Lixin Banji power station (中煤新集电力安徽利辛板集电厂) is an operating power station of at least 3320-megawatts (MW) in Banji, Lixin, Bozhou, Anhui, China.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Lixin Banji power station Banji, Lixin, Bozhou, Anhui, China 32.897245, 116.242561 (exact)[1]
Loading map...

Unit-level coordinates (WGS 84):

  • Phase I Unit 1, Phase I Unit 2, Phase II Unit 3, Phase II Unit 4: 32.897245, 116.242561

Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology Start year Emergency/Backup
Phase I Unit 1 Operating coal: unknown[2] 1000 ultra-supercritical 2016 False
Phase I Unit 2 Operating coal: unknown[2] 1000 ultra-supercritical 2016 False
Phase II Unit 3 Operating[3] coal: unknown[1][2] 660[1] ultra-supercritical[1] 2024[3] False
Phase II Unit 4 Operating[4] coal: unknown[1][2] 660[1] ultra-supercritical[1] 2024[4] False

Table 3: Unit-level ownership and operator details

Unit name Owner Parent
Phase I Unit 1 China Coal Xinji Lixin Power Generation Co Ltd [100%][1] China Coal Xinji Energy Co Ltd [55.0%]; An Hui Wenergy Co Ltd [45.0%]
Phase I Unit 2 China Coal Xinji Lixin Power Generation Co Ltd [100%][1] China Coal Xinji Energy Co Ltd [55.0%]; An Hui Wenergy Co Ltd [45.0%]
Phase II Unit 3 China Coal Xinji Lixin Power Generation Co Ltd [100%][1] China Coal Xinji Energy Co Ltd [55.0%]; An Hui Wenergy Co Ltd [45.0%]
Phase II Unit 4 China Coal Xinji Lixin Power Generation Co Ltd [100%][1] China Coal Xinji Energy Co Ltd [55.0%]; An Hui Wenergy Co Ltd [45.0%]

Project-level coal details

  • Coal source(s): domestic

Ownership Tree

This ownership tree is part of the Global Energy Ownership Tracker, a project of Global Energy Monitor.

Background on Project

SDIC is sponsor of a two-unit coal-fired power plant of 2,000 MW in Anhui Province. In November 2013, SDIC signed a construction contract with Shandong Electric Power Engineering Consulting Institute Corp., with construction slated to begin in 2014 and be completed in 2016.[5]

Environmental permits were issued in March 2014.[6]

The power station went online in 2016.[7][8]

Expansion

In March 2020, two additional 1,000 MW units at the power station (Units 3-4) were listed as a priority project for Anhui province, as part of a UHV power hub in the Yangtze River Delta.[9]

In January 2021, two new 660 MW units at the power station were permitted for construction.[10][11]

As of May 2021, construction was expected to begin by early 2022.[12] It began in September 2022.[13]

Phase II Unit 3 saw the chimney topped out in August 2023[14], and the turbine foundation was poured in October[15]. In November, the generator stator was hoisted[16], and the cooling towers were completed[17]. In January 2024, the chimney steel liner was installed[18], and the boiler hydraulic test passed[19]. In March, the high-pressure cylinder was hoisted[20]. In June, boiler ignition succeeded[21], and flushing was completed in July[22]. Unit 3 was connected to the grid on August 1[23] and passed the 168-hour trial on August 31[24].

Unit 4 had its plant power system energized in June 2024[25], was connected to the grid on September 10[26], and passed the 168-hour trial on September 30[27].

Ownership

The parent company changed from SDIC to China Coal and Wenergy Group in December 2016.[28]

Articles and Resources

References

  1. ↑ 1.00 1.01 1.02 1.03 1.04 1.05 1.06 1.07 1.08 1.09 1.10 https://news.bjx.com.cn/html/20210201/1133499.shtml. {{cite web}}: Missing or empty |title= (help)
  2. ↑ 2.0 2.1 2.2 2.3 https://www.gem.wiki/Coal_source_methodology_for_the_Global_Coal_Plant_Tracker. {{cite web}}: Missing or empty |title= (help)
  3. ↑ 3.0 3.1 https://news.bjx.com.cn/html/20240902/1398089.shtml. {{cite web}}: Missing or empty |title= (help)
  4. ↑ 4.0 4.1 "2×660MW!中煤利辛电厂二期项目通过168小时试运行-北极星火力发电网". news.bjx.com.cn. 2024-10-09. Archived from the original on 2025-02-05. Retrieved 2024-10-14.
  5. ↑ SDEPCI signed EPC contract for SDIC Banji 2×1000MW units project, SDEPCI press release, accessed Nov. 2014.
  6. ↑ "关于安徽利辛板集电厂(2×1000MW)新建工程环境影响报告书的批复,", 中华人民共和国环境保护部 , 2014-03-13.
  7. ↑ "国投新集电力利辛板集电厂#1机一次顺利通过168小时试运行," SDIC, 2016-08-24
  8. ↑ "安徽省环保厅关于拟作出安徽利辛板集电厂(2×1000MW)新建工程脱硫、脱硝、除尘设施竣工环境保护验收意见的公开," Anhui DEP, 2017-1-4
  9. ↑ "全文|安徽省实施长江三角洲区域一体化发展规划纲要行动计划," 安徽省人民政府, 2020/3/13
  10. ↑ "2×660MW!中煤新集利辛板集电厂二期项目核准前公示 - 北极星火力发电网". news.bjx.com.cn. 2021-01-14. Retrieved 2021-01-05.{{cite web}}: CS1 maint: url-status (link)
  11. ↑ 2×660MW!中煤新集利辛板集电厂二期项目获得核准批复, BJX, 2021-02-01
  12. ↑ "新集能源:中煤新集利辛板集电厂二期项目计划2021年底或2022年初开工建设," ifeng, May 17, 2021
  13. ↑ 2×660MW!安徽板集电厂二期项目开工, BJX, 2022-09-30
  14. ↑ "板集电厂二期烟囱到顶". 微信公众平台. 2023-10-09. Retrieved 2026-07-30.{{cite web}}: CS1 maint: url-status (link)
  15. ↑ "板集电厂二期3号机组汽机基座浇筑完成". 微信公众平台. 2023-10-09. Retrieved 2026-07-30.{{cite web}}: CS1 maint: url-status (link)
  16. ↑ "板集电厂二期3号机组发电机定子吊装就位". 北极星电力网. 2023-11-30. Retrieved 2026-07-30.{{cite web}}: CS1 maint: url-status (link)
  17. ↑ "板集电厂二期3、4号冷却塔到顶". 微信公众平台. 2023-12-06. Retrieved 2026-07-30.{{cite web}}: CS1 maint: url-status (link)
  18. ↑ "板集电厂二期烟囱钢内筒双筒提升到顶". 微信公众平台. 2024-03-13. Retrieved 2026-07-30.{{cite web}}: CS1 maint: url-status (link)
  19. ↑ "板集电厂二期3号机组锅炉水压试验一次成功". 微信公众平台. 2024-03-13. Retrieved 2026-07-30.{{cite web}}: CS1 maint: url-status (link)
  20. ↑ "板集电厂二期1号机组超高压缸吊装就位". 微信公众平台. 2024-03-13. Retrieved 2026-07-30.{{cite web}}: CS1 maint: url-status (link)
  21. ↑ "板集电厂二期3号机组锅炉点火一次成功". 北极星电力网. 2024-07-04. Retrieved 2026-07-30.{{cite web}}: CS1 maint: url-status (link)
  22. ↑ "板集电厂二期3号机组锅炉点火冲管完成". 微信公众平台. 2024-07-10. Retrieved 2026-07-30.{{cite web}}: CS1 maint: url-status (link)
  23. ↑ "板集电厂二期3号机组并网发电成功". 北极星电力网. 2024-08-05. Retrieved 2026-07-30.{{cite web}}: CS1 maint: url-status (link)
  24. ↑ "板集电厂二期3号机组168小时满负荷试运成功". 北极星电力网. 2024-09-02. Retrieved 2026-07-30.{{cite web}}: CS1 maint: url-status (link)
  25. ↑ "板集电厂二期4号机组倒送厂用电一次成功". 微信公众平台. 2024-06-17. Retrieved 2026-07-30.{{cite web}}: CS1 maint: url-status (link)
  26. ↑ "板集电厂二期4号机组并网一次成功". 北极星电力网. 2024-09-14. Retrieved 2026-07-30.{{cite web}}: CS1 maint: url-status (link)
  27. ↑ "板集电厂二期4号机组168小时试运成功". 北极星电力网. 2024-10-09. Retrieved 2026-07-30.{{cite web}}: CS1 maint: url-status (link)
  28. ↑ "新集能源:央企改革初见成效,未来将积极推动煤电一体化," China Finance, 2017-06-22

Additional data

To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.