Shuijiang Zutuan power station (南川工业园区水江组团热电联产) is an operating power station of at least 350-megawatts (MW) in Shuijiang Town Dayan Villege, Nanchuan, Chongqing, China with multiple units, some of which are not currently operating.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Shuijiang Zutuan power station Shuijiang Town Dayan Villege, Nanchuan, Chongqing, China 29.271511, 107.270846 (exact)

The map below shows the exact location of the power station.

Loading map...


Unit-level coordinates (WGS 84):

  • Unit 1: 29.271511, 107.270846
  • Unit 2, Unit 3, Unit 4: 29.266987, 107.266656

Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology Start year Retired year
Unit 1 operating coal - unknown 350 supercritical 2019
Unit 2 cancelled coal - unknown 50 supercritical
Unit 3 cancelled coal - unknown 50 supercritical
Unit 4 cancelled coal - unknown 50 supercritical

Table 3: Unit-level ownership and operator details

Unit name Owner
Unit 1 Chongqing Zhongfulan Thermal Power Co Ltd [100.0%]
Unit 2 Chongqing Zhongfulan Thermal Power Co Ltd [100.0%]
Unit 3 Chongqing Zhongfulan Thermal Power Co Ltd [100.0%]
Unit 4 Chongqing Zhongfulan Thermal Power Co Ltd [100.0%]

Project-level captive use details

  • Captive industry use (heat or power): aluminum

Project-level coal details

  • Permit(s): June 1, 2016

Background on Project

Chongqing Zhongfunan Cogen Power Co., Ltd. has proposed to construct a 300 MW supercritical coal plant with three 50 MW back-pressured units in Dayan Village, Shuijiang Town. It is a CHP power plant that will supply electricity to an aluminum-production-theme industrial park and surrounding factories which is typical for CHP.[1]

China Yangtze Power Co.,Ltd., a listed subsidiary of China Three Gorges Corporation owns 50% equity of this power plant through an equity investment fund. [2]

The plant was permitted in June 2016, and construction on unit 1 began in October 2016.[3] Unit 1 is planned for operation in May 2019,[4] and was commissioned in October 2019.[5]

As of April 2021 there are no further activities on the three 50 MW back-up units. They are presumedly abandoned.

Articles and Resources

References

  1. "重庆市环保局拟批准建设项目环评信息公示表," EC 1888, Apr 7, 2016
  2. "重庆涪陵三峡长涪股权投资基金合伙企业(有限合伙) - 企查查". www.qcc.com. Retrieved 2021-04-26.{{cite web}}: CS1 maint: url-status (link)
  3. "【一公司】重庆南川水江热电联产项目正式动工," PowerChina, 10-24-2016
  4. "工业园区水江组团中涪南热电联产项目举行锅炉钢架吊装仪式," cqnc.gov.cn, 2017年08月23日
  5. "中涪南热电联产项目试生产," 2019-10-30

Additional data

To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.