Satna Cement Plant power station is a shelved power station in Bela, Satna, Madhya Pradesh, India.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Satna Cement Plant power station Bela, Satna, Madhya Pradesh, India 24.594239, 80.857937 (exact)[1]
Loading map...

Unit-level coordinates (WGS 84):

  • Unit 2: 24.594239, 80.857937

Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology
Unit 2 Shelved[2] coal: unknown[1] 35[3] unknown

Table 3: Unit-level ownership and operator details

Unit name Owner Parent
Unit 2 Birla Corporation Ltd [100%][1] Birla Corporation Ltd [100.0%]

Project-level coal details

  • Permit(s): Environmental Clearance; Environmental Clearance Extension: 2021-06-03[1]

Ownership Tree

This ownership tree is part of the Global Energy Ownership Tracker, a project of Global Energy Monitor.

Background

The Satna Cement Plant power station originally received Environmental Clearance for a 35 MW captive power station in August 2013.[4][5] In May 2020, the plant owner, Birla Corporation, applied for an extension of validity of the project's Environmental Clearance (EC) and was granted a three-year EC extension on June 3, 2021.[6][7]

In November 2021, an EC compliance report filed by Birla noted that their proposed 35 MW power plant had not yet been established.[8]

Other reports in 2021 and 2023 indicated that the Satna Cement Plant included a captive 27 MW thermal power unit, which appeared to refer to a separate, pre-existing unit.[9][10]

As of June 2025, there no apparent updates on the proposed 35 MW unit.

Articles and Resources

References

  1. 1.0 1.1 1.2 1.3 https://web.archive.org/web/20240125144918/https://environmentclearance.nic.in/OnlinesearchModi_state_new.aspx?pid=/8uWi+EP6l4uG6S7yU4+s4Yy8tn5bHcAKH461mkWRDIbEnJTdjj8Yrpy2iWNA+Cs&EAC=wi3XQJNIsxdTXPNia9uMI+d9i3GLupWexWwqaKTfh/I=&type=q5weavCpROBMFZHgndEFyg==&status=BOII5FUynjpl5RZJJ8nW1g==&statename=Madhya%20Pradesh. Archived from the original on 2024-01-25. {{cite web}}: Missing or empty |title= (help)
  2. https://web.archive.org/web/20240125144936/https://environmentclearance.nic.in/TimeLinemodiB.aspx?pid=SIA/MP/THE/55032/2009&type=EC&ID=28711. Archived from the original on 2024-01-25. {{cite web}}: Missing or empty |title= (help)
  3. https://web.archive.org/web/20240125144819/https://environmentclearance.nic.in/state/Reports_State.aspx?pid=7BriPFNbSsnhgiEv7HDYap/GhePfaibJ2roGhk8u8wuNyUXDgD8Q2CnSyCEkZxNv&idd=BDr52qjnbmsGfYRCPXmCwQ==&forms=4B1QmJBAsAaLln5kYbI+JA==&sw_pid=COEtAnXNsi3YjkNFJZ34L0Itp7YCpnB6INNUhYQVfWg%3D. Archived from the original on 2024-01-25. {{cite web}}: Missing or empty |title= (help)
  4. Application for Extension of Validity of Environmental Clearance, Parivesh, Accessed: December 6, 2023
  5. Prior Environmental Clearance for Captive Thermal Power Plant, State level Environmental Impact Assessment Authority - Madhya Pradesh, August 5, 2013
  6. Timeline Details: Proposal No.: SIA/MP/THE/55032/2009, Parivesh - State level Environmental Impact Assessment Authority - Madhya Pradesh, Accessed: December 6, 2023
  7. “Extension of Validity Period of Environmental Clearance,” State Environment Impact Assessment Authority, June 3, 2021
  8. “EC Six Monthly Compliance Report - Proposed Captive 35 MW TPP,” Birla Corporation Ltd., November 22, 2021
  9. Confluence of growth, efficiency & frugality in the current cycle, Indian Cement Industry, September 1, 2021
  10. Case Study C&I RE Sector, MP Birla Group and InSolare, August 2023

Additional data

To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.