Pan'nan low-heat-value coal power station

From Global Energy Monitor
Part of the
Global Coal Plant Tracker,
a Global Energy Monitor project.
Download full dataset
Report an error
Related coal trackers:

Pan'nan low-heat-value coal power station (盘南2×660MW超超临界CFB燃煤发电机组, 贵州盘南低热值煤资源综合利用发电项目) is an operating power station of at least 660-megawatts (MW) in Dashan, Panzhou, Liupanshui, Guizhou, China with multiple units, some of which are not currently operating. It is also known as 盘南风光火储多能互补能源基地2×660MW低热值煤资源综合利用发电项目.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Pan'nan low-heat-value coal power station Dashan, Panzhou, Liupanshui, Guizhou, China 25.431494, 104.647459 (exact)[1]
Loading map...

Unit-level coordinates (WGS 84):

  • Unit 1, Unit 2: 25.431494, 104.647459

Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology Start year Emergency/Backup
Unit 1 Operating[2][3] coal: unknown[1][4] 660[1] ultra-supercritical[1] 2026[2] False
Unit 2 Construction[3] coal: unknown[1][4] 660[1] ultra-supercritical[1] 2026 (planned) False

Table 3: Unit-level ownership and operator details

Unit name Owner Parent
Unit 1 China Power Construction Panzhou Low Calorific Value Coal Power Generation Co Ltd [100%] Power Construction Corporation of China Ltd [100.0%]
Unit 2 China Power Construction Panzhou Low Calorific Value Coal Power Generation Co Ltd [100%] Power Construction Corporation of China Ltd [100.0%]

Project-level coal details

  • Coal source(s): domestic
  • Permit(s): 黔发改能源〔2022〕719号[1], 黔发改能源【2022】719号[1]

Ownership Tree

This ownership tree is part of the Global Energy Ownership Tracker, a project of Global Energy Monitor.

Background

This 2 x 660 MW ultra-supercritical CFB coal-fired power station was reportedly permitted to build (黔发改能源〔2022〕719号) by Guizhou Provincial Development and Reform Commission on 20 September 2022.[5][6]

In 2022, the project was included in the construction plan of thermal power projects in Guizhou Province.[7]

In 2023, the project was included in the Guizhou Province Coal Power Projects Three-Year Action Plan (2023-2025), with construction expected to start in July 2023.[8] The two units were expected to be in operation by 2025.[8]

Harbin Electric Co. Ltd. won the contract to supply the generators[9][10] and Dongfang Boiler Group Co., Ltd won the bid to supply boilers.[11][12]

Unit 1 had the EPC contract awarded in November 2023[13], and the contract was signed in December[14]. In April 2024, a project inspection was conducted[15], and in May the first concrete was poured[16]. In July, the boiler steel frame for Unit 1 began hoisting[17]. In December, the boiler beam was hoisted[18]. By January 2025, the project was 30% complete[19]. In March, the chimney outer cylinder was topped out[20]. In June, the generator stator was hoisted[21], and in July the generator rotor was inserted[22]. By October, 31 milestones had been completed[23]. In December, boiler ignition succeeded[24]. In January 2026, flushing was completed[25], and the unit was connected to the grid later that month[26]. In April, Unit 1 passed the 168-hour trial[27].

Unit 2 had its first boiler steel frame hoisted in September 2024[28]. In April 2025, the boiler beam was hoisted[29]. In September, the cooling tower was topped out[30]. In May 2026, boiler ignition for Unit 2 succeeded[31]. In July, Unit 2 passed the 168-hour trial, completing the project[32].

Articles and Resources

References

  1. 1.0 1.1 1.2 1.3 1.4 1.5 1.6 1.7 1.8 http://fgw.gzlps.gov.cn/ywgz_42246/zdxmjs/gzjz/202209/t20220923_76551003.html. {{cite web}}: Missing or empty |title= (help)
  2. 2.0 2.1 https://news.bjx.com.cn/html/20260420/1492599.shtml. {{cite web}}: Missing or empty |title= (help)
  3. 3.0 3.1 "贵州盘南2×660MW低热值煤发电项目正式开工-北极星火力发电网". news.bjx.com.cn. 2024-05-20. Archived from the original on 2024-05-31. Retrieved 2024-05-31.
  4. 4.0 4.1 https://www.gem.wiki/Coal_source_methodology_for_the_Global_Coal_Plant_Tracker. {{cite web}}: Missing or empty |title= (help)
  5. "盘南2×660MW低热值煤资源综合利用发电项目获得核准". 北极星火力发电网. 2022-09-26. Retrieved 2023-02-06.
  6. 盘南低热值煤资源综合利用发电项目获省级核准 Liu Pan Shui Development and Reform Commission, Sept. 23, 2022
  7. 马邦凯与六盘水市委副书记、盘州市委书记杨引明举行会谈 Power China Investment Corporation, 2022-08-29
  8. 8.0 8.1 省能源局关于公开征求《贵州省煤电项目建设三年攻坚行动方案(2023-2025年)》意见的函 Guizhou Energy Commission, June 2, 2023
  9. 哈电机微讯:石成义 (2023-07-28). "哈电电机中标盘南2台660兆瓦汽轮发电机". 北极星火力发电网. Retrieved 2023-9-8. {{cite web}}: Check date values in: |access-date= (help)CS1 maint: url-status (link)
  10. 哈汽小微 (2023-07-31). "哈电汽轮机中标盘南2X660MW低热值煤发电项目汽轮发电机组及其附属设备采购项目". 火电之声. Retrieved 2023-09-08.{{cite web}}: CS1 maint: url-status (link)
  11. 东锅微讯:黄一龙 (2023-09-05). ""东方造"大容量循环流化床机组+2!". 北极星火力发电网. Retrieved 2023-09-08.{{cite web}}: CS1 maint: url-status (link)
  12. "东方锅炉中标盘南2X660MW低热值煤发电项目锅炉及其附属设备采购项目". 火电之声. 2023-08-07. Retrieved 2023-09-08.{{cite web}}: CS1 maint: url-status (link)
  13. "盘南2×660MW低热值煤发电EPC中标". 微信公众平台. 2023-12-21. Retrieved 2026-07-30.{{cite web}}: CS1 maint: url-status (link)
  14. "盘南项目EPC合同签字仪式". 微信公众平台. 2024-01-03. Retrieved 2026-07-30.{{cite web}}: CS1 maint: url-status (link)
  15. "盘南项目检查指导". 贵州工程公司. 2024-04-01. Retrieved 2026-07-30.{{cite web}}: CS1 maint: url-status (link)
  16. "盘南项目主厂房第一罐混凝土浇筑". 微信公众平台. 2024-05-31. Retrieved 2026-07-30.{{cite web}}: CS1 maint: url-status (link)
  17. "盘南1号锅炉钢架开始吊装". 北极星电力网. 2024-07-18. Retrieved 2026-07-30.{{cite web}}: CS1 maint: url-status (link)
  18. "盘南1号锅炉大板梁吊装成功". 微信公众平台. 2025-02-03. Retrieved 2026-07-30.{{cite web}}: CS1 maint: url-status (link)
  19. "盘南项目完成工程量30%". 微信公众平台. 2025-02-03. Retrieved 2026-07-30.{{cite web}}: CS1 maint: url-status (link)
  20. "盘南项目烟囱外筒到顶". 微信公众平台. 2025-04-01. Retrieved 2026-07-30.{{cite web}}: CS1 maint: url-status (link)
  21. "盘南1号发电机定子吊装就位". 微信公众平台. 2025-06-20. Retrieved 2026-07-30.{{cite web}}: CS1 maint: url-status (link)
  22. "盘南1号发电机转子穿装成功". 微信公众平台. 2025-08-05. Retrieved 2026-07-30.{{cite web}}: CS1 maint: url-status (link)
  23. "盘南项目完成31项重大里程碑". 微信公众平台. 2025-10-29. Retrieved 2026-07-30.{{cite web}}: CS1 maint: url-status (link)
  24. "盘南1号机组锅炉点火启动成功". 微信公众平台. 2026-01-06. Retrieved 2026-07-30.{{cite web}}: CS1 maint: url-status (link)
  25. "盘南1号锅炉吹管完成". 微信公众平台. 2026-02-24. Retrieved 2026-07-30.{{cite web}}: CS1 maint: url-status (link)
  26. "盘南1号机组并网发电". 微信公众平台. 2026-03-10. Retrieved 2026-07-30.{{cite web}}: CS1 maint: url-status (link)
  27. "盘南1号机组168小时试运行成功". 微信公众平台. 2026-05-15. Retrieved 2026-07-30.{{cite web}}: CS1 maint: url-status (link)
  28. "盘南2号锅炉首根钢架吊装". 北极星电力网. 2024-10-10. Retrieved 2026-07-30.{{cite web}}: CS1 maint: url-status (link)
  29. "盘南2号锅炉大板梁吊装就位". 微信公众平台. 2025-05-14. Retrieved 2026-07-30.{{cite web}}: CS1 maint: url-status (link)
  30. "盘南2号冷却塔主体结构到顶". 微信公众平台. 2025-10-29. Retrieved 2026-07-30.{{cite web}}: CS1 maint: url-status (link)
  31. "盘南2号机组锅炉点火成功". 微信公众平台. 2026-05-15. Retrieved 2026-07-30.{{cite web}}: CS1 maint: url-status (link)
  32. "盘南项目2号机组168小时试运行成功". 北极星电力网. 2026-07-08. Retrieved 2026-07-30.{{cite web}}: CS1 maint: url-status (link)

Additional data