Lakvijaya Power Plant

From Global Energy Monitor
Part of the
Global Coal Plant Tracker,
a Global Energy Monitor project.
Download full dataset
Report an error
Related coal trackers:

Lakvijaya Power Plant is an operating power station of at least 900-megawatts (MW) in Norocholai, Puttalam, North Western, Sri Lanka with multiple units, some of which are not currently operating. It is also known as Norocholai Power Station, Puttalam Coal Plant, Norochcholai Coal Power Plant.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Lakvijaya Power Plant Norocholai, Puttalam, North Western, Sri Lanka 8.0172, 79.7225 (exact)

The map below shows the exact location of the power station.

Loading map...


Unit-level coordinates (WGS 84):

  • Unit 1, Unit 2, Unit 3, Unit 4, Unit 5: 8.0172, 79.7225

Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology Start year Retired year
Unit 1 operating coal - unknown 300 subcritical 2011 2041 (planned)
Unit 2 operating coal - unknown 300 subcritical 2014
Unit 3 operating coal - unknown 300 subcritical 2014
Unit 4 cancelled coal - unknown 300 subcritical 2025
Unit 5 cancelled coal - unknown 300 subcritical 2026

Table 3: Unit-level ownership and operator details

Unit name Owner
Unit 1 Ceylon Electricity Board (CEB) [100.0%]
Unit 2 Ceylon Electricity Board (CEB) [100.0%]
Unit 3 Ceylon Electricity Board (CEB) [100.0%]
Unit 4 Ceylon Electricity Board (CEB) [100.0%]
Unit 5 Ceylon Electricity Board (CEB) [100.0%]

Project-level coal details

  • Coal source(s): Indonesia

Background

The plant is Sri Lanka's first coal power plant and is located in Norocholai, Puttalam district, North Western province[1]

The plant's name, Lakjawiya, means Victorious Lanka in Sinhalese.[2]

The plant was reportedly first proposed to be commissioned in late 1980’s, according to the Ministry of Power and Energy. However, due to pressure from various organizations, it was kept on hold. It wasn't until 2005 - when the civil war was still raging - that President Mahinda Rajapaksha decided to press ahead with the project and enter into a contract for the project in 2006.[3]

In March 2007, the Sri Lankan government took over 300 acres at Narakkaliya and Paniadiya, displacing 68 families. While the displaced families were given houses in the Daluwa Manpuriya Nirmalapura housing scheme, they complained the new houses were poorly built. During its pre-development stages, a number of protests were launched by residents living at the project site, claiming that they were deceived by the government.[4]

The construction work for the 300 MW coal fired thermal power plant with infrastructure for a 900 MW power plant started in 2006 amid heavy resistance from the Catholic community of the area. The delivery of the first shipment of 65,500 tonnes of coal at a cost of US$7 million from Indonesia was expected in the first week of November 2010.[5]

With the end of the civil war in May 2009, the development of the power station was accelerated to cater to increased electricity demand and to reduce the outflow of foreign exchange on oil imports for power generation. Construction of Unit 2 (300 MW) was officially inaugurated by the President in March 2010.[6]

In July 2021, it was reported that CEB signed multimillion dollar deals with Chinese company without cabinet approval.[7]

In January 2023, a peer-reviewed and published article concluded that communities surrounding the power plant were "extremely exposed to threats and are highly sensitive to poverty and yet they have no adequate sets of strategies to cope and/or adapt to threats or increase their resilience."[8]

Reporting throughout 2023 noted that the power station faced continuous shut-offs and various operational issues due to a lack of engineer personnel and poor management.[9][10]

Extension

In June 2019, the Sri Lankan Cabinet floated a new draft energy plan that called for two new 300 MW units at the Lakvijaya plant.[11]

In September 2019, the Sri Lankan Cabinet granted approval to construct a new 300 MW coal plant at the Lakvijaya Plant.[12] The Sri Lankan government sought funding for the project from China, and solicited China Machinery Engineering Corporation (CMEC) to build the extension on an Engineering, Procurement, and Construction (EPC) basis. The new unit was planned for operation in 2024.[13]

In February 2020, it was reported the Chinese government would provide a soft loan of US$350 to 400 million for the fourth unit at Norochcholai. The Sri Lankan government said it would complete the feasibility study on the new unit in one month, and then put the project's construction up for competitive bidding.[14][15]

Plans for an additional unit at the power station were reaffirmed in the Ceylon Electricity Board (CEB)'s Long Term Power Generation Expansion Plan dated March 2020. The proposal was listed with a planned commissioning year of 2023. Also listed were plans for an additional 3 x 400 MW coal plant at an unspecified location.[16]

In June 2020, the Sri Lankan Cabinet approved the new unit as a joint venture with China Machinery Engineering Corporation (CMEC), saying the investment would be 50% from each side.[17] Shortly after, the CEB said it was still studying the proposed unit, and would conduct an environmental assessment and consider the other ramifications of the project. It remained unclear if CMEC would be awarded the contract sans tender.[18]

In November 2020, the Chairman of the Committee on Public Enterprises (COPE) noted the long-term plan of the plant where it was disclosed that 300 new megawatts were to be added to the power plant by 2023 and another 300 megawatts by 2026. CEB officials stated that the plant's ability to expand was being studied and that an expansions would be carried if the relevant requirements were met. It was recommended that the Central Environmental Authority (CEA) and the Provincial Environmental Authority carry out any environmental assessments jointly given the plant's importance and impacts.[19][20]

CEB's 2023-2040 Long Term Generation Expansion Plan confirmed the discontinuation of the expansion, stating that "the development of all noncommitted coal power plants identified in previous planning cycles [...] were discontinued" [21].

No New Coal announcement

In July 2021, Sri Lanka formally committed to no new coal in its updated Nationally Determined Contributions (NDC).[22]

In August 2021, perturbed by reports that the government was going to terminate the ongoing 300 MW extension project, the Ceylon Electricity Board Engineers Union (CEBEU) appealed to the President to allow the completion of "this project of national importance." Officials at the plant complex said they had not been officially informed to halt work on the plant. The extension project was reportedly underway with the China Machinery Engineering Corporation (CMEC) investing US$4 million and the Ceylon Electricity Board (CEB) US$1 million. All preliminary work – such as feasibility studies, finalizing technical requirements, Environmental Impact Assessment (EIA) studies, and commercial agreements – were reportedly completed.[23]

That month, the Public Utilities Commission of Sri Lanka (PUCSL) also instructed the CEB to submit a new Long-Term Electricity Generation Plan (LTEGP) reflecting national policy. The CEB’s LTEGP 2022-2041 included the 300 MW extension (and 300 MW of the proposed Foul Point power station).[24][25][26]

In advance of the 26th United Nations Convention on Climate Change in Glasgow (October-November 2021), Sri Lanka was among seven countries that announced a No New Coal Compact. CEB officials reportedly told AFP the decision meant a planned fourth unit at the power station "would be scrapped."[27]

The extension was presumed shelved and was likely cancelled.

In February 2023, the cancellation of the extension was confirmed by CEB's 2023-2040 Long Term Generation Expansion Plan, which included the extension in a list of plants to be discontinued by Sri Lanka's General Policy Guidelines for Electricity Industry 2021 [21].

CEB engineers continue to cast doubts

In January 2022, the CEBEU continued to stress the need for reliable power generation from energy sources such as LNG and coal for the sustainability of the country’s power sector while increasing the share of renewable power generation gradually. The Union stated: “To achieve this target, we need to increase solar from 425MW to 4000MW and wind from 250MW to 1500MW. We also need firm LNG and coal. The fourth unit of Norochcholai is just an addition of 300MW, with infrastructure already in place. We need LNG and coal cake with solar and wind as the icing." The fresh Long-Term Generation Expansion Plan (LTGEP) in compliance with the government’s renewable power generation policies was expected within the next four months.[28]

As of mid-June 2022, a revised Long-Term Generation Expansion Plan did not appear to be available. The October 2021 letter by the Public Utilities Commission of Sri Lanka (attached to the existing plan as Annex 15) stated that the updated plan must be prepared on or before June 30, 2022.[29] Though the Ceylon Electricity Board has labelled the Annex as an "approval to carry out development contained therein", an August 2021 letter from the Commission clearly stated that resubmission in line with the government policy includes "no capacity addition of coal power plants".[30]

Accidents and shutdowns

The plant has been beset with problems and shutdowns including:

  • In October 2010, a fire broke out at the plant. According to CEB officials, the fire erupted due to the clogging of a chimney that emits waste from the combustion of coal. The fire did not interrupt construction.[31] The Ministry of Power and Energy commented that damages to the facility would be borne by the constructors, and not the government or the developers.[32]
  • On July 22, 2012 the power station ceased operations due to a leak in one of the thousands of tubes carrying water between the boiler. The country was put into controlled regional power outages to cope with the missing generation.[33] Reuters reported that with the failure of the first unit - the fifth since it had been commissioned, that the CEB had determined that power cuts would be required for three hours a day until July 28. "The only alternative to resolve the current situation is to go for power cuts," CEB said in a statement.[34]
  • The first 300 MW unit was commissioned on March 22, 2011.[35]
  • On August 8, 2012 a tripping of the powerline from Lakvijaya caused the power station to cease operations.[36]
  • On January 29, 2013 the power station exceeded its designed levels of 300MW, causing a complete shutdown. The plant was reactivated a day later.[37][38]
  • On December 13, 2013 a steam leak was detected. “Although the plant could still function with the defect we concluded that it would be dangerous to the plant and therefore decided to halt operations. However we later detected that there was also another problem in the condenser. The issue is that the steam leakage cannot be detected without the specialised equipment which is not available in Sri Lanka and the Chinese said that they would take over a month to get the required equipment from China," said CEB DGM Business and Operational Strategy and spokesman Senajith Dasanayake. Facing a potentially long shutdown, the CEB call for bids from both the Chinese company and Indian firms. "Since the Indians quoted the lowest we decided to seek the help of the Indians. The DGM of Norochcholai informed me that the Chinese were attending to the problem and the Indian intervention has been temporarily put on hold,” he said.[39]
The adviser to the National Electricity Consumer Movement, Bandula Chandrasekera, said that a consequence of the problems with the coal-fired plant was that the CEB's operating losses were higher than planned.[39]
  • On January 12 2014 the Sunday Star Times reported that since the start of the year the plant had been shut down for six days. Just a day after being restarted after its latest shutdown, the newspaper reported that a leak from the repaired condenser had been detected and the plant shut down for the 26th time. It also reported that in the previous 24 days it had been shut down on four occasions. With the CEB having to spend US$3.3 million a day to buy alternative diesel power during shutdowns, the financial losses from the Lakwijaya Coal Power Plant continue to mount. The newspaper reported that in the first six months of 2013 the plant had been closed for 32 days and in the second halef of the year for between 90 and 100 days.[40]
The Sunday Star Times editorialised that the problems with Unit 1 at the plant were wide ranging including "mishaps from valve repairs and pipe damages to coal mill fires, abnormal fluctuation in turbine lube oil pressure, a hydrogen seal oil leak, debris filter damages, high temperature in cooling water pumps and a failure of both transmission lines."[41]
Compounding these problems, the editorial stated, was "the fact that all instruction manuals for the plant –including its many, many auxiliaries — are in Chinese is “a big problem”. Even machine components are labelled in Chinese. Translations are ongoing ‘on the run’, so to say. What government in the world agrees to a design-build-and-transfer power plant without an assurance that basic instruction manuals are in a language that could be understood by the party expected to run it? It is difficult enough to operate a Chinese mobile phone with directions only in that language. The scale of Lakvijaya is a thousand times bigger," the paper editorialised. demonstrate the need for right to information laws.[41]
  • On January 23, 2014 the Minister of Power and Energy Pavithra Wanniarachchi told parliament that that the power station had been offline for 271 days of of 1,086 days since commissioning in 2011.[42]
  • In late August 2014, problems emerged once again. On August 27, a CEB spokesman said that an "error in instrumentation" had sent a wrong signal to the protection system on Unit 1, shutting the unit down automatically. Unit 3, which was being test run at the time ahead of the target commissioning date of September 16, was also shut down. At the same time, the generator in Unit 2 had also broken down due to a problem with its turbine blades and - as of the end of August - was scheduled to take another ten to fifteen day to repair. Spokesman Senajith Dassanayake said that the filters on the water intake had been clogged by jellyfish. "Around 30-40 divers have to be used to remove these creatures from the filters. We were hoping to remove these creatures from the filters of Unit 1, but unfortunately, seas these days are extremely rough in the area and the divers haven’t been able to go in thus far," he said.[43]
  • In December 2015, it was reported that all three coal plants in the facility were offline due to multiple plant failures.[44]
  • In March 2016, the country was without electricity for more than eight hours following a massive system breakdown stemming at the power plant.[45]
  • In August 2020, a ‘technical fault’ at the plant caused a nationwide blackout and power rationing.[45] Despite a previous expert committee having recommended it as far back as February 2017, the plant still didn't have an auxiliary (external) power supply mechanism to keep the units alive in the event of a grid failure. Having one can facilitate a controlled shutdown of plants so they can be restarted without waiting for three to four days.[46]
  • In December 2021, some engineers claimed power shedding and random power cuts were expected as coal was in short supply. In addition, two generators may have developed faults.[47]
  • In September 2022, the Public Utilities Commission of Sri Lanka issued a notice warning about potential power outages caused by a breakdown at Lakvijaya Power Plant. The breakdown was caused by a steam leak in Unit 3.[48]
  • In August 2023, Unit 2 was offline for a week after another breakdown.[49]
  • In November 2023, Units 2 and 3 were both offline and undergoing repairs.[50]

Call for inquiry on plant tender

In December 2013, the National Electricity Consumers Movement, unions, and opposition political parties called for a Parliamentary Select Committee (PSC) to investigate the recurrent breakdowns with the first phase of the Norochcholai coal power plant. It was reported that since the plant was commissioned in December 2011, the plant, which was built by China Machinery and Engineering Corporation (CMEC), experienced more than 20 breakdowns. As a result, the CEB incurred significant financial loss.[51]

The General Secretary of the Lanka Electricity Board Employees’ Union, Ranjan Jayalal, said that some CEB "officials went to China with their families thanks to technical evaluations and other similar operations. It is clear that they have not done their job. We urge the government to start an inquiry. As much as the Chinese company is responsible for the breakdowns in the Norochcholai coal power plant, those officials too should take the blame for the problem.”[51]

Parliamentarian Ajith P Perera said that it was important that a Parliamentary Select Committee on the construction of the first unit be held before work proceeded further on stage two of the plant. "The power plant has been built on an ‘unsolicited tender’, without taking any other competitive tender into consideration. The same contractor has handled every aspect of the construction without getting any other party involved in the process. Also, there is a serious question about the cost involving the construction. This is just the tip of the iceberg. Therefore, the only option is to appoint a Parliamentary Select Committee to look into the problem,” he told the Sunday Leader.[51]

Bandula Chandrasekara, an Advisor to the National Electricity Consumers Movement, told The Sunday Leader that the project had become a financial nightmare for the CEB. "The cost of one electricity unit at the Norochcholai plant is making a debilitating effect on the CEB as it is in stark contrast with the ‘Cost Generation Plan’ of the CEB. The plan was made at the beginning of the year. The reason for the difference is that the CEB has not taken the foreign exchange variation and coal price fluctuations in the world market into consideration, when making the initial plan. Therefore, in the Cost Generation Plan, the production cost of a unit stands at a lower rate than the actual cost. This has now become a serious concern for the CEB,” he added.[51]

Controversy over cost and origins of the deal

In November 2013, with controversy over the reliability raging in the Sri Lankan community and media, the Vice President of China Machinery Engineering Corporation (CMEC), Li Chaoyang, wrote an extraordinary letter to the Power and Energy Ministry Secretary, M.M.C. Ferdinando, defending the company and rejecting accusations that a significant commission had been factored into the cost of what turned out to be a defective plant.[52]

"Recently, it is reported by local media that the Phase I Puttalam Coal Power Project was a corrupted (sic) project with high commission contained in the contract price and CMEC was chosen as the contactor due to the requirement of commission payment could be met (sic), which led to poor quality of project and the Sri Lankan government has compelled to sell the power plant, etc,” Mr. Li wrote.[52]

“These reports are completely baseless, severely distorted and totally irresponsible and nonsense,” he asserted. “It has ruthlessly insulted all of the staff from all involved parties who have devoted their hearts and exerted their utmost efforts to this project for so many years, and it is just a deliberate sabotage and attempt to destructing of long-history friendship (sic) between the two countries,” he wrote.[52]

The Sunday Times reported that it had been provided with a copy of a June 10, 2005 email which alleged that commission payments were "discussed between CMEC’s Norochcholai Project Manager Ning Li and businessman Eshana de Silva, who was the commission agent for the project. In it, Mr. Ning instructed Mr. de Silva to arrange for him and some colleagues to apply for multiple entry visas to Sri Lanka. He then wrote, “According to my calculation, your comm. is $25.4Mn, including: A. $13.2Mn and B. $12.2Mn. Please check and contact me if any questions.” The contract for the power station was signed in August 2005 and witnessed by the then Sri Lankan President Chandrika Kumaratunga and former Chinese President Hu Jintao.[52]

Controversy over pollution impacts

A June 2018 report by the Coalition Against Coal found the Lakvijaya plant lacks an environmental management licence, a waste management licence, approval for a recent expansion of a coal yard, or authorisation for the drilling of water bores. The report also found that sensors for environmental monitoring had not been properly calibrated, that there had been repeated breakdowns of the flue gas desulphurisation units, and the plant had no mercury control system.[53]

In July 2018, the flue-gas desulphurizer (FGD) on unit 2 was destroyed when a welding fault set its insulation material on fire. This instrument removes sulphur dioxide from the flue gas. In October 2018, the Wayamba Provincial Council Environmental Authority issued the license to Lakvijaya despite the FGD not functioning.[54]

In March and April 2019, tests at the Lakvijaya plant showed particulate matter sixteen times over the maximum permissible level in the stack emissions of unit one. The quantity of sulphur dioxide was also over the limit in the stacks emissions of both unit one and two, with the latter performing significantly worse than the former, due to the lack of a flue-gas desulphurizer.[54] The air-borne ash particulates from the plant have been monitored reaching the hills of Nawalapitiya hills and Colombo.[55]

In August 2021, Bishop Valence Mendis of Chilaw said pollution from the plant was posing a serious risk to the health of residents.[56]

In February 2023, it was reported that the impact of the coal plant was "catastrophic" to residents, for reasons including the community's primarily fishery- and agriculturally based livelihoods.[57] Various skin conditions and illnesses common to community members were also linked to the proximity of the coal plant's pollutive emissions. [57]

Maintenance agreement with CMEC

In February 2014, CEM Chairman W.B. Ganegala stated that "we are going to sign a Memorandum of Understanding for technical Corporation with the CMEC on technologies, to ensure technical efficiency of the Power Plant, which is by all means not "handing over" of its functions to anyone."[58]

In September 2014 it was announced that the Ministry of Power and Energy had negotiated two Memorandum of Understandings (MOUs) between with China to "provide technical co-operation for the stable, efficient functioning of the Norochcholai Coal Power Project". The government stated that the first MOU was between the governments of Sri Lanka and China to be signed on September 16 at the commissioning of the final unit at the power station and a second MOU "to be signed between CEB and China Machinery Engineering Corporation."[59]

The Sunday Times reported that it had obtained a copy of the government to government MOU. The MOU included provisions for:[60]

  • "Providing operation and maintenance advisory service for the Project";
  • "Assisting CEB to plan to purchase its spare parts requirements on a long term basis, facilitating CEB to procure genuine spare parts from original manufacturers at competitive prices while guaranteeing cost effectiveness, quality and technical standards to ensure effective operation and maintenance of the Project in a timely manner";
  • "Providing effective advisory services for annual inspection and overhaul of the project, and the related machinery including advisory services on effective remedial measures to be taken to rectify the shortcomings and lapses, particularly with regard to machinery of the Unit One of the project"; and
  • "Providing training to CEB personnel with the intention of improving their technical capabilities and to provide exposure to a different technical culture to such CEB personnel."

The MOU also proposed the establishment of a four member committee to oversee the agreement.[60]

Coal supplies and barges

In October 2012, the Sri Lankan power minister Champika Ranawaka told Parliament that the first 300 MW unit of the Norochcholai Power plant would use between 650,000 to 700,000 tonnes of coal a year.[61]

Coal for the plant is supplied through Lanka Coal (Pvt) Ltd, a government-owned company. However, Lanka Coal put the supply of coal for the power plant out to tender and received two bids: one from Holcim, which operates cement plants which it already imports coal for, and another from Nobel Resources[61], a company owned by casino businessman Ravi Wijeratne. (Wijeratne is a major partner in James Packer’s Colombo Crown casino.)[62] (The controversy over the awarding of the coal contract reportedly provided the impetus for the government to consider direct investment in a coal mine.[62])

Ranawaka told parliament that at first Holcim Trading (Pvt) Ltd had been awarded the contract but that this was overturned in favour of Nobel Resources following an appeal to cabinet. It was reported that Holcim had bid US$58.763 million and Nobel Resources US$58.736 million to supply 325,839 tonnes.[61]

Member of Parliament Dayasiri Jayasekera told parliament that Holcim's bid included the cost of coal landed at the jetty - including the costs of barge transport from the coal carriers while Nobel's excluded the costs of barging. Power Minister Ranawaka stated that Lanka Coal had already bought a barge which would be operated by the government-owned Ceylon Shipping Corporation, a state-run firm. However, he said that in future tenders the cost of barging operations would be included.[61]

In November 2013, it was reported that the Power and Energy Ministry had undertaken a tender process.[62] It was later reported that the CEB initially signed a contract in November 2013 for the provision of one million tonnes of coal at US$64.80 per tonne. But then, in March, the supplier reportedly informed the CEB that they could only supply 200,000 tonnes instead of the initially contracted volume. This led to fuel shortages as the power station could not be resupplied until after the monsoon.[63]

The Island reported that "then, the CEB once again in July 2014 to signed a contract with the same supplier for purchasing another 200,000 MT of coal at a higher price––an additional USD 9.62 per tonne." The higher price reportedly led Power and Energy Ministry officials to question why a company which hadn't fulfilled their initial contract had then been chosen as the supplier for another contract while a senior CEB official estimated that calling for separate bids for 200,000 tonnes shipments should have led to lower prices.[63]

The Island also revealed in September 2014 that the CEB Chairman W. B. Ganegala, Lanka Coal Company Chairman Menaka Liyanage and other government officials had gone to China to buy a coal barge.[63]

In September 2022, the Public Utility Commission of Sri Lanka (PUCSL) warned of possible power cuts at Lakvijaya Power Plant and across the grid due to limited coal supplies. At the time, only one out of three units was in operation due to breakdowns and faults. The PUCSL Chairman stated: "authorities should focus on finding a permanent solution to this. It can be renewable or any other method. But the time has come for us to find a solution without waiting any longer".[48]

In November 2022, new recommendations were approved regarding the procurement and purchase of coal for the Lakvijaya Power Plant for the period of 2022 to 2025.[64] In January 2023, the Lanka Coal Company stated that "regardless of various reports", all coal supplies necessary for continuous operation were being delivered the plant. Seven shipments were to arrive in January alone.[65]

In February 2023, the Lanka Coal Company reported that rather than pursuing Indonesian coal, 720,000 tonnes of coal from Russia would be purchased to run the power station.[66]

Legal action

Environmental Foundation Limited (EFL), together with three affected community members (a fisherman and 2 farmers) from Norochcholai, invoked jurisdiction of the Supreme Court under a Fundamental Rights application on August 22, 2016, against the power station. The case was taken up before the Supreme Court in 2020 and the Court refused to grant ‘Leave to proceed.’[67]

Financing

Unit 1: The Sri Lankan Ministry of Power and Energy stated that for the first 300 MW Unit, the Export-Import Bank of China provided a US$450 million loan of which US$300 million was at 2% interest and US$150 million was at 6% interest. The Sri Lankan government contributed 5300 Million Sri Lanka Rupees as its contribution to the project.[3]

Unit 2 and 3: The Sri Lankan Ministry of Power and Energy stated on its website that the second stage - comprising two addition 300 MW units - was estimated to cost US$891 Million. The Ministry stated that the second stage of the project has "been funded by a soft loan" of US$891 million by EXIM Bank of China. The Ministry stated that "As local investment the Sri Lankan Government has invested Rs. 5300 Million for the first stage and Rs. 11,000 Million for the second stage of construction."[3]

Unit 4: In February 2020, it was reported the Chinese government would provide a soft loan of US$350 to 400 million for the fourth unit at Norochcholai.[14]

Planned retirements

As of February 2023, Unit 1 was planned for retirement in 2041. [68]

Articles and Resources

References

  1. "Norocholai (Laskvijaya) Coal Power Plant Sri Lanka," Global Energy Observatory, accessed March 2014
  2. Ranga Sirilal, "With Chinese push, Sri Lanka boosts power generation by 11 pct," Reuters, March 22, 2011
  3. 3.0 3.1 3.2 "Norochcholai Coal Power Plant," Ministry of Power and Energy website, accessed September 2014
  4. "Displaced families complain of shocking deception". SundayTimes.lk. April 13, 2008. Retrieved October 13, 2012.
  5. Shirajiv Sirimane, "Two major development projects from November," Sunday Observer, October 24, 2010, Archived Oct. 17, 2015
  6. "Coal-fired power plants around the world". IndustCards.com. March 11, 2012. Retrieved October 13, 2012.
  7. "Lakvijaya: CEB signed multimillion dollar deals with Chinese company without cabinet approval," The Sunday Times, July 18, 2021
  8. "A local perspective of the socio-environmental vulnerability to environmental pollution and economic crises: a case of locals around a coal power plant in Sri Lanka," Environ Dev Sustain, January 11, 2023
  9. Norochcholai power plant out of action due to engineers’ shortage, The Leader, October 1, 2023
  10. Norochcholai Coal Power Plant plagued by problems since its inception, Colombo Gazette, May 25, 2023
  11. "Cabinet approves four coal power plants, moves to reduce PUCSL’s authority," Sunday Times, June 23, 2019
  12. "Plans to expand Norochcholai coal power plant gets cabinet approval," SL Time, September 25, 2019
  13. "Environment at risk: Multiple coal power projects proposed," The Sunday Morning, October 6, 2019
  14. 14.0 14.1 "China to Sri Lanka’s rescue with soft loan for fourth coal plant at Norochcholai," Asia News Network, February 17, 2020
  15. "Sri Lanka: Coal power extension project to be pushed through under 'emergency' COVID-19 situation". IEA Clean Coal Centre. June 19, 2020. Retrieved November 30, 2020.
  16. "Long Term Generation Expansion Plan," Ceylon Electricity Board, March 2020
  17. "Proposed 300MW coal plant in Puttalam: CEB joint venture with Chinese firm - The Morning - Sri Lanka News". The Morning - Sri Lanka News. June 7, 2020. Retrieved June 25, 2020. {{cite news}}: no-break space character in |title= at position 39 (help)
  18. "No final decision yet on Norochcholai extension | Daily FT". www.ft.lk. June 24, 2020. Retrieved June 25, 2020.{{cite web}}: CS1 maint: url-status (link)
  19. "COPE Chairman recommends CEA’s involvement for the environmental assessment of the Lakvijaya power plant," ColomboPage, November 25, 2020
  20. "Norochcholai environmental impact affects entire country – COPE," The Island, November 26, 2020
  21. 21.0 21.1 "Long Term Generation Expansion Plan 2023-2042," CEB, February 10, 2023
  22. “Sri Lanka: Updated Nationally Determined Contributions,” Ministry of Environment, July 2021
  23. "CEB engineers ask President to allow completion of coal-fired power plant extension project," The Island, August 1, 2021
  24. "LCLTGEP 2022-2041 Resubmission," Public Utilities Commission of Sri Lanka, August 9, 2021
  25. "LCLTGEP 2022-2041 Communications," Public Utilities Commission of Sri Lanka, updated August 16, 2021
  26. "CEB to revise power plan to reach 70% renewable energy target," Sunday Times, August 15, 2021
  27. "No new coal-based power plants to be set up in Sri Lanka: Govt," AFP, October 27, 2021
  28. "PUCSL expects CEB’s new long-term power generation plan within next 4 months," Daily Mirror, January 26, 2022
  29. "Long Term Generation Expansion Plan: 2022-2041," Ceylon Electricity Board, October, 2021
  30. "Least Cost Long Term Generation Expansion Plan 2022-2041 Resubmission," Public Utilities Commission of Sri Lanka, August 9, 2021
  31. "Minister orders a full report on fire at Sri Lanka power plant" Colombo Page, October 24, 2010
  32. "Government won't bear costs of Norocholai fire," Adaderana.lk, December 2, 2010
  33. "Cause of Lakvijaya breakdown identified," AdaDerana.lk, July 24, 2012
  34. "Sri Lanka imposes daily power cut after Chinese plant fails again," Reuters, July 24, 2012
  35. "First phase of Sri Lanka's first coal power plant to be opened tomorrow," ColomboPage, March 21, 2011
  36. "Power cuts again," DailyMirror.lk, August 8, 2012
  37. "Norochcholai Coal Power Plant at a standstill," DailyMirror.lk, January 29, 2013
  38. "Norochcholai back to life," January 30, 2013
  39. 39.0 39.1 Camelia Nathaniel, "Norochcholai: Indian Help Put On Hold," Sunday Leader, December 29, 2013
  40. "A Costly Breakdown," The Sunday Leader, January 12, 2014
  41. 41.0 41.1 "Throw some light," Sunday Star Times, January 12, 2014
  42. "Sri Lanka's china-built coal power plant failed 271 day since start," Colombo Page, January 23, 2014
  43. Sandun Jayawardana, "Lakvijaya Coal Power Plant woes - Jellyfish clog pump filters," The Nation, August 31, 2014
  44. "Lakvijaya stalled but no blackouts envisaged," Daily News, December 14, 2015
  45. 45.0 45.1 "Sri Lanka cuts power for 21 million people after Chinese generator trips". South China Morning Post. August 19, 2020. Retrieved October 29, 2020.
  46. "Expert committee slams CEB for last year’s islandwide blackout," The Sunday Times, April 25, 2021
  47. "Mixed signals from CEB on possible power shedding," The Islands, December 23, 2021
  48. 48.0 48.1 "Sri Lanka likely to plunge deeper into darkness as coal plant reports another breakdown: UPDATED," Economy Next, September 27, 2022
  49. "Norochcholai Generator 2 to be restored," News First, August 15, 2023
  50. Two generating units of Norochcholai power plant to remain inoperative for 2 weeks?, Adaderana, November 19, 2023
  51. 51.0 51.1 51.2 51.3 Rasika Jayakody, "PSC Sought On Norochcholai," Sunday Leader, December 8, 2013
  52. 52.0 52.1 52.2 52.3 Namini Wijedasa, "Coal power chaos: Chinese firm fumes: Top official defends Norochcholai plant, dismisses bribery charge," Sunday Times, February 2, 2014
  53. "Explosive report on hazards of Norochcholai coal power plant," Sunday Times, June 3, 2018
  54. 54.0 54.1 "Tests show Lakvijaya plant spews out dust 16 times over the limit," The Sunday Times, June 2, 2019
  55. "Norochcholai ash contaminates Lanka’s western atmosphere," The Sunday Times, March 10, 2019
  56. "Sri Lankan bishop attacks coal power plant," UCA News, August 2, 2021
  57. 57.0 57.1 "Report on Norochcholai Power Plant," Ilankai Tamil Sangam, Feb. 2023
  58. Chamikara Weerasinghe, "Lakvijaya fully operational No power cuts," Daily News, April 10, 2014
  59. "Sri Lanka-China to sign two MOUs for Norochcholai Coal Power Project," News.lk, September 7, 2014
  60. 60.0 60.1 "More power for China in Norochcholai: MoU to prevent ‘technical failures’ to be signed with China’s Ministry of Commerce during President Xi’s vist to Sri Lanka," The Sunday Times, August 31, 2014
  61. 61.0 61.1 61.2 61.3 "Sri Lanka power plant to use up to 700,000 tonnes of coal a year," Lanka Business Online, October 17, 2012
  62. 62.0 62.1 62.2 "SL considers investments in foreign coal mines," Sunday Times, November 3, 2013
  63. 63.0 63.1 63.2 "Now, top CEB officials fly off to buy vessel to bring coal," The Island, September 3, 2014
  64. "COPE directs the implementation of the Auditor General’s recommendations regarding the purchase of coal," ColomboPage, November 11, 2022
  65. "Seven ships of coal to arrive in Sri Lanka within this month," ColomboPage, January 6, 2023
  66. "Sri Lanka to buy Russian coal; LCC will no longer pursue Indonesian order," The Sunday Times, February 12, 2023
  67. "Norochcholai Coal Power Plant," Environmental Foundation Limited, accessed June 24, 2021
  68. "LONG TERM GENERATION EXPANSION PLAN," CEYLON ELECTRICITY BOARD, Feb. 2023

Additional data

To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.