Sakaide LNG Terminal

From Global Energy Monitor
Part of the
Global Gas Infrastructure Tracker,
a Global Energy Monitor project.
Download full dataset
Report an error

Sakaide LNG Terminal is an operating LNG import terminal in Japan.

Location

Table 1: Location details

Name Location Coordinates (WGS 84)
Sakaide LNG Terminal Sakaide, Kagawa, Shikoku, Japan 34.3568348, 133.8367306 (exact)

The map below shows the exact location of the terminal:

Loading map...

Project Details

Table 2: Infrastructure details

mtpa = million tonnes per year
Name Facility type Status Capacity Total terminal capacity Offshore Associated infrastructure
Sakaide LNG Terminal import operating 1.2 mtpa 1.2 mtpa False –

Table 3: Cost

Name Facility type Cost Total known terminal costs
Sakaide LNG Terminal import – –

Financing

No financing data available.

Table 4: Project timeline

FID = Final Investment Decision, used by some developers to indicate a project will move forward
Name Facility type Status Proposal year FID year Construction year Operating year Inactive year
Sakaide LNG Terminal import operating – – – 2010 –

Ownership

Table 5: Ownership

Name Facility type Status Owners Parent companies Operator
Sakaide LNG Terminal import operating Sakaide LNG [100%] Sakaide LNG [100.0%] –

Background

Sakaide LNG Terminal is an LNG terminal in Shikoku, Japan.[1]

Sakaide LNG Terminal began operation in 2010 with LNG storage capacity of 180,000 m3.[2] The facility has received cargo from Malaysia.[3]

In August 2025, Sakaide LNG announced an additional LNG tank with a capacity of 180,000 kiloliters and vaporization unit with a gas flow rate of 50 tons/hour. They are set to begin operations in 2031 and 2029, respectively.[4]

Articles and Resources

Additional data

To access additional data, including an interactive map of LNG terminals, a downloadable dataset, and summary data, please visit the Global Gas Infrastructure Tracker on the Global Energy Monitor website.

References

  1. ↑ Sakaide LNG Terminal, A Barrel Full, accessed April 2017
  2. ↑ LNG Terminal Delivered to Sakaide LNG, Kawasaki, March 25, 2010
  3. ↑ Sakaide LNG terminal in W Japan to receive cargo from Malaysia Saturday, RIM Intelligence Co, January 1, 2012
  4. ↑ "Shikoku Electric Power Company to expand tank capacity at Sakaide LNG terminal; submits environmental impact assessment methodology for Unit 5 (Kagawa Prefecture)". KSB 5ch. August 27, 2025. Retrieved June 1, 2026.