Nantong Tongzhou Bay power station
| Part of the Global Coal Plant Tracker, a Global Energy Monitor project. |
| Related coal trackers: |
Nantong Tongzhou Bay power station (华能南通通州湾发电项目, 中煤通州湾二期2×1000MW机组扩建工程) is a power station in Tongzhou District, Nantong, Jiangsu, China with multiple units of varying statuses, none of which are currently operating.
Location
Table 1: Project-level location details
| Plant name | Location | Coordinates (WGS 84) |
|---|---|---|
| Nantong Tongzhou Bay power station | Tongzhou District, Nantong, Jiangsu, China | 32.213932, 121.561137 (exact)[1] |
Unit-level coordinates (WGS 84):
- Phase II Unit 3, Phase II Unit 4, Unit 1, Unit 2: 32.213932, 121.561137
Project Details
Table 2: Unit-level details
| Unit name | Status | Fuel(s) | Capacity (MW) | Technology | Emergency/Backup |
|---|---|---|---|---|---|
| Phase II Unit 3 | Announced[2] | coal: unknown[3][4] | 1000[3] | ultra-supercritical[3] | False |
| Phase II Unit 4 | Announced[2] | coal: unknown[3][4] | 1000[3] | ultra-supercritical[3] | False |
| Unit 1 | Construction[2] | coal: unknown[4][1] | 1000[1] | ultra-supercritical[1] | False |
| Unit 2 | Construction[2] | coal: unknown[4][1] | 1000[1] | ultra-supercritical[1] | False |
Table 3: Unit-level ownership and operator details
| Unit name | Owner | Parent |
|---|---|---|
| Phase II Unit 3 | Huaneng International Power Jiangsu Energy Development Co Ltd Nantong Power Plant [100%][1] | Huaneng Power International Inc [100.0%] |
| Phase II Unit 4 | Huaneng International Power Jiangsu Energy Development Co Ltd Nantong Power Plant [100%][1] | Huaneng Power International Inc [100.0%] |
| Unit 1 | Huaneng International Power Jiangsu Energy Development Co Ltd Nantong Power Plant [100%][1] | Huaneng Power International Inc [100.0%] |
| Unit 2 | Huaneng International Power Jiangsu Energy Development Co Ltd Nantong Power Plant [100%][1] | Huaneng Power International Inc [100.0%] |
Project-level coal details
- Coal source(s): imported
Ownership Tree
This ownership tree is part of the Global Energy Ownership Tracker, a project of Global Energy Monitor.
Background on Project
In June 2015, China Huadian proposed a 2 x 1,000 MW coal plant for Tongzhou.[5]
There were no further developments until 2020, when the project was revived by China Huaneng.[6]
In June 2022, the project was reportedly moving forward and considered pre-permitted.[7]
In November 2022, it was reported that the project was permitted.[8]
Units 1 & 2
Construction of Units 1 and 2 continued in 2024 and 2025, with milestones including the first concrete pour, boiler steel hoisting, and progress on the steam turbines.[9][10]
Unit 1's boiler and system were undergoing startup procedures in early 2026.[11]
Unit 2's boiler water pressure test was successful in October 2025, and its generator stator was in place.[12][13]
Phase II Units 3 & 4
The project's preliminary feasibility study was reviewed in early 2025, and its feasibility study was evaluated in June 2025.[14][15] Tendering for environmental reports began in early 2026.[16]
Articles and Resources
References
- ↑ 1.00 1.01 1.02 1.03 1.04 1.05 1.06 1.07 1.08 1.09 1.10 https://news.bjx.com.cn/html/20220606/1230737.shtml.
{{cite web}}: Missing or empty|title=(help) - ↑ 2.0 2.1 2.2 2.3 "华能集团2×1000MW煤电项目正式开工". Weixin Official Accounts Platform. 2023-12-31. Archived from the original on 2024-02-07. Retrieved 2024-01-03.
- ↑ 3.0 3.1 3.2 3.3 3.4 3.5 https://news.bjx.com.cn/html/20250604/1444639.shtml.
{{cite web}}: Missing or empty|title=(help) - ↑ 4.0 4.1 4.2 4.3 https://www.gem.wiki/Coal_source_methodology_for_the_Global_Coal_Plant_Tracker.
{{cite web}}: Missing or empty|title=(help) - ↑ "通州湾百万煤机项目初步可行性研报告顺利通过专家评审," China Huadian, 2015年06月24日
- ↑ "华能集团再签2台百万千瓦煤电项目!这次在江苏南通," 南通发布, 2020/6/8
- ↑ 华能南通(通州湾)2×100万千瓦大型清洁高效煤电项目环境影响评价信息公开, BJX, 2022-06-06
- ↑ 华能南通(通州湾)2×100万千瓦大型清洁高效煤电项目获批复, BJX, 2022-11-03
- ↑ "见证第一罐混凝土浇灌". WeChat. 2023-12-28. Retrieved 2026-05-30.
{{cite web}}: CS1 maint: url-status (link) - ↑ "华能南通(通州湾)2×100万千瓦大型清洁高效煤电项目1、2号锅炉钢架首件吊装仪式举行". BeiJiXing (BJX) News. 2024-07-23. Retrieved 2026-05-30.
{{cite web}}: CS1 maint: url-status (link) - ↑ "通州湾项目1号炉风烟系统迎来首次整套启动". WeChat. 2026-04-15. Retrieved 2026-07-22.
{{cite web}}: CS1 maint: url-status (link) - ↑ "华能南通(通州湾)2×1000MW 煤电安装工程2号机组锅炉水压试验一次成功". WeChat. 2025-10-01. Retrieved 2026-05-30.
{{cite web}}: CS1 maint: url-status (link) - ↑ "通州湾煤电项目2号机组发电机定子顺利吊装就位". WeChat. 2025-09-16. Retrieved 2026-05-30.
{{cite web}}: CS1 maint: url-status (link) - ↑ "通州湾二期扩建工程初可研及接入系统规划报告评估". WeChat. 2025-01-03. Retrieved 2026-05-30.
{{cite web}}: CS1 maint: url-status (link) - ↑ "中煤通州湾二期2×1000MW机组扩建工程可行性研究报告评审会顺利召开". BeiJiXing (BJX) News. 2025-06-04. Retrieved 2026-05-30.
{{cite web}}: CS1 maint: url-status (link) - ↑ "中煤通州湾二期2×1000MW机组扩建工程(含配套码头)涉海相关专题海洋环境影响专题报告编制外协项目竞争性磋商公告". China Government Procurement. 2026-05-09. Retrieved 2026-05-30.
{{cite web}}: CS1 maint: url-status (link)
Additional data
To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.