Rivne nuclear power plant
From Global Energy Monitor
| Part of the Global Nuclear Power Tracker, a Global Energy Monitor project. |
Other names: Rovno
Rivne nuclear power plant is an operating nuclear power plant in Rivne Oblast, Ukraine.
Project Details
Table 1: Unit-level project details for Rivne nuclear power plant
| Unit name | Status | Commissioning year | Nameplate capacity | Reactor type | Model | Owner | Operator |
|---|---|---|---|---|---|---|---|
| 1 | Operating[1] | 1981[1] | 420 MW[1] | Pressurized water reactor[1] | VVER V-213[1] | SE NNEGC "Energoatom" [100%][1] | SE NNEGC "Energoatom"[1] |
| 2 | Operating[2] | 1982[2] | 415 MW[2] | Pressurized water reactor[2] | VVER V-213[2] | SE NNEGC "Energoatom" [100%][2] | SE NNEGC "Energoatom"[2] |
| 3 | Operating[3] | 1987[3] | 1000 MW[3] | Pressurized water reactor[3] | VVER V-320[3] | SE NNEGC "Energoatom" [100%][3] | SE NNEGC "Energoatom"[3] |
| 4 | Operating[4] | 2006[4] | 1000 MW[4] | Pressurized water reactor[4] | VVER V-320[4] | SE NNEGC "Energoatom" [100%][4] | SE NNEGC "Energoatom"[4] |
| 5 | Announced[5] | 2029 (planned)[5] | 1250 MW[6] | Pressurized water reactor[7] | AP-1000[6] | SE NNEGC "Energoatom" [100%][6] | SE NNEGC "Energoatom"[6] |
Table 2: Additional unit-level timeline details for Rivne nuclear power plant
| Unit name | Construction start | First criticality (more info) | First grid connection | Commercial operation |
|---|---|---|---|---|
| 1 | August 1, 1973[1] | December 17, 1980[1] | December 22, 1980[1] | September 22, 1981[1] |
| 2 | October 1, 1973[2] | December 19, 1981[2] | December 22, 1981[2] | July 29, 1982[2] |
| 3 | February 1, 1980[3] | November 11, 1986[3] | December 21, 1986[3] | May 16, 1987[3] |
| 4 | August 1, 1986[4] | September 26, 2004[4] | October 10, 2004[4] | April 6, 2006[4] |
| 5 | – | – | – | 2029[5] |
Table 3: Additional unit-level capacity details for Rivne nuclear power plant
(Read more about nuclear capacity definitions.)
| Unit name | Reference net capacity | Design net capacity | Thermal capacity |
|---|---|---|---|
| 1 | 381 MW[1] | 361 MW[1] | 1375 MWt[1] |
| 2 | 376 MW[2] | 384 MW[2] | 1375 MWt[2] |
| 3 | 950 MW[3] | 950 MW[3] | 3000 MWt[3] |
| 4 | 950 MW[4] | 950 MW[4] | 3000 MWt[4] |
Location
Table 4: Unit-level location details for Rivne nuclear power plant
| Unit name | Location | Coordinates (WGS 84) |
|---|---|---|
| 1 | Rivne Oblast, Ukraine[8] | 51.3245, 25.8974 (exact) |
| 2 | Rivne Oblast, Ukraine[8] | 51.3245, 25.8974 (exact) |
| 3 | Rivne Oblast, Ukraine[8] | 51.3245, 25.8974 (exact) |
| 4 | Rivne Oblast, Ukraine[8] | 51.3245, 25.8974 (exact) |
| 5 | Rivne Oblast, Ukraine[8] | 51.3245, 25.8974 (exact) |
The map below shows the exact location of the nuclear power plant:
Articles and Resources
Additional data
To access additional data, including an interactive map of global nuclear power plants, a downloadable dataset, and summary data, please visit the Global Nuclear Power Tracker on the Global Energy Monitor website.
References
- ↑ 1.00 1.01 1.02 1.03 1.04 1.05 1.06 1.07 1.08 1.09 1.10 1.11 1.12 1.13 https://web.archive.org/web/20220524163834/https://pris.iaea.org/PRIS/CountryStatistics/ReactorDetails.aspx?current=570. Archived from the original on 2022-05-24.
{{cite web}}: Missing or empty|title=(help) - ↑ 2.00 2.01 2.02 2.03 2.04 2.05 2.06 2.07 2.08 2.09 2.10 2.11 2.12 2.13 https://web.archive.org/web/20220522163123/https://pris.iaea.org/PRIS/CountryStatistics/ReactorDetails.aspx?current=571. Archived from the original on 2022-05-22.
{{cite web}}: Missing or empty|title=(help) - ↑ 3.00 3.01 3.02 3.03 3.04 3.05 3.06 3.07 3.08 3.09 3.10 3.11 3.12 3.13 https://web.archive.org/web/20220524153211/https://pris.iaea.org/PRIS/CountryStatistics/ReactorDetails.aspx?current=572. Archived from the original on 2022-05-24.
{{cite web}}: Missing or empty|title=(help) - ↑ 4.00 4.01 4.02 4.03 4.04 4.05 4.06 4.07 4.08 4.09 4.10 4.11 4.12 4.13 https://web.archive.org/web/20220524153252/https://pris.iaea.org/PRIS/CountryStatistics/ReactorDetails.aspx?current=589. Archived from the original on 2022-05-24.
{{cite web}}: Missing or empty|title=(help) - ↑ 5.0 5.1 5.2 https://ua-energy.org/en/posts/energoatom-plans-to-build-the-fifth-power-unit-of-the-rivne-npp.
{{cite web}}: Missing or empty|title=(help) - ↑ 6.0 6.1 6.2 6.3 https://web.archive.org/web/20230529145248/https://www.neimagazine.com/news/newswestinghouse-signs-contract-with-ukraine-for-first-ap1000-9277721. Archived from the original on 2023-05-29.
{{cite web}}: Missing or empty|title=(help) - ↑ https://web.archive.org/web/20220811095606/https://en.wikipedia.org/wiki/AP1000. Archived from the original on 2022-08-11.
{{cite web}}: Missing or empty|title=(help) - ↑ 8.0 8.1 8.2 8.3 8.4 https://web.archive.org/web/20240125091319/https://datasets.wri.org/dataset/globalpowerplantdatabase. Archived from the original on 2024-01-25.
{{cite web}}: Missing or empty|title=(help)