Shaanxi Jingyi Chemical Company captive power station (榆林能源陕西精益化工有限公司自备电厂) is an operating power station of at least 100-megawatts (MW) in Jinjie, Shenmu, Yulin, Shaanxi, China with multiple units, some of which are not currently operating.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Shaanxi Jingyi Chemical Company captive power station Jinjie, Shenmu, Yulin, Shaanxi, China 38.721485, 110.192604 (exact)

The map below shows the exact location of the power station.

Loading map...


Unit-level coordinates (WGS 84):

  • Unit 1, Unit 2, Unit 3, Unit 4: 38.721485, 110.192604

Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology Start year Retired year
Unit 1 operating coal - unknown 50 unknown 2019
Unit 2 operating coal - unknown 50 unknown 2020
Unit 3 shelved coal - unknown 60 unknown
Unit 4 shelved coal - unknown 60 unknown

Table 3: Unit-level ownership and operator details

Unit name Owner
Unit 1 Shaanxi Jingyi Chemical Co Ltd [100.0%]
Unit 2 Shaanxi Jingyi Chemical Co Ltd [100.0%]
Unit 3 Shaanxi Jingyi Chemical Co Ltd [100.0%]
Unit 4 Shaanxi Jingyi Chemical Co Ltd [100.0%]

Project-level captive use details

  • Captive industry use (heat or power): chemicals
  • Captive industry: Both

Background

Shaanxi Jingyi Chemical Company captive power station is a 2 x 50 MW coal plant in Shaanxi Province, commissioned in 2019–2020.[1][2] An additional 2 x 60 MW was proposed. The plant is owned by Shaanxi Jingyi Chemical Company.[3]

With no news on the expansion in recent years, the expansion was presumed shelved as of January 2023.

Articles and Resources

References

  1. "中国能建陕西精益化工项目1号机组并网成功-北极星火力发电网". news.bjx.com.cn (in 中文(中国大陆)). 2019-11-11.{{cite web}}: CS1 maint: url-status (link)
  2. "陕西精益化工有限公司 陕西恒源投资集团有限公司官网". www.smhygroup.com (in 中文). Retrieved 2022-11-29.{{cite web}}: CS1 maint: url-status (link)
  3. "西北电建陕西精益化工项目机组试运成功," 中国电力新闻网, 2020.01.19

Additional data

To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.