Suzhou Qianyingzi power station

From Global Energy Monitor
Part of the
Global Coal Plant Tracker,
a Global Energy Monitor project.
Download full dataset
Report an error
Related coal trackers:

Suzhou Qianyingzi power station (皖能安徽钱营孜发电厂) is an operating power station of at least 700-megawatts (MW) in Taoyuan Town, Yongqiao District, Suzhou, Anhui, China with multiple units, some of which are not currently operating. It is also known as 皖能安徽钱营孜发电厂二期扩建项目 (Unit 3).

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Suzhou Qianyingzi power station Taoyuan Town, Yongqiao District, Suzhou, Anhui, China 33.5107954, 116.9261351 (exact)

The map below shows the exact location of the power station.

Loading map...


Unit-level coordinates (WGS 84):

  • Unit 1, Unit 2, Unit 3: 33.5107954, 116.9261351

Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology Start year Retired year
Unit 1 operating coal - subbituminous 350 subcritical 2018
Unit 2 operating coal - subbituminous 350 subcritical 2018
Unit 3 construction coal - unknown 1000 ultra-supercritical 2024

Table 3: Unit-level ownership and operator details

Unit name Owner
Unit 1 Anhui Qianyingzi Power Generation Co Ltd [100.0%]
Unit 2 Anhui Qianyingzi Power Generation Co Ltd [100.0%]
Unit 3 Anhui Qianyingzi Power Generation Co Ltd [100.0%]

Project-level coal details

  • Permit(s): September 19, 2022, December 2014

Background on Project

In 2016, the two-unit, 700 MW coal plant was under construction and planned for commissioning in 2017. It was sponsored by Wanbei Coal-Electricity Group and Wenergy Group.[1]

Plant postponed by July 2017 suspension

In July 2017, the NEA released the "Guideline of Supply-Side Reform of the Coal Power Bubble". The Guideline included a draft list which slowed down or halted 185 coal-burning units across 21 provinces, totaling 107 GW. 114 coal units (65 GW) are ordered to slow down the construction progress during 2017 to 2020, and are not allowed to connect to the grid in 2017. In addition, 71 coal units (42 GW) were halted indefinitely for regulation violations. The list partly overlapped with the projects listed in the January NEA letter to 13 provinces.[2]

Suzhou Qianyingzi power station Units 1-2 are among the postponed coal-burning units,[2] and also appeared on an updated list of postponements released in September 2017.[3]

For more information, see China's 2016/2017 Restrictions on Development of Coal-Fired Power Capacity.

2018 development

Unit 1 was reported as commissioned in April 2018.[4]

Satellite photographs from July 2017 and March 2018 show that Unit 2 continued construction and appeared to be substantially complete in March 2018.[5]

Unit 2 was commissioned in August 2018.[6]

Expansion

A third unit was permitted on September 19, 2022.[7][8]

The construction ceremony was held on December 28, 2022.[9]

In 2023, the project was on Anhui's key projects list as continuing construction, and a project supervision bid was awarded to Shanghai Electric Power Supervision Consulting Co., Ltd. in March 2023.[10]

In May 2023, concrete pouring reportedly marked the official start of construction.[11] The power station was expected by 2024.

Articles and Resources

References

Additional data

To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.