Tacheng power station

From Global Energy Monitor
Part of the
Global Coal Plant Tracker,
a Global Energy Monitor project.
Download full dataset
Report an error
Related coal trackers:

Tacheng power station (国家电投塔城煤电一体化项目) is a power station under construction in Tiechanggou Town, Toli County, Tacheng Prefecture, Xinjiang, China.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Tacheng power station Tiechanggou Town, Toli County, Tacheng Prefecture, Xinjiang, China 46.173817, 84.434753 (approximate)[1]
Loading map...

Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology Start year
Unit 1 Construction[2] coal: unknown 660 ultra-supercritical 2026 (planned)[3]
Unit 2 Construction[2] coal: unknown 660 ultra-supercritical 2026 (planned)[3]

Table 3: Unit-level ownership and operator details

Unit name Owner Parent
Unit 1 Cpi Xinjiang Energy Chemical Group Co Ltd [100%] State Power Investment Corp Ltd [67.9%]; Xinjiang Investment Development (Group) Co Ltd [32.1%]
Unit 2 Cpi Xinjiang Energy Chemical Group Co Ltd [100%] State Power Investment Corp Ltd [67.9%]; Xinjiang Investment Development (Group) Co Ltd [32.1%]

Project-level coal details

  • Permit(s): 新发改批复〔2023〕150号[1]

Ownership Tree

This ownership tree is part of the Global Energy Ownership Tracker, a project of Global Energy Monitor.

Background

This proposed 2 × 660 MW ultra-supercritical coal-fired power station called for tender in November 2022.[4]

In December 2022, Tacheng District Development and Reform Commission announced that the first-place winner of the power project's bidding process was State Power Investment Corporation Xinjiang Energy and Chemical Co.[5]

In April 2022, bidding results for feasibility study[6] and social impact assessment were announced.[7]

In September 2023, the power station was permitted.[8]

Articles and Resources

References

  1. 1.0 1.1 "国家电投塔城2×66万千瓦煤电一体化项目 获得自治区发展改革委核准批复_经济动态_今日塔城_要闻动态_塔城地区行政公署". www.xjtc.gov.cn. 2023-09-19. Archived from the original on 2024-01-25. Retrieved 2023-11-03.
  2. 2.0 2.1 https://news.bjx.com.cn/html/20250826/1457688.shtml. {{cite web}}: Missing or empty |title= (help)
  3. 3.0 3.1 "2×660MW煤电一体化项目开工,国家电投的!-北极星火力发电网". news.bjx.com.cn. 2023-10-07. Archived from the original on 2024-01-25. Retrieved 2023-11-03.
  4. "塔城2×66万千瓦煤电一体化项目竞争性配置投资主体招标公告". 塔城地区行政公署网站. 2022-11-03. Retrieved 2023-02-06.
  5. 塔城2×66万千瓦煤电一体化项目竞争性配置投资主体(二次), People's Government of Tacheng, Dec. 10, 2023
  6. "塔城2×66万千瓦煤电一体化项目(火电部分)可行性研究报告编制结果公告". 知了标讯. 2023-04-29. Retrieved 2023-7-27. {{cite web}}: Check date values in: |access-date= (help)CS1 maint: url-status (link)
  7. "塔城2×66万千瓦煤电一体化项目(火电部分)社会稳定风险分析和评估报告编制结果公告". 知了标讯. 2023-04-29. Retrieved 2023-7-27. {{cite web}}: Check date values in: |access-date= (help)CS1 maint: url-status (link)
  8. 国家电投塔城2×66万千瓦煤电一体化项目 获得自治区发展改革委核准批复, xjtc.gov, September 19, 2023

Additional data

To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.