Peusanga hydroelectric plant
From Global Energy Monitor
Part of the Global Hydropower Tracker, a Global Energy Monitor project. |
Other names: Peusanga 1 & 2 hydroelectric plant
Peusanga hydroelectric plant (PLTA Peusanga 1 & 2, PLTA Peusanga) is a hydroelectric power plant under construction in Isaq Village, Linge District, Central Aceh Regency, Aceh Province, Indonesia.
Project Details
Table 1: Project details for Peusanga hydroelectric plant
Status | Commissioning year | Nameplate capacity | Turbines | Technology type | Owner |
---|---|---|---|---|---|
Construction[1][2] | 2025[3] | 88 MW[2] | 2 x 23.1 MW; 2 x 22 MW[4] | Run-of-river[2] | PT PLN (Persero) [100%] (PT Perusahaan Listrik Negara)[5] |
Location
Table 2: Location details for Peusanga hydroelectric plant
Location | River | Coordinates (WGS 84) |
---|---|---|
Isaq Village, Linge District, Central Aceh Regency, Aceh Province, Indonesia[5] | Peusangan River[6] | 4.4495, 96.8839 (approximate)[5] |
The map below shows the approximate location of the hydroelectric power plant:
Articles and Resources
Additional data
To access additional data, including an interactive map of global hydroelectric power plants, a downloadable dataset, and summary data, please visit the Global Hydropower Tracker on the Global Energy Monitor website.
References
- ↑ https://www.petromindo.com/news/article/peusangan-hydropower-plant-to-start-commercial-operation-in-october.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 2.0 2.1 2.2 https://www.pwc.com/id/en/media-centre/infrastructure-news/may-2022/pln-targets-operation-of-peusangan-hydroelectric-power-plant.
{{cite web}}
: Missing or empty|title=
(help) - ↑ https://web.archive.org/web/20240109005434/https://en.antaranews.com/news/297549/minister-stresses-hydropower-use-to-speed-up-energy-transition. Archived from the original on 2024-01-09.
{{cite web}}
: Missing or empty|title=
(help) - ↑ (PDF) https://www.andritz.com/resource/blob/31246/e29852aa1eed5d1d8fd8d7be55938fee/hy-25-peusangan-1-2-data.pdf.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 5.0 5.1 5.2 https://www.pwc.com/id/en/media-centre/infrastructure-news/may-2022/pln-targets-operation-of-peusangan-hydroelectric-power-plant-in-july-2023.html.
{{cite web}}
: Missing or empty|title=
(help) - ↑ https://web.archive.org/web/20210920025020/https://www.andritz.com/hydro-en/hydronews/25/hy-25-10-peusangan. Archived from the original on 2021-09-20.
{{cite web}}
: Missing or empty|title=
(help)