Strait West Natural Gas Pipeline Network Phase II

From Global Energy Monitor
This article is part of the Global Fossil Infrastructure Tracker, a project of Global Energy Monitor.
Sub-articles:

Strait West Natural Gas Pipeline Network Phase II 海西天然气管网二期工程, also translated as Haixi Natural Gas Pipeline Network Phase II, is a pipeline network with segments that are operating and in construction in Fujian Province, China. It is located along the western bank of the Taiwan Strait, and inherits its name west strait from this geographical location.

Location

Loading map...

Background

The Strait West Natural Gas Pipeline Network Phase II is described as an important natural gas interconnection project in Fujian Province.[1] It was originally estimated to have a total length of 830 kilometers and a total investment of over 10 billion RMB. The approval process took two years and three months.[2]

  • Construction for the Zhangzhou–Zhao'an Gas Pipeline segment began in 2013.[3] The pipeline was divided into two sections for approval, from Zhangzhou to Zhangpu and from Zhangpu to Zhao'an, and the full pipeline was reportedly finished with construction and operational at the beginning of 2020.[1]
  • Construction on the Fuzhou–Sanming Gas Pipeline began on June 28, 2021.
  • The Fuzhou–Fuding Gas Pipeline segment began operating in December, 2020.
  • Construction on the Quanzhou–Dehua Branch segment began on May 28, 2021 with an investment of 1.34 billion RMB.

Zhangzhou–Zhao'an Gas Pipeline 漳州—诏安段

Loading map...
  • Owner: PipeChina[4]
  • Capacity:
  • Length: 128 kilometers[1]
  • Diameter:
  • Status: Operating
  • Start year: 2020
  • Cost: 1.8 billion RMB[1]

Zhangzhou–Longyan Gas Pipeline 漳州—龙岩段

Loading map...
  • Owner: PipeChina[4]
  • Capacity:
  • Length: 103 kilometers[3][5]
  • Diameter:
  • Status: construction[6]
  • Start year:

Fuzhou–Sanming Gas Pipeline 福州—三明段

Loading map...
  • Owner: PipeChina[4]
  • Capacity:
  • Length: 286.6 kilometers[4]
  • Diameter: 813 millimeters[4]
  • Status: Construction[4]
  • Start year: 2022[4]
Fuzhou-Fuding Gas Pipeline.png

Fuzhou–Fuding Gas Pipeline 福州—福鼎段

Loading map...
  • Owner: PipeChina[4]
  • Capacity:
  • Length: 256.8 kilometers[7]
  • Diameter:
  • Status: Operating[7]
  • Start year: 2020[7]

Quanzhou–Dehua Branch 德化支线 (泉州—德化)

Loading map...
  • Owner: PipeChina[4]
  • Capacity:
  • Length: 124 kilometers[8][9]
  • Diameter:
  • Status: Construction[8]
  • Start year: 2021[8]
  • Cost: 1.34 billion RMB[8]

Zhangzhou LNG Connecting Gas Pipeline 漳州LNG联络线

Loading map...
  • Owner: 国家管网集团福建省管网有限公司[10]
  • Capacity: 4.2 billion cubic meters per year[11]
  • Length: 77.8 kilometers[11]
  • Diameter: 1016mm[11]
  • Status: Construction[11]
  • Start year: 2021[11]
  • Cost:

Articles and resources

References

  1. 1.0 1.1 1.2 1.3 漳浦: 海西天然气管网二期工程漳州至诏安段项目顺利完工, k.sina.com.cn, Jan. 8, 2020, accessed Aug. 30, 2021.
  2. 福建海西天然气管网二期工程全部获得核准, SASAC, Jun. 26, 2013, accessed Aug. 30, 2021.
  3. 3.0 3.1 海西天然气管网二期工程在漳全线铺开, fjsztb.com, Sep. 2, 2013, accessed Aug. 30, 2021.
  4. 4.0 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 海西天然气管网二期工程 (福州—三明段) 全面开工, PipeChina, Jun. 29, 2021, accessed Aug. 30, 2021.
  5. "漳州发改部门服务海西天然气二期管网建设小记 - 民生 - 东南网漳州频道". zzpd.fjsen.com. 2014-02-06. Retrieved 2021-09-17.
  6. "漳州LNG接收站遭遇管网瓶颈,怎么破--腾讯内容开放平台". page.om.qq.com. 2019-09-04. Retrieved 2021-09-17.
  7. 7.0 7.1 7.2 福建省这两个天然气基础设施重点工程按期建成, in-en.com, Nov. 2, 2020, accessed Aug. 30, 2021.
  8. 8.0 8.1 8.2 8.3 海西天然气管网德化支线工程德化段开工, DehuaJun. 1, 2020, accessed Aug. 30, 2021.
  9. 青海海西天然气管网德化支线项目 南安段二期启动征迁, Quanzhou Evening News, Apr. 28, 2020, accessed Aug. 30, 2021.
  10. "福建省水利厅关于福建天然气管网二期工程漳州LNG联络线工程水土保持方案报告书的批复_ 水利行政许可_福建省水利厅". slt.fujian.gov.cn. 2021-07-02. Retrieved 2022-09-16. line feed character in |title= at position 43 (help)
  11. 11.0 11.1 11.2 11.3 11.4 "福建管网二期工程漳州LNG联络线正式启动". finance.sina.com.cn. 2021-11-28. Retrieved 2022-09-16.