |title= (help)
  5. 5.0 5.1 5.2 5.3 https://maps.app.goo.gl/zdFQjHvcQBUyfiCV8. {{cite web}}: Missing or empty |title= (help)