ST LNG FLNG Terminal
| Part of the Global Gas Infrastructure Tracker, a Global Energy Monitor project. |
ST LNG FLNG Terminal, also known as ST LNG Deepwater Port Development Project, is a proposed LNG export terminal in United States.
Location
Table 1: Location details
| Name | Location | Coordinates (WGS 84) |
|---|---|---|
| ST LNG FLNG Terminal | United States[1] | 28.40171590938048, -95.82841712550056 (approximate) |
The map below shows the approximate location of the terminal:
Project Details
Table 2: Infrastructure details
| Name | Facility type | Status | Capacity | Total terminal capacity | Offshore | Associated infrastructure |
|---|---|---|---|---|---|---|
| ST LNG FLNG Terminal | export[1] | proposed[1] | 8.4 mtpa[1] | 8.4 mtpa | True | – |
Table 3: Cost
| Name | Facility type | Cost | Total known terminal costs |
|---|---|---|---|
| ST LNG FLNG Terminal | export[1] | – | – |
Financing
No financing data available.
Table 4: Project timeline
| Name | Facility type | Status | Proposal year | FID year | Construction year | Operating year | Inactive year |
|---|---|---|---|---|---|---|---|
| ST LNG FLNG Terminal | export[1] | proposed[1] | 2025[1] | – | – | – | – |
Ownership
Table 5: Ownership
| Name | Facility type | Status | Owners | Parent companies | Operator |
|---|---|---|---|---|---|
| ST LNG FLNG Terminal | export[1] | proposed[1] | ST LNG LLC [100%][1] | Tak Investments Inc [100.0%] | – |
Background
In June 2025, ST LNG filed an application with the United States Maritime Administration (MARAD) for the development of the ST LNG Deepwater Port Development Project, an LNG export terminal with fixed and floating components. The terminal is planned to have four 2.1 mtpa liquefaction systems totaling 8.4 mtpa in export capacity, and to be developed in four phases each adding a 2.1-mtpa liquefaction system. The project would be sited about 10.4 nautical miles offshore Matagorda, Texas.[2]
In May 2026, ST LNG was granted approval by the U.S. Department of Energy to export LNG to free trade agreement (FTA) countries, after submitting requests for FTA and non-FTA approval in December 2025. As of this time, the expected start year for the first phase of the project was 2029. The second, third, and fourth phases could start in March 2031, September 2032, and March 2034 respectively.[3]
Articles and Resources
Additional data
To access additional data, including an interactive map of LNG terminals, a downloadable dataset, and summary data, please visit the Global Gas Infrastructure Tracker on the Global Energy Monitor website.
References
- ↑ 1.00 1.01 1.02 1.03 1.04 1.05 1.06 1.07 1.08 1.09 1.10 https://maritime-executive.com/article/marad-receives-proposal-for-floating-offshore-lng-export-terminal-off-texas?utm_source=substack&utm_medium=email.
{{cite web}}: Missing or empty|title=(help) - ↑ "MARAD Receives Proposal for Floating Offshore LNG Export Terminal off Texas". maritime-executive.com. Retrieved 2025-10-08.
- ↑ "ST LNG gets FTA approval from DOE - LNG Prime". lngprime.com. Retrieved 2026-05-26.