Nudo Mudéjar de Andorra wind farm

From Global Energy Monitor
This article is part of the
Global Wind Power Tracker, a Global Energy Monitor project.
Report an error

Nudo Mudéjar de Andorra wind farm (Parque eólico Nudo Mudéjar de Andorra) is a wind farm in pre-construction in Andorra-Sierra de Arcos, Teruel, Aragón, Spain.

Project Details

Table 1: Phase-level project details for Nudo Mudéjar de Andorra wind farm

Phase name Status Commissioning year Nameplate capacity Type Owner
Alcor Pre-construction[1] 2027 (planned)[2] 111.6 MW[3] Onshore[4] Endesa SA [100%][4]
Castillo Pre-construction[1] 2027 (planned)[2] 111.6 MW[3] Onshore[4] Endesa SA [100%][4]
Empeltre Pre-construction[1] 2027 (planned)[2] 173.6 MW[3] Onshore[4] Endesa SA [100%][4]
La Plana Pre-construction[1] 2027 (planned)[2] 86.8 MW[3] Onshore[4] Endesa SA [100%][4]
Pitarra Pre-construction[1] 2027 (planned)[2] 108 MW[4] Onshore[4] Endesa SA [100%][4]
Torica Pre-construction[1] 2027 (planned)[2] 48 MW[4] Onshore[4] Endesa SA [100%][4]
Ítaca Pre-construction[1] 2027 (planned)[2] 55.8 MW[3] Onshore[4] Endesa SA [100%][4]

Location

Table 2: Phase-level location details for Nudo Mudéjar de Andorra wind farm

Phase Name Location Coordinates (WGS 84)
Alcor Andorra-Sierra de Arcos, Teruel, Aragón, Spain[4] 41.0000, -0.3851 (approximate)[4]
Castillo Andorra-Sierra de Arcos, Teruel, Aragón, Spain[4] 41.0000, -0.3851 (approximate)[4]
Empeltre Andorra-Sierra de Arcos, Teruel, Aragón, Spain[4] 41.0000, -0.3851 (approximate)[4]
La Plana Andorra-Sierra de Arcos, Teruel, Aragón, Spain[4] 41.0000, -0.3851 (approximate)[4]
Pitarra Andorra-Sierra de Arcos, Teruel, Aragón, Spain[4] 41.0000, -0.3851 (approximate)[4]
Torica Andorra-Sierra de Arcos, Teruel, Aragón, Spain[4] 41.0000, -0.3851 (approximate)[4]
Ítaca Andorra-Sierra de Arcos, Teruel, Aragón, Spain[4] 41.0000, -0.3851 (approximate)[4]

The map below shows the approximate locations of the wind farm phases:

Loading map...

Articles and Resources

Additional data

To access additional data, including an interactive map of global wind farms, a downloadable dataset, and summary data, please visit the Global Wind Power Tracker on the Global Energy Monitor website.

References

  1. 1.0 1.1 1.2 1.3 1.4 1.5 1.6 https://www.diariodeteruel.es/bajoaragon/el-macroproyecto-de-renovables-de-endesa-para-el-nudo-de-andorra-sera-admitido-a-tramite-en-febrero, https://www.heraldo.es/noticias/aragon/teruel/2023/11/29/endesa-aumenta-la-inversion-en-nudo-mudejar-de-andorra-en-200-millones-1694238.html https://www.endesa.com/es/prensa/sala-de-prensa/noticias/transicion-energetica/endesa-presenta-plan-futuro-andorra-dejara-dentro-5-anos-500-empleos-fijos, https://www.diariodeteruel.es/bajoaragon/el-macroproyecto-de-renovables-de-endesa-para-el-nudo-de-andorra-sera-admitido-a-tramite-en-febrero, https://www.heraldo.es/noticias/aragon/teruel/2023/11/29/endesa-aumenta-la-inversion-en-nudo-mudejar-de-andorra-en-200-millones-1694238.html. {{cite web}}: Check |url= value (help); Missing or empty |title= (help)
  2. 2.0 2.1 2.2 2.3 2.4 2.5 2.6 https://www.heraldo.es/noticias/aragon/teruel/2023/11/29/endesa-aumenta-la-inversion-en-nudo-mudejar-de-andorra-en-200-millones-1694238.html. {{cite web}}: Missing or empty |title= (help)
  3. 3.0 3.1 3.2 3.3 3.4 https://elperiodicodelaenergia.com/el-megaplan-de-endesa-para-andorra-teruel-1-500-mw-de-renovables-la-mayor-bateria-de-espana-hidrogeno-y-el-uso-de-compensadores-sincronos/ https://www.endesa.com/es/prensa/sala-de-prensa/noticias/transicion-energetica/endesa-presenta-plan-futuro-andorra-dejara-dentro-5-anos-500-empleos-fijos, https://elperiodicodelaenergia.com/el-megaplan-de-endesa-para-andorra-teruel-1-500-mw-de-renovables-la-mayor-bateria-de-espana-hidrogeno-y-el-uso-de-compensadores-sincronos/. {{cite web}}: Check |url= value (help); Missing or empty |title= (help)
  4. 4.00 4.01 4.02 4.03 4.04 4.05 4.06 4.07 4.08 4.09 4.10 4.11 4.12 4.13 4.14 4.15 4.16 4.17 4.18 4.19 4.20 4.21 4.22 4.23 4.24 4.25 4.26 4.27 4.28 4.29 "Endesa presenta su plan de futuro para Andorra que dejará dentro de 5 años 500 empleos fijos y duraderos en la zona". Endesa. 2022-12-15. Archived from the original on 2024-01-26.