Shaoguan Wastecoal power station
| Part of the Global Coal Plant Tracker, a Global Energy Monitor project. |
| Related coal trackers: |
Shaoguan Wastecoal power station (国粤韶关综合利用发电厂) is an operating power station of at least 1400-megawatts (MW) in Lishi Town, Zhenjiang District, Shaoguan, Guangdong, China. It is also known as 韶关浈江煤矸石综合利用发电二期项目 (Unit 3), 国粤华银韶关热电综合利用有限公司700兆瓦超超临界循环流化床机组 (Unit 3), 广东粤华投资集团韶关电厂 (Unit 1 & 2).
Location
Table 1: Project-level location details
| Plant name | Location | Coordinates (WGS 84) |
|---|---|---|
| Shaoguan Wastecoal power station | Lishi Town, Zhenjiang District, Shaoguan, Guangdong, China | 24.945064, 113.548835 (exact)[1] |
Unit-level coordinates (WGS 84):
- Phase II Unit 3, Unit 1, Unit 2: 24.945064, 113.548835
Project Details
Table 2: Unit-level details
| Unit name | Status | Fuel(s) | Capacity (MW) | Technology | CHP | Start year | Emergency/Backup |
|---|---|---|---|---|---|---|---|
| Phase II Unit 3 | Operating[2] | coal: waste coal[1][3] | 700[1] | ultra-supercritical[1] | yes[1] | 2025[2] | False |
| Unit 1 | Operating | coal: waste coal[3] | 350 | subcritical | yes | 2017 | False |
| Unit 2 | Operating | coal: waste coal[3] | 350 | subcritical | yes | 2017 | False |
Table 3: Unit-level ownership and operator details
| Unit name | Owner | Parent |
|---|---|---|
| Phase II Unit 3 | Guoyue Huayin (Shaoguan) Thermal Power Comprehensive Utilization Co Ltd [100%] | Guoyue Investment Group Co Ltd [100.0%] |
| Unit 1 | Guoyue Huayin (Shaoguan) Thermal Power Comprehensive Utilization Co Ltd [100%] | Guoyue Investment Group Co Ltd [100.0%] |
| Unit 2 | Guoyue Huayin (Shaoguan) Thermal Power Comprehensive Utilization Co Ltd [100%] | Guoyue Investment Group Co Ltd [100.0%] |
Project-level coal details
- Coal source(s): domestic
Ownership Tree
This ownership tree is part of the Global Energy Ownership Tracker, a project of Global Energy Monitor.
Background
Shaoguan Wastecoal power station is a 2 x 350 MW subcritical coal plant in Lishi Town.[4][5]
It was permitted for construction in 2015.[6]
Unit 1 was commissioned in 2017.[7] Unit 2 was commissioned in November 2017.[8]
Expansion
In November 2020, plans were announced for a new 700 MW coal-fired unit at the power station. Construction was reportedly planned to begin immediately, with commissioning targeted for 2022.[9]
On August 29, 2022, the new unit was permitted.[10][11]
In September 2022, a preliminary construction ceremony was held.[12]
In November 2022, another ceremony for construction was held,[13] although it was unclear whether construction was truly underway.
Construction for Unit 3 continued in 2023 and 2024, with milestones including the first concrete pour and boiler steel hoisting.[14][15]
In 2024, the generator stator and rotor were installed.[16][17]
Phase II Unit 3 achieved grid connection in May 2025 and passed its 168-hour trial run in July 2025.[18][19]
Articles and Resources
References
- ↑ 1.0 1.1 1.2 1.3 1.4 "全国首台700MW超超临界CFB扩建项目锅炉钢架开始吊装". Weixin Official Accounts Platform. 2023-11-06. Archived from the original on 2024-01-25. Retrieved 2023-11-10.
- ↑ 2.0 2.1 https://mp.weixin.qq.com/s/dKUBAdTXVjoohTT3-Rk7nA.
{{cite web}}: Missing or empty|title=(help) - ↑ 3.0 3.1 3.2 https://www.gem.wiki/Coal_source_methodology_for_the_Global_Coal_Plant_Tracker.
{{cite web}}: Missing or empty|title=(help) - ↑ "国粤集团项目介绍," BJX Job, accessed Dec 2017
- ↑ "韶关粤华电力综合利用发电新建项目," Guangdong Guoyue Group, 2014-7-1
- ↑ "关于广东国粤韶关综合利用发电新建项目环境影响报告书的批复," China MEP, 2015年01月20日
- ↑ "国粤韶关综合利用发电新建项目1号机组首次并网发电一次成功," 中国电力化工网, 2017-06-20
- ↑ "国粤韶关综合利用发电新建项目2号机组顺利通过168小时满负荷," Sohu, Nov 13, 2017
- ↑ "700MW!广东国粤韶关综合利用发电(扩建)项目计划年底开工 - 北极星火力发电网". news.bjx.com.cn. 2020-11-30. Retrieved 2021-01-05.
{{cite web}}: CS1 maint: url-status (link) - ↑ 世界首台700MW超超临界循环流化床锅炉方案过审, BJX News, 2022-10-14
- ↑ 广东省发展改革委关于广东国粤韶关综合利用发电扩建项目核准的批复, Guangdong Provincial Development and Reform Commission, 2022-08-29
- ↑ 国家级发电示范项目在广东韶关正式动工,总投资30亿!, Seetao, 2022-09-05
- ↑ 全国首台700MW CFB扩建项目开工建设, BJX News, 2022-11-24
- ↑ "广东国粤韶关综合利用发电扩建项目第一罐混凝土浇筑仪式". Guoyue Group. 2023-08-25. Retrieved 2026-05-30.
{{cite web}}: CS1 maint: url-status (link) - ↑ "国粤韶关综合利用发电扩建项目锅炉钢架第一钩顺利吊装完成". BeiJiXing (BJX) News. 2023-11-06. Retrieved 2026-05-30.
{{cite web}}: CS1 maint: url-status (link) - ↑ "广东国粤韶关综合利用发电扩建项目发电机定子顺利吊装就位". WeChat. 2024-08-26. Retrieved 2026-05-30.
{{cite web}}: CS1 maint: url-status (link) - ↑ "广东国粤韶关综合利用发电扩建项目发电机转子成功完成穿装". WeChat. 2024-11-25. Retrieved 2026-05-30.
{{cite web}}: CS1 maint: url-status (link) - ↑ "广东国粤韶关综合利用发电扩建项目1×700MW超超临界循环流化床机组首次并网一次成功". BeiJiXing (BJX) News. 2025-05-30. Retrieved 2026-05-30.
{{cite web}}: CS1 maint: url-status (link) - ↑ "广东国粤韶关综合利用发电扩建项目700兆瓦循环流化床机组一次顺利通过168小时试运行". WeChat. 2025-07-01. Retrieved 2026-05-30.
{{cite web}}: CS1 maint: url-status (link)
Additional data
To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.