Shuicheng Dongdi power station (贵州能源水城2×66万千瓦燃煤发电项目) is a power station in Shuicheng, Liupanshui, Guizhou, China with multiple units of varying statuses none of which are currently operating. It is also known as 水城经济开发区董地发电项目.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Shuicheng Dongdi power station Shuicheng, Liupanshui, Guizhou, China 26.481944, 105.095233 (approximate)

The map below shows the approximate location of the power station.

Loading map...


Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology Start year Retired year
Phase I Unit 1 permitted coal - unknown 660 ultra-supercritical 2025
Phase II Unit 2 pre-permit coal - unknown 660 ultra-supercritical

Table 3: Unit-level ownership and operator details

Unit name Owner
Phase I Unit 1 Guizhou Shuicheng Energy Investment Power Generation Co Ltd [100.0%]
Phase II Unit 2 Guizhou Shuicheng Energy Investment Power Generation Co Ltd [100.0%]

Project-level coal details

  • Permit(s): January 20, 2023 – 本次获批的是一期工程(首台机组核准批复),总投资34.1093亿元。[1]

Background

In September 2021, a "cooperation protocol" was reportedly signed for a 1,000 MW project.[2] The project was also listed as a 1 x 1,000 MW capacity project in the provincial major construction plan for 2022.[3][4]

In May 2022 and August 2022, a review meeting for a 2 x 660 MW project of the same name (Shuicheng Dongdi power generation project) was held.[5][6]

In January 2023, the first unit of the project was permitted.[7] In the 2023 Guizhou Province Coal Power Projects Three-Year Action Plan (2023-2025), only the first unit of the project was listed, with an estimated COD of 2025.[8]

In July 2023, a Feasibility Study review took place for both units of the proposed power station.[9][10] Thus, Unit 2 of the project was considered to be in pre-permit development.

In December 2023, the Environmental Impact Assessment for both units was approved.[11]

Articles and Resources

References

  1. https://web.archive.org/web/20240125125237/https://news.bjx.com.cn/html/20230207/1286878.shtml. Archived from the original on 25 January 2024. {{cite web}}: Missing or empty |title= (help)
  2. 何枢率队到四川省成都市考察招商, shuicheng.gov, 2021-09-28
  3. 贵州六盘水市:推动水电和风光等新能源参与市场化交易 探索可再生能源消纳指标、电力绿证交易, BJX, 2021-12-14
  4. 2022年贵州省重大工程和重点项目名单, guizhou.gov, 2022-02-15
  5. "董地2×660MW超超临界发电项⽬社会稳定⻛险评估公众参与公示," Shuicheng, 2022-08-24
  6. "董地2X660MW超超临界发电项⽬可⾏性研究报告审查会议顺利召开," Shuicheng, 2022-05-25
  7. [https://news.bjx.com.cn/html/20230207/1286878.shtml "贵州2×660MW燃煤发电机组核准批复,"] BJX, 2023-02-07
  8. "省能源局关于公开征求《贵州省煤电项目建设三年攻坚行动方案(2023-2025年)》意见的函," Guizhou Energy Administration, June 2, 2023
  9. "贵州能源水城2×66万千瓦燃煤发电项目可研报告评审会召开," BJX, 2023-07-17
  10. "【项目】火电|2×1000MW!中电建河南公司喜中华润海丰二期4号机安装工程/2×660MW!贵州能源水城项目可研评审会顺利召开," MP Weixin, 2023-07-19
  11. "贵州能源水城2×66万千瓦燃煤发电项目环评审批公示," news.bjx.com, December 27, 2023