Payra FSRU
| Part of the Global Gas Infrastructure Tracker, a Global Energy Monitor project. |
Payra FSRU is a proposed LNG import terminal in Bangladesh.
Location
Table 1: Location details
| Name | Location | Coordinates (WGS 84) |
|---|---|---|
| Payra FSRU | Payra Sea Port, Kalapara, Patuakhali, Bangladesh[1] | 21.988808, 90.280506 (approximate) |
The map below shows the approximate location of the terminal:
Project Details
Table 2: Infrastructure details
| Name | Facility type | Status | Capacity | Total terminal capacity | Offshore | Associated infrastructure |
|---|---|---|---|---|---|---|
| Payra FSRU | import[2] | proposed[3] | 3.75 mtpa[4] | 3.75 mtpa | True | – |
Table 3: Cost
| Name | Facility type | Cost | Total known terminal costs |
|---|---|---|---|
| Payra FSRU | import[2] | – | – |
Financing
No financing data available.
Table 4: Project timeline
| Name | Facility type | Status | Proposal year | FID year | Construction year | Operating year | Inactive year |
|---|---|---|---|---|---|---|---|
| Payra FSRU | import[2] | proposed[3] | 2017[5] | – | – | 2028[1][3][1] | –[6] |
Ownership
Table 5: Ownership
| Name | Facility type | Status | Owners | Parent companies | Operator |
|---|---|---|---|---|---|
| Payra FSRU | import[2] | proposed[3] | Excelerate Energy LP [100%][3] | Excelerate Energy Inc [24.3%]; Excelerate Energy Holdings LLC | Excelerate Energy[1][3] |
Background
In 2017, State-owned Rupantarita Prakritik Gas Company Limited (RPGCL) invited expressions of interest (EoI) from prospective bidders to set up a liquefied natural gas (LNG) terminal at Payra maritime port area in Patuakhali.[7]
In September 2021, Bangladesh's Energy and Mineral Resources Division under the Ministry of Power, Energy and Mineral Resources decided to conduct a feasibility study for a FSRU project at Payra, amid growing lobbying from parties interested in developing the project. US-based Excelerate Energy, Bangladesh's Summit Group, and the state-run North West Power Generation Company Ltd (NWPGCL) are among the interested firms.[8]
In March 2023, Excelerate’s CEO Steven Kobos told analysts that the company was working on advancing this project and that the project's proposed scope involved an offshore FSRU import terminal and an onshore pipeline to the city of Khulna. Kobos stated that the company has invested about $5 million in the project up to date. At the time, the company was "finalizing a term sheet with Petrobangla, evaluating financing options and was in discussions with potential partners for the project".[9]
As part of the project, Excelerate was also negotiating a long-term LNG supply agreement with the government of Bangladesh.[9] In November 2023, Excelerate Energy and Petrobangla have signed an LNG sale and purchase agreement under which Petrobangla agreed to purchase 0.85 to 1 mtpa of LNG from Excelerate for a term of 15 years beginning January 2026.[10]
In June 2023, it was reported that Excelerate Energy was still in the process of developing the terminal.[11]
In January 2024, Petrobangla's Director of Operation stated that there were three new LNG terminals to be set up in Payra, Moheshkhali and Matarbari, with the terminal at Payra expected to be commissioned by 2028.[12]
In May 2024, it was reported that the company was still intending to develop the terminal.[13]
In November 2024, Gas Outlook reported that Bangladesh's interim government had scrapped deals with several prospective LNG terminal developers in a move to overturn deals signed under a special law by Bangladesh's prior authoritarian Awami Leauge government. Among the projects targeted was Payra FSRU, as the government scrapped a term-sheet agreement with Excelerate Energy. Gas Outlook wrote that "Petrobangla would need to extend the tenure of the term-sheet agreement and ink a [Terminal Use Agreement] with Excelerate Energy to ensure its effectiveness," according to Petrobangla's chairman.[14]
Articles and Resources
Additional data
To access additional data, including an interactive map of LNG terminals, a downloadable dataset, and summary data, please visit the Global Gas Infrastructure Tracker on the Global Energy Monitor website.
References
- ↑ 1.0 1.1 1.2 1.3 https://www.observerbd.com/news.php?id=456940.
{{cite web}}: Missing or empty|title=(help) - ↑ 2.0 2.1 2.2 2.3 (PDF) https://www.adb.org/sites/default/files/linked-documents/50161-003-sd-04.pdf.
{{cite web}}: Missing or empty|title=(help) - ↑ 3.0 3.1 3.2 3.3 3.4 3.5 https://lngprime.com/americas/excelerate-to-supply-spot-lng-cargo-to-bangladesh-working-on-payra-deal/77458/.
{{cite web}}: Missing or empty|title=(help) - ↑ https://thefinancialexpress.com.bd/public/trade/growing-lobbying-prompts-authorities-to-decide-to-conduct-study-on-fsru-at-payra-1631759768.
{{cite web}}: Missing or empty|title=(help) - ↑ https://www.dhakatribune.com/bangladesh/power-energy/2017/12/18/lng-terminal-payra-seaport.
{{cite web}}: Missing or empty|title=(help) - ↑ https://web.archive.org/web/20221031142630/http://en.prothomalo.com/bangladesh/ptkzj7h291. Archived from the original on 2022-10-31.
{{cite web}}: Missing or empty|title=(help) - ↑ Another LNG terminal at Payra in the offing, Dhaka Tribune, December 18th, 2017
- ↑ Express, The Financial. "Growing lobbying prompts authorities to decide to conduct study on FSRU at Payra". The Financial Express. Retrieved 2022-06-09.
- ↑ 9.0 9.1 "Excelerate to supply spot LNG cargo to Bangladesh, working on Payra deal". LNGPrime. Mar 29, 2023. Retrieved June 5, 2024.
{{cite web}}: CS1 maint: url-status (link) - ↑ "Excelerate Energy and Petrobangla pen 15-year LNG supply deal". Offshore Energy. Nov 9, 2023. Retrieved June 4, 2024.
{{cite web}}: CS1 maint: url-status (link) - ↑ "Summit plans to develop a second FSRU project in Bangladesh by 2026". Kpler.com. June 1, 2023. Retrieved June 5, 2024.
{{cite web}}: CS1 maint: url-status (link) - ↑ "Petrobangla plans to set up 3 more LNG terminals". Daily Observer. Jan 25, 2024. Retrieved June 5, 2024.
{{cite web}}: CS1 maint: url-status (link) - ↑ "Excelerate reveals growth plans". LNGPrime. May 13, 2024. Retrieved June 5, 2024.
{{cite web}}: CS1 maint: url-status (link) - ↑ "Bangladeshi state-run Petrobangla scraps LNG deals - Gas Outlook". Gas Outlook. Retrieved 2025-08-18.