Tacheng power station
| Part of the Global Coal Plant Tracker, a Global Energy Monitor project. |
| Related coal trackers: |
Tacheng power station (国家电投塔城煤电一体化项目) is a power station under construction in Tiechanggou Town, Toli County, Tacheng Prefecture, Xinjiang, China.
Location
Table 1: Project-level location details
| Plant name | Location | Coordinates (WGS 84) |
|---|---|---|
| Tacheng power station | Tiechanggou Town, Toli County, Tacheng Prefecture, Xinjiang, China | 46.173817, 84.434753 (approximate)[1] |
Project Details
Table 2: Unit-level details
| Unit name | Status | Fuel(s) | Capacity (MW) | Technology | Start year |
|---|---|---|---|---|---|
| Unit 1 | Construction[2] | coal: unknown | 660 | ultra-supercritical | 2026 (planned)[3] |
| Unit 2 | Construction[2] | coal: unknown | 660 | ultra-supercritical | 2026 (planned)[3] |
Table 3: Unit-level ownership and operator details
| Unit name | Owner | Parent |
|---|---|---|
| Unit 1 | Cpi Xinjiang Energy Chemical Group Co Ltd [100%] | State Power Investment Corp Ltd [67.9%]; Xinjiang Investment Development (Group) Co Ltd [32.1%] |
| Unit 2 | Cpi Xinjiang Energy Chemical Group Co Ltd [100%] | State Power Investment Corp Ltd [67.9%]; Xinjiang Investment Development (Group) Co Ltd [32.1%] |
Project-level coal details
- Permit(s): 新发改批复〔2023〕150号[1]
Ownership Tree
This ownership tree is part of the Global Energy Ownership Tracker, a project of Global Energy Monitor.
Background
This proposed 2 × 660 MW ultra-supercritical coal-fired power station called for tender in November 2022.[4]
In December 2022, Tacheng District Development and Reform Commission announced that the first-place winner of the power project's bidding process was State Power Investment Corporation Xinjiang Energy and Chemical Co.[5]
In April 2022, bidding results for feasibility study[6] and social impact assessment were announced.[7]
In September 2023, the power station was permitted.[8]
Articles and Resources
References
- ↑ 1.0 1.1 "国家电投塔城2×66万千瓦煤电一体化项目 获得自治区发展改革委核准批复_经济动态_今日塔城_要闻动态_塔城地区行政公署". www.xjtc.gov.cn. 2023-09-19. Archived from the original on 2024-01-25. Retrieved 2023-11-03.
- ↑ 2.0 2.1 https://news.bjx.com.cn/html/20250826/1457688.shtml.
{{cite web}}: Missing or empty|title=(help) - ↑ 3.0 3.1 "2×660MW煤电一体化项目开工,国家电投的!-北极星火力发电网". news.bjx.com.cn. 2023-10-07. Archived from the original on 2024-01-25. Retrieved 2023-11-03.
- ↑ "塔城2×66万千瓦煤电一体化项目竞争性配置投资主体招标公告". 塔城地区行政公署网站. 2022-11-03. Retrieved 2023-02-06.
- ↑ 塔城2×66万千瓦煤电一体化项目竞争性配置投资主体(二次), People's Government of Tacheng, Dec. 10, 2023
- ↑ "塔城2×66万千瓦煤电一体化项目(火电部分)可行性研究报告编制结果公告". 知了标讯. 2023-04-29. Retrieved 2023-7-27.
{{cite web}}: Check date values in:|access-date=(help)CS1 maint: url-status (link) - ↑ "塔城2×66万千瓦煤电一体化项目(火电部分)社会稳定风险分析和评估报告编制结果公告". 知了标讯. 2023-04-29. Retrieved 2023-7-27.
{{cite web}}: Check date values in:|access-date=(help)CS1 maint: url-status (link) - ↑ 国家电投塔城2×66万千瓦煤电一体化项目 获得自治区发展改革委核准批复, xjtc.gov, September 19, 2023
Additional data
To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.