McGinness Hills 3 geothermal plant is a 70 MW operating geothermal power plant in Lander County, Nevada, United States.


Project Details

Table 1: Unit-level project details for McGinness Hills 3 geothermal plant

Unit Name Status Commissioning Year Nameplate Capacity Type Owner
1 Operating[1] 2018[2] 48 MW[2] Binary cycle[3] Ormat Technology INC[2]


Location

Table 2: Unit-level location details for McGinness Hills 3 geothermal plant

Unit Name Location Coordinates (WGS 84)
1 Lander County, Nevada, United States[4] 39.5933, -116.9126 (exact)[4]

The map below shows the exact location of the geothermal power plant:

Loading map...

Background

Articles and Resources

Additional data

To access additional data, including an interactive map of global geothermal power plants, a downloadable dataset, and summary data, please visit Global Geothermal Power Tracker on the Global Energy Monitor website.

References

  1. "48 MW McGinness Hills Phase 3 geothermal plant starts operation in Nevada". Think Geoenergy. December 20, 2018. Archived from the original on May 11, 2022. Retrieved July 13, 2022.
  2. 2.0 2.1 2.2 "Completion of McGinness Hills geothermal plant complex expansion". Think Geoenergy. June 7, 2021. Archived from the original on May 11, 2022. Retrieved July 13, 2022.
  3. "Global Geothermal Power Plant Map". Think Geoenergy. January 10, 2012. Archived from the original on March 7, 2022. Retrieved July 13, 2022.
  4. 4.0 4.1 https://goo.gl/maps/ab9xmeMsd1VRsf1J8. {{cite web}}: Missing or empty |title= (help)