Patache power station

From Global Energy Monitor
Part of the
Global Coal Plant Tracker,
a Global Energy Monitor project.
Download full dataset
Report an error
Related coal trackers:

Patache power station (Central termoeléctrica Tarapacá) is a power station in Punta Patache, Iquique, Tarapacá Region, Chile with multiple units of varying statuses none of which are currently operating. It is also known as Tarapacá power station.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Patache power station Punta Patache, Iquique, Tarapacá Region, Chile -20.80532, -70.193195 (exact)

The map below shows the exact location of the power station.

Loading map...


Unit-level coordinates (WGS 84):

  • Unit 1, Unit 2: -20.80532, -70.193195

Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology Start year Retired year
Unit 1 retired coal - bituminous 154 subcritical 1998 2019
Unit 2 cancelled coal - bituminous 110 subcritical

Table 3: Unit-level ownership and operator details

Unit name Owner
Unit 1 Enel Generación Chile SA [100.0%]
Unit 2 Enel Generación Chile SA [100.0%]

Background

The 158 MW Patache plant is owned by Enel Generación Chile (formerly Compañía Eléctrica Tarapacá), a subsidiary of the Italian multinational Enel S.p.A. It began operating in January 1999.[1][2]

Planned retirement

In June 2019 the Chilean government announced that the plant would be retired by 2024 as part of a plan to reduce the country's annual CO2 emissions from the current 30 million tonnes (tons) to four million by 2024.[3] In July 2019 Enel received permission from the Chilean government to close the plant as of Dec. 31, 2019.[4] The plant was officially shut down at the end of December 2019[1][5], marking an important early step in Enel's company-wide decarbonization plan.[6]

Proposed expansion

A 110 MW expansion unit was planned at the Punto Patache location. In May 2011 Compañía Eléctrica Tarapacá won approval for the project from the regional environmental commission CEA (Comisión de Evaluación Ambiental) to build a second unit at the same location, despite strong community opposition and sustained protests by local fishermen, environmentalists and others concerned about health and environmental dangers posed by the plant.[7] CEA's decision was upheld in October 2011 by the Chilean Supreme Court[8] and again in September 2012 by a committee of Chilean government ministers headed by Environment Minister María Ignacia Benítez.[9][10] As of 2015, industry source Equus Mining lists the expansion as approved but not yet under construction.[11]

However, given Chile's ongoing move towards renewable energy sources, the lack of subsequent coverage of the expansion in the Chilean press, and the fact that the project is no longer mentioned on Enel’s website as of January 2018[12], the Patache expansion appears to have been abandoned.

Violations of environmental code

In September 2013, Chile's environmental regulator SMA charged the Patache plant with several violations of environmental code. As reported by BNAmericas, "SMA inspections discovered that at 100,000t the coal yard was over its maximum permitted capacity of 70,000t and lacked barriers to retain particulates, the ash decanter pools exceeded more than three times their 400m3 capacity and the ash dump was not properly compacted. Inspectors also discovered an unauthorized fuel storage system, minor fuel spills and improper storage of dangerous substances, as well as dead birds and marine life in the plant's seawater intake system. Due to the severity of the charges, the firm faces fines of up to 5,000 annual tax units (UTA) (US$4.76mn), revocation of the coal-fired plant's RCA permit or even shutdown of the facility." In late October 2013, Endesa presented an environmental compliance plan addressing the problems detected during SMA's inspection. SMA sources said that the agency was studying the plan and expected to decide within a few weeks whether to impose sanctions.[13]

Articles and Resources

References

  1. 1.0 1.1 "Hoy se concreta cierre definitivo de la central termoeléctrica Tarapacá | Gobierno Regional de Tarapacá". Gobierno Regional de Tarapacá. 2019-12-31.{{cite web}}: CS1 maint: url-status (link)
  2. "PLAN DE DESCARBONIZACION Y RETIRO DE CENTRALES TERMOELÉCTRICAS A CARBÓN EN CHILE" (PDF). Chile Sustentable. June 4, 2019.{{cite web}}: CS1 maint: url-status (link)
  3. Chile to close eight coal-fired stations by 2024, IEEFA, Jun., 2019
  4. Enel Chile receives permit to shut down coal-fired plant early, Renewables Now, Jul. 29, 2019
  5. Enel Chile cierra Central de Tarapacá y es su primera planta de carbón en cesar operaciones, America Economia, Jan. 2, 2020
  6. "Enel to unveil coal closure plan on November 24". S&P Global Platts. 2020-11-06.{{cite web}}: CS1 maint: url-status (link)
  7. "Termoeléctricas Patache y Pacífico son aprobadas en Iquique a pesar del repudio ciudadano,", Observatorio Latinoamericano de Conflictos Ambientales, May 8, 2011.
  8. "Corte Suprema da luz verde a construcción de termoeléctricas Pacífico y Patache,", Emol, Oct 19, 2011.
  9. Sebastian Boyd, "Chile Ministers Approve Coal-Fired Power Plants, Tercera Says," Bloomberg, Sep 8, 2012.
  10. "Aprueban construcción de termoeléctricas Patache y Pacífico: Organizaciones ambientalistas en alerta,", El Boyaldía, Sept 9, 2012.
  11. "Reducing Chile's Dependency on Energy Imports,", Equus Mining Ltd report, February 2015.
  12. "Enel Generación Chile," Enel website, accessed Jan 14, 2018
  13. "Presentan plan de cumplimiento ambiental para central Patache - Electricidad". La Tercera. November 5, 2013.{{cite web}}: CS1 maint: url-status (link)