Qinhuangdao-2 power station
| Part of the Global Coal Plant Tracker, a Global Energy Monitor project. |
| Related coal trackers: |
Qinhuangdao-2 power station (秦皇岛热电厂) is an operating power station of at least 1900-megawatts (MW) in Jianshe Avenue, Haigang, Qinhuangdao, Hebei, China with multiple units, some of which are not currently operating. It is also known as 河北建投神华国能秦皇岛发电厂 (Unit 1 & 2, Unit 3 & 4), 国电电力秦皇岛公司2×350MW燃煤机组扩建工程 (New Unit 1 & 2), 河北建投秦皇岛秦热发电厂 (Unit 5 & 6), 河北建投神华国能秦皇岛发电公司一期等容量替代发电项目 (New Unit 1 & 2).
Location
Table 1: Project-level location details
| Plant name | Location | Coordinates (WGS 84) |
|---|---|---|
| Qinhuangdao-2 power station | Jianshe Avenue, Haigang, Qinhuangdao, Hebei, China | 39.945305, 119.6430272 (exact)[1] |
Unit-level coordinates (WGS 84):
- Replace Unit 1 (Unit 7), Replace Unit 2 (Unit 8), Unit 1, Unit 2, Unit 3, Unit 4, Unit 5, Unit 6: 39.945305, 119.6430272
Project Details
Table 2: Unit-level details
| Unit name | Status | Fuel(s) | Capacity (MW) | Technology | CHP | Start year | Retired year | Emergency/Backup |
|---|---|---|---|---|---|---|---|---|
| Replace Unit 1 (Unit 7) | Operating[2][3] | coal: bituminous[4][1] | 350[1] | supercritical[1] | yes[1] | 2025[5] | – | False |
| Replace Unit 2 (Unit 8) | Operating[6][3] | coal: bituminous[4][1] | 350[5] | supercritical[5] | yes[5] | 2026[6][5] | – | False |
| Unit 1 | Retired[7] | coal: bituminous[4] | 215 | subcritical | yes | 1992 | 2025[7] | False |
| Unit 2 | Mothballed | coal: bituminous[4] | 215 | subcritical | yes | 1993 | 2025 (planned) | False |
| Unit 3 | Operating | coal: bituminous[4] | 300 | subcritical | yes | 1996 | – | False |
| Unit 4 | Operating | coal: bituminous[4] | 300 | subcritical | yes | 1996 | – | False |
| Unit 5 | Operating | coal: bituminous[4] | 300 | subcritical | yes | 2007 | – | False |
| Unit 6 | Operating | coal: bituminous[4] | 300 | subcritical | yes | 2007 | – | False |
Table 3: Unit-level ownership and operator details
| Unit name | Owner | Parent |
|---|---|---|
| Replace Unit 1 (Unit 7) | Qinhuangdao Power Generation Co Ltd [100%][1] | China Energy Investment Corp [50.0%]; Hebei Construction & Investment Group Co Ltd [50.0%] |
| Replace Unit 2 (Unit 8) | Qinhuangdao Power Generation Co Ltd [100%][1] | China Energy Investment Corp [50.0%]; Hebei Construction & Investment Group Co Ltd [50.0%] |
| Unit 1 | Qinhuangdao Power Generation Co Ltd [100%] | China Energy Investment Corp [50.0%]; Hebei Construction & Investment Group Co Ltd [50.0%] |
| Unit 2 | Qinhuangdao Power Generation Co Ltd [100%] | China Energy Investment Corp [50.0%]; Hebei Construction & Investment Group Co Ltd [50.0%] |
| Unit 3 | Qinhuangdao Power Generation Co Ltd [100%] | China Energy Investment Corp [50.0%]; Hebei Construction & Investment Group Co Ltd [50.0%] |
| Unit 4 | Qinhuangdao Power Generation Co Ltd [100%] | China Energy Investment Corp [50.0%]; Hebei Construction & Investment Group Co Ltd [50.0%] |
| Unit 5 | Qinhuangdao Qinre Power Generation Co Ltd [100%] | Hebei Construction Investment Energy Investment Co Ltd [40.0%]; Jinneng Holding Shanxi Electric Power Co Ltd [40.0%]; Qinhuangdao Thermal Power Investment Management Center [20.0%] |
| Unit 6 | Qinhuangdao Qinre Power Generation Co Ltd [100%] | Hebei Construction Investment Energy Investment Co Ltd [40.0%]; Jinneng Holding Shanxi Electric Power Co Ltd [40.0%]; Qinhuangdao Thermal Power Investment Management Center [20.0%] |
Project-level coal details
- Coal source(s): domestic
Background
Qinhuangdao-2 power station is a six-unit coal-fired power plant with a total capacity of 1,630 MW. The plant was completed between 1992 and 2007, and is majority-owned by Hebei Construction & Investment Group.[8]
Expansion project
Two new units of 350 MW each are planned to replace units 1-2 of the power station. The project was on 2023 Hebei provincial key construction projects list.[9]
As of March 2021, plans for the new units was undergoing feasibility studies.[10] By the end of August 2023, no permit information could be found apart from various calls for bidding.[11][12]
The replacement units (Unit 7 and 8) are now operational. In 2023, the project was permitted, and construction began.[13]
In 2024, the project appeared on Hebei's key projects list, and by June, the first concrete was poured.[14][15] The old Unit 1 was mothballed in 2024.[16]
In 2025, construction was ongoing, and Unit 7 was retired from its backup role in October 2025.[17]
By early 2026, both new units (7 and 8) successfully passed 168‑hour full‑load trials.[18][19][20]
Articles and Resources
References
- ↑ 1.0 1.1 1.2 1.3 1.4 1.5 1.6 1.7 "国能2×350兆瓦等容量替代热电联产项目正式开工". Weixin Official Accounts Platform. 2023-10-28. Archived from the original on 2024-01-25. Retrieved 2023-10-30.
- ↑ https://news.bjx.com.cn/html/20251231/1477425.shtml.
{{cite web}}: Missing or empty|title=(help) - ↑ 3.0 3.1 https://mp.weixin.qq.com/s/FyLKwbBjnozbtVePOTc48Q.
{{cite web}}: Missing or empty|title=(help) - ↑ 4.0 4.1 4.2 4.3 4.4 4.5 4.6 4.7 https://www.gem.wiki/Coal_source_methodology_for_the_Global_Coal_Plant_Tracker.
{{cite web}}: Missing or empty|title=(help) - ↑ 5.0 5.1 5.2 5.3 5.4 "国能秦皇岛热电厂2×350MW等容量替代热电联产项目开工-北极星火力发电网". news.bjx.com.cn. 2023-10-27. Archived from the original on 2024-01-25. Retrieved 2023-10-30.
- ↑ 6.0 6.1 https://news.bjx.com.cn/html/20260202/1482223.shtml.
{{cite web}}: Missing or empty|title=(help) - ↑ 7.0 7.1 https://news.bjx.com.cn/html/20251023/1466372.shtml.
{{cite web}}: Missing or empty|title=(help) - ↑ Qinhuangdao-2 Powerplant, Enipedia, accessed Sept. 2015.
- ↑ "河北省公布2023年重点建设项目名单". 河北省发展改革委. 2023-01-31. Retrieved 2023-9-7.
{{cite web}}: Check date values in:|access-date=(help)CS1 maint: url-status (link) - ↑ "秦皇岛发电有限责任公司2×350MW等容量替代热电联产项目(更新资讯.," Sohu, 2021-04-23
- ↑ "国电电力秦皇岛公司2×350MW等容量替代热电联产项目相关的2项招标". 北极星电力网. 2023-07-27. Retrieved 2023-9-7.
{{cite web}}: Check date values in:|access-date=(help)CS1 maint: url-status (link) - ↑ "【招标】2×350MW!国电电力秦皇岛项目2项招标". 能源电力新观察. 2023-07-27. Retrieved 2023-9-7.
{{cite web}}: Check date values in:|access-date=(help)CS1 maint: url-status (link) - ↑ "国能秦皇岛热电厂2×350MW等容量替代热电联产项目开工". 北极星电力网. 2023-10-27. Retrieved 2026-07-30.
{{cite web}}: CS1 maint: url-status (link) - ↑ "河北省2024年省重点建设项目名单". 北极星电力网. 2024-04-02. Retrieved 2026-07-30.
{{cite web}}: CS1 maint: url-status (link) - ↑ "秦皇岛发电有限责任公司2×350MW等容量替代热电联产项目7号锅炉第一根钢架顺利吊装就位". 微信公众号. 2024-08-28. Retrieved 2026-07-30.
{{cite web}}: CS1 maint: url-status (link) - ↑ "关于2024年河北省火电行业淘汰落后产能目标任务完成情况的公告". 河北省发改委. 2025-03-24. Retrieved 2026-07-30.
{{cite web}}: CS1 maint: url-status (link) - ↑ "关于秦皇岛发电有限责任公司1号机组退出应急备用电源有关事宜的公示". 北极星电力网. 2025-10-23. Retrieved 2026-07-30.
{{cite web}}: CS1 maint: url-status (link) - ↑ "国能秦皇岛公司2×350兆瓦热电联产等容量替代项目7号机组顺利通过168小时满负荷试运行". 微信公众号. 2026-01-05. Retrieved 2026-07-30.
{{cite web}}: CS1 maint: url-status (link) - ↑ "中国能建天津电建承建的河北秦皇岛项目8号机组首次并网一次成功". 北极星电力网. 2026-01-09. Retrieved 2026-07-30.
{{cite web}}: CS1 maint: url-status (link) - ↑ "国能秦皇岛公司2×350兆瓦等容量替代热电联产项目8号机组顺利通过168小时满负荷试运行". 微信公众号. 2026-03-06. Retrieved 2026-07-30.
{{cite web}}: CS1 maint: url-status (link)
Additional data
To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.