Portovesme FSRU
| Part of the Global Gas Infrastructure Tracker, a Global Energy Monitor project. |
Portovesme FSRU is a shelved (inferred 2 y) LNG import terminal in Italy.
Location
Table 1: Location details
| Name | Location | Coordinates (WGS 84) |
|---|---|---|
| Portovesme FSRU | Portovesme, Italy[1] | 39.195612, 8.391925 (approximate) |
The map below shows the approximate location of the terminal:
Project Details
Table 2: Infrastructure details
| Name | Facility type | Status | Capacity | Total terminal capacity | Offshore | Associated infrastructure |
|---|---|---|---|---|---|---|
| Portovesme FSRU | import[1] | shelved (inferred 2 y) | – | – | True | – |
Table 3: Cost
| Name | Facility type | Cost | Total known terminal costs |
|---|---|---|---|
| Portovesme FSRU | import[1] | US$283,000,000[2] | US$283,000,000 |
Financing
No financing data available.
Table 4: Project timeline
| Name | Facility type | Status | Proposal year | FID year | Construction year | Operating year | Inactive year |
|---|---|---|---|---|---|---|---|
| Portovesme FSRU | import[1] | shelved (inferred 2 y) | 2021[3] | – | – | –[4][5][4][5] | – |
Ownership
Table 5: Ownership
| Name | Facility type | Status | Owners | Parent companies | Operator |
|---|---|---|---|---|---|
| Portovesme FSRU | import[1] | shelved (inferred 2 y) | Snam SpA [100%][1] | Snam SpA [100.0%] | Snam[4] |
Table 6: Vessel ownership
| Name | Facility type | Status | Vessel | Vessel owners |
|---|---|---|---|---|
| Portovesme FSRU | import[1] | shelved (inferred 2 y) | Golar Arctic[6][7] | Golar LNG[6][7] |
Background
SNAM expressed interest in a second (following HIGAS LNG Terminal) import terminal on the island of Sardinia in February 2021.[8]
In May 2022, Golar LNG signed a deal with SNAM to convert its LNG carrier, known as "Golar Arctic", into a floating storage and regasification unit for SNAM.[9] Once the conversion is completed, the vessel will be sold to SNAM. The contract was priced at 269 million euros (283.3 million USD). In 2022, Golar stated that the conversion and delivery of the FRSU would be complete by 2024.[10]
According to 2022 news reports, the project is a part of the Italy's plans to boost LNG imports, replacing Russian oil and gas, following the invasion of Ukraine.[10]
In August 2023, LNG Prime reported that Golar LNG's deal to covert the Golar Arctic into an FSRU had fallen through because SNAM had not issued a notice to proceed. According to Golar's CEO, “This option lapsed in July and we are now reviewing alternatives for [the vessel], including long-term charter or asset sale.”[11]
As of July 2025, there have been no project updates in over two years, and the project is inferred to be shelved.
Articles and Resources
Additional data
To access additional data, including an interactive map of LNG terminals, a downloadable dataset, and summary data, please visit the Global Gas Infrastructure Tracker on the Global Energy Monitor website.
References
- ↑ 1.0 1.1 1.2 1.3 1.4 1.5 1.6 https://www.ogj.com/pipelines-transportation/lng/article/14276809/snam-signs-golar-for-sardinia-fsru-conversion.
{{cite web}}: Missing or empty|title=(help) - ↑ https://lngprime.com/europe/golar-inks-deal-with-snam-to-supply-converted-fsru-for-sardinian-project/51836/.
{{cite web}}: Missing or empty|title=(help) - ↑ https://www.tradewindsnews.com/gas/snam-invites-interest-on-fsru-for-sardinian-project/2-1-963024.
{{cite web}}: Missing or empty|title=(help) - ↑ 4.0 4.1 4.2 (PDF) https://www.snam.it/export/sites/snam-rp/repository/ENG_file/Governance/Social_bodies/Shareholders_meeting/Questions-and-answers-ReCommon.pdf.
{{cite web}}: Missing or empty|title=(help) - ↑ 5.0 5.1 https://www.snam.it/en/Media/Press-releases/2022/Snam_Golar_LNG_FSRU_Sardinia.html.
{{cite web}}: Missing or empty|title=(help) - ↑ 6.0 6.1 https://lngprime.com/contracts-and-tenders/golars-fsru-conversion-deal-with-italys-snam-falls-through/88647/.
{{cite web}}: Missing or empty|title=(help) - ↑ 7.0 7.1 https://www.energyintel.com/00000184-2f21-d8b5-ab9f-af2d9dfd0000.
{{cite web}}: Missing or empty|title=(help) - ↑ Hine (l_hine), Lucy (2021-02-16). "SNAM invites interest on FSRU for Sardinian project | TradeWinds". TradeWinds | Latest shipping and maritime news. Retrieved 2022-06-29.
- ↑ Cite error: Invalid
<ref>tag; no text was provided for refs named:3 - ↑ 10.0 10.1 Staff, LNG Prime (2022-05-18). "Golar inks deal with Snam to supply converted FSRU for Sardinian project". LNG Prime. Retrieved 2022-06-29.
- ↑ Cite error: Invalid
<ref>tag; no text was provided for refs named:5