Shenzhen Energy East power station
| Part of the Global Oil and Gas Plant Tracker, a Global Energy Monitor project. |
| Related categories: |
Shenzhen Energy East power station (深圳能源东部电厂) is an operating power station of at least 2390-megawatts (MW) in Shenzhen, Dapeng New District, Guangdong, China with multiple units, some of which are not currently operating.
Location
Table 1: Project-level location details
| Plant name | Location | Coordinates (WGS 84) |
|---|---|---|
| Shenzhen Energy East power station | Shenzhen, Dapeng New District, Shenzhen, Guangdong, China | 22.575253, 114.442407 (exact)[1][2] |
Unit-level coordinates (WGS 84):
- 1-1, 1-2, 1-3, 2-1, 2-2, 3-1, 3-2, 3-3: 22.575253, 114.442407
Project Details
Table 2: Unit-level details
| Unit name | Status | Fuel(s) | Capacity (MW) | Technology | CHP | Start year | Equipment | Emergency/Backup |
|---|---|---|---|---|---|---|---|---|
| 1-1 | Operating[1] | fossil gas: LNG[1] | 350[1] | combined cycle[1] | not found | 2007[1] | Shanghai Electric: M701F, Mitsubishi Heavy Industries: M701F[3] | no |
| 1-2 | Operating[1] | fossil gas: LNG[1] | 350[1] | combined cycle[1] | not found | 2007[1] | Shanghai Electric: M701F, Mitsubishi Heavy Industries: M701F[3] | no |
| 1-3 | Operating[1] | fossil gas: LNG[1] | 350[1] | combined cycle[1] | not found | 2007[1] | Mitsubishi Heavy Industries: M701F, Shanghai Electric: M701F[3] | no |
| 2-1 | Operating[4] | fossil gas: LNG[5][2] | 670[4] | combined cycle[6][7] | not found | 2024[4] | Siemens Energy: SST5-5000[6] | no |
| 2-2 | Operating[8] | fossil gas: LNG[5][2] | 670[4] | combined cycle[6][7] | not found | 2024[8] | Siemens Energy: SST5-5000[6] | no |
| 3-1 | Announced[9][10][11] | fossil gas: LNG[1][12] | 870[9][11] | combined cycle[10] | not found | – | not found | no |
| 3-2 | Announced[9][11] | fossil gas: LNG[1][12] | 870[11] | combined cycle[10] | not found | – | not found | no |
| 3-3 | Announced[10][11] | fossil gas: LNG[1][12] | 870[10][11] | combined cycle[10] | not found | – | not found | no |
CHP is an abbreviation for Combined Heat and Power. It is a technology that produces electricity and thermal energy at high efficiencies. Coal units track this information in the Captive Use section when known.
Table 3: Unit-level ownership and operator details
| Unit name | Owner | Parent |
|---|---|---|
| 1-1 | Shenzhen Energy Group Co Ltd [100%][5][13] | Shenzhen Energy Group Co Ltd [100.0%] |
| 1-2 | Shenzhen Energy Group Co Ltd [100%][5][13] | Shenzhen Energy Group Co Ltd [100.0%] |
| 1-3 | Shenzhen Energy Group Co Ltd [100%][5][13] | Shenzhen Energy Group Co Ltd [100.0%] |
| 2-1 | Shenzhen Energy Group Co Ltd [100%][5][13] | Shenzhen Energy Group Co Ltd [100.0%] |
| 2-2 | Shenzhen Energy Group Co Ltd [100%][5][13] | Shenzhen Energy Group Co Ltd [100.0%] |
| 3-1 | Shenzhen Energy Group Co Ltd [100%][5][13] | Shenzhen Energy Group Co Ltd [100.0%] |
| 3-2 | Shenzhen Energy Group Co Ltd [100%][5][13] | Shenzhen Energy Group Co Ltd [100.0%] |
| 3-3 | Shenzhen Energy Group Co Ltd [100%][5][13] | Shenzhen Energy Group Co Ltd [100.0%] |
Ownership Tree
This ownership tree is part of the Global Energy Ownership Tracker, a project of Global Energy Monitor.
Background
Shenzhen Energy East power station (深圳能源东部电厂) uses clean liquefied natural gas (LNG) as its fuel, with a planned total capacity of 9 F-class gas steam combined cycle power units, constructed in three phases. [14]
The first phase project ( Unit1-1, Unit 1-2 and Unit 1-3), with an installed capacity of three 350MW-class gas steam combined cycle power units, was completed and put into operation in 2007.[14]
The second-phase project (Unit 2-1 and Unit 2-2) obtained approval from the Shenzhen Municipal Development and Reform Commission on January 25, 2022.[15] It officially commenced construction in October 2022, with a plan to start operation in 2024.[16]
Articles and Resources
References
- ↑ 1.00 1.01 1.02 1.03 1.04 1.05 1.06 1.07 1.08 1.09 1.10 1.11 1.12 1.13 1.14 1.15 1.16 1.17 1.18 https://web.archive.org/web/20221204105409/https://www.sec.com.cn/queryMemberById.do?id=88. Archived from the original on 2022-12-04.
{{cite web}}: Missing or empty|title=(help) - ↑ 2.0 2.1 2.2 https://data.eastmoney.com/notices/detail/000027/AN202204211560707995.html.
{{cite web}}: Missing or empty|title=(help) - ↑ 3.0 3.1 3.2 https://www.szygcgpt.com/ygcg/detailTop?com=Purchase&guid=280442_b7df1f56-dbba-4f90-bc28-43529ff78a3d&ggGuid=e31f5211-2b10-4422-aa80-be3651b13a86&bdGuid=75342c2c-98fe-4441-863a-280daa865a0e&ggLeiXing=1&dataSource=0&type=purchase.
{{cite web}}: Missing or empty|title=(help) - ↑ 4.0 4.1 4.2 4.3 "2×670MW!深圳能源东部电厂二期工程首台机组正式投产-北极星电力新闻网". m.bjx.com.cn. 2024-07-01. Archived from the original on 2025-06-30. Retrieved 2024-11-04.
- ↑ 5.00 5.01 5.02 5.03 5.04 5.05 5.06 5.07 5.08 5.09 (PDF) https://web.archive.org/web/20210614210919/http://gdee.gd.gov.cn/protect/P0201604/P020160407/P020160407426474726546.pdf. Archived from the original (PDF) on 2021-06-14.
{{cite web}}: Missing or empty|title=(help) - ↑ 6.0 6.1 6.2 6.3 "2×700MW!深圳能源东部电厂二期项目迎来重要节点". 2024-01-25. Archived from the original on 2024-05-09. Retrieved 2024-05-05.
- ↑ 7.0 7.1 http://www.dpxq.gov.cn/xxgk/xxgk/bmdt/content/post_10163932.html.
{{cite web}}: Missing or empty|title=(help) - ↑ 8.0 8.1 "深圳能源集团东部电厂二期工程"双投"_电力网". mm.chinapower.com.cn. 2024-10-28. Archived from the original on 2025-06-30. Retrieved 2024-11-04.
- ↑ 9.0 9.1 9.2 https://isp.sec.com.cn/source_detail?sourceId=S5%2FB2DYScZrZxFxWT4exMw%3D%3D.
{{cite web}}: Missing or empty|title=(help) - ↑ 10.0 10.1 10.2 10.3 10.4 10.5 https://www.sohu.com/a/665118497_683016.
{{cite web}}: Missing or empty|title=(help) - ↑ 11.0 11.1 11.2 11.3 11.4 11.5 "深圳东部电厂消泡剂采购(二次) 招 标 公 告". 2025-07-24. Archived from the original on 2025-12-05. Retrieved 2025-12-01.
- ↑ 12.0 12.1 12.2 https://web.archive.org/web/20210927191516/https://www.csust.edu.cn/ndxy/info/1117/2517.htm. Archived from the original on 2021-09-27.
{{cite web}}: Missing or empty|title=(help) - ↑ 13.0 13.1 13.2 13.3 13.4 13.5 13.6 13.7 https://web.archive.org/web/20220127205747/https://news.bjx.com.cn/html/20180423/893562.shtml. Archived from the original on 2022-01-27.
{{cite web}}: Missing or empty|title=(help) - ↑ 14.0 14.1 "深圳能源". Retrieved 2023-11-02.
{{cite web}}: CS1 maint: url-status (link) - ↑ "深圳能源:关于投资建设深圳东部电厂二期工程项目的公告". 2022-04-22. Retrieved 2023-11-02.
{{cite web}}: CS1 maint: url-status (link) - ↑ "深圳能源东部电厂二期主体工程项目正式开工". 2022-10-11. Retrieved 2023-11-02.