Mchuchuma power station

From Global Energy Monitor
Part of the
Global Coal Plant Tracker,
a Global Energy Monitor project.
Download full dataset
Report an error
Related coal trackers:

Mchuchuma power station is a power station in the pre-permit stage in Mchuchuma, Ludewa district, Njombe region, Iringa, Tanzania.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Mchuchuma power station Mchuchuma, Ludewa district, Njombe region, Iringa, Tanzania -9.25, 34.25 (approximate)

The map below shows the approximate location of the power station.

Loading map...


Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology Start year Retired year
Unit 1 pre-permit coal - unknown[1] 150 unknown 2026[1]
Unit 2 pre-permit coal - unknown[1] 150 unknown 2026[1]
Unit 3 pre-permit coal - unknown[1] 150 unknown 2026[1]
Unit 4 pre-permit coal - unknown[1] 150 unknown 2026[1]

Table 3: Unit-level ownership and operator details

Unit name Owner
Unit 1 Tanzania China International Mineral Resources Ltd [100.0%]
Unit 2 Tanzania China International Mineral Resources Ltd [100.0%]
Unit 3 Tanzania China International Mineral Resources Ltd [100.0%]
Unit 4 Tanzania China International Mineral Resources Ltd [100.0%]

Project-level captive use details

  • Captive industry use (heat or power): other metals & mining[2]
  • Captive industry: Power[2]

Project-level coal details

  • Coal source(s): Mchuchuma coal mine

Background

In September 2011, China's Sichuan Hongda Co. Ltd. signed a US$3 billion deal with Tanzania to mine coal and iron ore in Tanzania. The investment involved construction of the Mchuchuma Coal Mine, a 220kv transmission line between Mchuchuma and Liganga for supplying the Liganga Metallurgical Complex, and an accompanying 600-megawatt (MW) thermal power station. 250 MW from the power plant would be devoted to the Liganga Metallurgical Complex, with the remaining 350 MW provided to the national grid. It was estimated that Mchuchuma coal deposits have more than 480 million tonnes of coal reserves.[3][4]

In 2013, it was reported that the power station would be constructed over the next three years, with the first 300 MW planned by 2015.[5]

However, in October 2014, it was reported that construction would begin on the projects in 2015, and expected to be completed by 2019.[6]

The estimated cost for Mchuchuma and Liganga iron ore mines and plants was US$3 billion, which would be sourced in partnership between the Tanzania government and Sichuan Hongda. In January 2015, it was reported that the government was having difficulty securing the funding, given budget constraints.[7]

In May 2016, it was reported that work on the mining projects had been pushed to 2017.[8]

According to an October 2016 report, the process of evaluating compensation for 126 households around the Mchuchuma projects (290 individuals) and the 19 households and farms around the Liganga project (299 individuals) was completed in September 2015, but the process of compensating the villagers was not subsequently carried out.[4]

In March 2017, it was reported that the government was in the midst of settling issues with investors regarding incentives and power tariffs. It was expected that conclusion of the negotiations would lead to funds being released to compensate people relocated for the projects. Mining would then begin.[9]

According to a March 2017 report, the mines ministry had opened an inquiry into the performance of Sichuan Hongda Group in the wake of disappointment with the firm's performance.[10]

In September 2018, it was reported the country would need US$645.75 million for the plant, and that the project’s feasibility studies still needed to be actualized.[11]

Plans Revived following Uncertainty

In May 2020, the government reaffirmed its plans to proceed with the plant. The ministry also told Parliament that a lack of funds and technology to drill iron core were key reasons behind the continued delay.[12]

In January 2021, it was reported Tanzania China International Mineral Resource Ltd (TCIMRL) was asking for tax incentives on import duty on goods to be imported for the construction work, incentives on spare parts and machinery, and relief on fuel. The Chinese firm’s parent company, Sichuan Hongda Group Ltd (SHG), "discharged its part of the contract by carrying out geological exploration, environmental and social impact assessment, valuation for purposes of compensation of people affected by the project, research, as well as development for smelting technology to the tune of about $70 million."[13] These requests were contrary to the Natural Wealth and Resources (Permanent Sovereignty) Act, 2017 along with the Natural Wealth and Resources (Contract Review and Renegotiation of Unconscionable Terms) Act of 2017.[14]

In June 2021, President Samia Suluhu Hassan called for the removal of red tape delaying the implementation of the Mchuchuma and other projects, saying it was high time the projects take-off. She said there was a need to establish the reasons behind the delay of the strategic extractive projects, and added the government would not hesitate to act if the investor was incapable of implementing the projects.[15] Tanzania also budgeted 2.34tri/- for power generation, transmission, and distribution projects, including an SGR line between Liganga and Mchuchuma. The Mchuchuma Coal project was identified as a flagship project. (Assuming "/-" represents TZS and not KES, this was an estimated US$1 billion.)[16][17]

By the end of 2021, drilling exploration was completed, Environmental and Social Impact Assessment (ESIA) studies had been completed, and ESIA certificates and licenses for mining coal and water rights for use of Katewaka and Mchuchuma Rivers had been obtained. The government and TCIMRL also signed a Strategic Investor Status Certification and Performance Contract.

In May 2022 Parliament debates over the 22/23 national budget, members pushed at why the government has been "dragging their feet" over the strategic investment for over a decade. The project was still actively being pursued at this point, with ongoing issues such as land acquisition being addressed by the Lands Ministry and the Attorney General's Office.[18] China's pledge to halt all foreign investments in coal projects is likely also contributing to this delay.

In November 2022, Parliament had not made any progress on decision-making surrounding the plant.[19]

According to reports from January and February 2023, the government had revived negotiations with investors and had shifted the task of negotiating from the Government Negotiation Team committee to the National Development Corporation, “in order to speed up negotiations.” The Deputy Minister for Investment, Trade and Industries reportedly expected negotiations to be completed by financial year 2023-24, but also said that if the government could not reach a conclusion with current investors, they would consider seeking other investors for the project.[20][21]

As of June 2023, the government of Tanzania had identified the project as a priority in its National Development Plan for 2023/2024,[22] and had launched a compensation program for the 1,142 residents that would be displaced by the project.[23] According to reporting from July 2023, the power plant project was expected to begin construction in 2025 and start commercial operation in 2026.[24] Of the planned 600 MW capacity, 250 MW would be used for an iron plant and the remaining 350 MW would be supplied to the national grid.[25]

Articles and Resources

References

  1. 1.0 1.1 1.2 1.3 1.4 1.5 1.6 1.7 https://web.archive.org/web/20240125081826/https://www.plantandequipment.news/news/projects/latest-africa-mega-projects-from-july-and-august-2023/. Archived from the original on 25 January 2024. {{cite web}}: Missing or empty |title= (help)
  2. 2.0 2.1 https://web.archive.org/web/20240125081838/https://thebusinesswiz.co.tz/2023/07/18/mtwara-mbamba-bay-sgr-project-will-be-an-economic-game-changer-govt-official-says/. Archived from the original on 25 January 2024. {{cite web}}: Missing or empty |title= (help)
  3. "China co signs $3 bln Tanzania coal, iron deal," Fumbuka Ng'wanakilala, Reuters, September 22, 2011
  4. 4.0 4.1 Rosemary Mirondo, "Tanzania: Sh6 Trillion Coal, Iron Ore Projects Hit Snag," allAfrica, October 20, 2016
  5. "Waiting for the dragon to spit fire," Mjengwa Blog, October 2, 2013
  6. "Tanzania to start $3bn iron ore and power projects in 2015," Mining News, October 1, 2014
  7. "$3bn needed to develop Mchuchuma, Liganga," The Citizen, January 14, 2015
  8. "Coal and iron-ore projects in Tanzania to start early 2017," CR, May 4, 2016
  9. "Tanzania: Liganga Coal Mining Starts April," allAfrica, March 23, 2017
  10. "Sichuan Hongda Group could be about to lose its license," The Indian Ocean Newsletter, March 24, 2017
  11. "Tanzania seeks $3.6 billion for 9 energy projects," Ecofin Agency, September 27, 2018
  12. "Mchuchuma, Liganga projects see light at end of tunnel as Govt, investors hold talks," PPRA, May 2, 2020
  13. "Liganga, Mchuchuma iron ore, coal deals for review," The Citizen, January 13, 2020
  14. "Ministry, investor ticking out Liganga, Mchuchuma snags," IPP Media, The Guardian, June 16, 2021
  15. "Tanzania Keen for Liganga, Mchuchuma Swift Take-Off," Tanzania Daily News, June 14, 2021
  16. "Tanzania: Budget Allocates 7tri/ - for Flagship Projects," All Africa, June 11, 2021
  17. "Tanzania: New Milestone in Mining Sector," All Africa, August 2, 2021
  18. "Ministry Stalls Investment in Key Coal, Iron Projects -MP," IPP Media, May 10, 2022
  19. "Parliament team tells government to act on iron, coal projects," The Citizen, November 4, 2022
  20. "Light at the end of tunnel for Liganga, Mchuchuma projects," The Citizen, January 17, 2023
  21. "Government on the spot over delays in Liganga, Mchuchuma projects," The Citizen, February 4, 2023
  22. "National Development Plan Of Year 2023/24," Tanzania Ministry of Finance and Planning, June 14, 2023
  23. "MCHUCHUMA, LIGANGA PROJECTS: Economic game changer," Daily News, June 7, 2023
  24. "Latest Africa Mega Projects from July and August 2023," Plant & Equipment News, July 12, 2023
  25. "Mtwara-Mbamba Bay SGR project will be an economic game changer, Gov’t official says," The Business Wiz, July 18, 2023

Additional data

To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.