NU Vista Limited Cement power station is a shelved power station in Tangeda, Dachepalli, Guntur, Andhra Pradesh, India.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
NU Vista Limited Cement power station Tangeda, Dachepalli, Guntur, Andhra Pradesh, India 16.65655, 79.80908 (exact)

The map below shows the exact location of the power station.

Loading map...


Unit-level coordinates (WGS 84):

  • Unit 1: 16.65655, 79.80908

Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology Start year Retired year
Unit 1 shelved coal - unknown 30 unknown

Table 3: Unit-level ownership and operator details

Unit name Owner
Unit 1 NU Vista Ltd (NVL) [100.0%]

Project-level captive use details

  • Captive industry use (heat or power): cement & building
  • Captive industry: Power

Project-level coal details

  • Permit(s): Terms of Reference: 2021-10-18

Background

The cement plant and captive power station had previously received Terms of Reference (ToR) from the India government in 2017, when the project was proposed by Emami Cement Ltd. The project failed to progress and its ToR expired in January 2021. The company changed its name to NU Vista Ltd., who obtained new ToR in October 2021.[1][2]

The power station was not mentioned in NU Vista's 2022–2023 annual report, which was published in July 2023.[3] There had been no further progress as of April 2024, and the project was presumed shelved.

Captive mine rejected (2021)

According to the Indian Bureau of Mines, NU Vista's proposal for a captive mine had been rejected in 2021.[4]

Articles and Resources

References

  1. "Terms of Reference," India Ministry of Environment, Forest and Climate Change, October 18, 2021
  2. "Pre-Feasibility Report of Greenfield Cement Plant with Captive Power Plant," NU Vista Limited, September 17, 2021
  3. "Integrated Annual Report 2022-23," Nuvoco Vistas Corp. Ltd., July 4, 2023
  4. Status of processing of Mining Plan/Modified Mining Plan received from 01.03.2021 upto 31.12.2023, Indian Bureau of Mines, December 31, 2023

Additional data